Trump v. Sierra Club
Cases that cite this one
17 later published cases cite this decision.
- Sierra Club v. Donald Trump (9th Cir. 2020)
- State of California v. Donald Trump (9th Cir. 2020)
- State of Washington v. Trump (District Court, W.D. Washington 2020)
- (PC) Harper v. Ayala (United States District Court for the Eastern District of California 2024)
- El Paso County, Texas v. Trump (District Court, W.D. Texas 2019)
- Rio Grande International Study Center v. Trump (District Court, District of Columbia 2020)
- Trump v. Sierra Club (Supreme Court of the United States 2020)
- Lorusso v. Duke Energy Company (District Court, W.D. North Carolina 2023)
- Committee on Ways and Means, United States House of Representatives v. TREA (D.C. Cir. 2022)
- Securities and Exchange Commission v. Chen (District Court, W.D. Washington 2022)
- State of Texas v. United States (5th Cir. 2021)
- Hesketh v. Total Renal Care Inc (District Court, W.D. Washington 2021)
- United States v. Maceo Strother (5th Cir. 2020)
- Sierra Club v. Donald Trump (9th Cir. 2020)
- Manzanita Band of the Kumeyaay Nation v. Wolf (District Court, District of Columbia 2020)
- (DP) Cowan v. Cates (United States District Court for the Eastern District of California 2020)
- County of San Francisco v. Uscis (9th Cir. 2019)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion
To warrant this stay, the Government must show not just (1) a reasonable probability that the Court will grant certiorari and (2) a fair prospect that the Court will reverse, but also (3) " 'a likelihood that irreparable harm will result from the denial of a stay.' "
Maryland v. King
,
Before granting a stay, however, we must still assess the competing claims of harm and balance the equities.
Barnes v. E-Systems, Inc. Group Hospital Medical & Surgical Ins. Plan
,
If we grant the stay, the Government may begin construction of a border barrier that would cause irreparable harm to the environment and to respondents, according to both respondents and the District Court. The Government's only response to this claim of irreparable harm is that, if respondents ultimately prevail, the border barrier may be taken down (with what funding, the Government does not say). But this is little comfort because it is not just the barrier, but the construction itself (and presumably its later destruction) that contributes to respondents' injury.
If we instead deny the stay, however, it is the Government that may be irreparably harmed. The Government has represented that, if it is unable to finalize the contracts by September 30, then the funds at issue will be returned to the Treasury and the injunction will have operated, in effect, as a final judgment. Respondents suggest a court could still award the Government relief after an appropriation lapses, though *2 that proposition has yet to be endorsed by this Court.
But there is a straightforward way to avoid harm to both the Government and respondents while allowing the litigation to proceed. Allowing the Government to finalize the contracts at issue, but not to begin construction, would alleviate the most pressing harm claimed by the Government without risking irreparable harm to respondents. Respondents do not suggest that they will be harmed by finalization of the contracts alone, and there is reason to believe they would not be. See,
e.g.
, 36 Opinion of Office of Legal Counsel 11 (2012) (noting that, because of the Anti-Deficiency Act, "the government [is] legally incapable of incurring a contractual obligation to pay more money than Congress had appropriated"), online at https://www.justice.gov/file/20596/download (as last visited July 26, 2019); see also
Leiter v. United States
,
I can therefore find no justification for granting the stay in full, as the majority does. I would grant the Government's application to stay the injunction only to the extent that the injunction prevents the Government from finalizing the contracts or taking other preparatory administrative action, but leave it in place insofar as it precludes the Government from disbursing those funds or beginning construction. I accordingly would grant the stay in part and deny it in part.