Global Fitness Holdings, LLC v. Federal Recovery Acceptance, Inc.
Global Fitness Holdings, LLC v. Federal Recovery Acceptance, Inc.
Opinion of the Court
MEMORANDUM DECISION AND ORDER GRANTING IN PART AND DENYING IN PART [III] DEFENDANTS’ MOTION FOR PARTIAL SUMMARY JUDGMENT ON PLAINTIFF’S BREACH OF CONTRACT AND BREACH OF THE IMPLIED COVENANT CLAIMS
This case is a dispute between a former owner of physical fitness clubs and one of its billing services providers regarding the parties’ obligations to each other at the
In the Global-L.A. Fitness Asset Purchase Agreement (“APA”), Global was to transfer customer data to L.A. Fitness, but Global claims Federal Recovery wrongfully withheld the data pending Global’s payment of termination fees to Federal Recovery.
Paramount filed several motions for partial summary judgment
TABLE OF CONTENTS
FACTUAL AND PROCEDURAL BACKGROUND................................1182
STATEMENT OF UNDISPUTED MATERIAL FACTS............................1183
A. Element 1: The Contracts........................................1183
B. Element 2: Global’s Performance Under the Contracts...............1184
C. Element 3: Paramount’s Performance Under the Contracts...........1185
D. Element 4: Damages............................................1186
II. Breach of the Implied Covenant of Good Faith and Fair Dealing...........1186
SUMMARY JUDGMENT STANDARD...........................................1186
APPLICABLE LAW.................................................. 1186
ANALYSIS....................................................................1187
I. Global’s Claim for Breach of Contract..................................1187
A. The 2008, 2009, and 2011 Contracts Between Global and FRAI
Were Ml Unambiguously Valid and Enforceable as a Matter of Law When Global Terminated the Contracts.......................1188
B. The Parties’ Rights and Obligations Under the Contracts.............1190
1. FRAI Had the Unambiguous Contractual Right to Possess, Maintain, and Process the Member Account Data Throughout the Duration of the 45-Day Termination Period.........................................1190
2. Global Had No Express Contractual Right to Demand Transfer of the Billing Information Prior to October 26, 2012, but Its Demands Did Not Constitute a Breach of the Contracts____1191
C. Paramount Has No Defense to Breach of Contract Based on Global’s Notice of Termination of a 2009 Contract via Email Because That Notice Was Sufficient under the Contracts, and Paramount Waived the Right to Notice of Termination of the Parties’ Remaining Contracts....................................1191
D. Both Parties Performed Under the Contracts Until Simultaneously Breaching them: FRAI Breached the Parties’ Contracts by Withholding Funds Beyond the 45-Day Termination Period While Global Breached the Parties’ Contracts by Failing to Pay Termination Fees..............................................1193
1. Global Breached the Contracts by Failing to Pay Contractually Required Termination or Exit Fees...........................1193
2. Paramount Breached the Contracts by Withholding Funds Beyon d the 45-Day Termination Period.......................1194
3. Neither Party’s Breach Excused the Other Party from Performing; Damages Remain to be Determined...............1195
E. Conclusion: Global and Paramount Are Both Liable for Breach of Contract; Damages and Offsets Remain to Be Determined at Trial.........................................................1195
II. Global’s Claim for Breach of the Implied Covenant of Good Faith and Fair Dealing......................................................1195
A. Global Cannot Maintain A Claim for Breach of the Implied Covenant Premised on Paramount’s Retention of the Member Account Data Where the Contracts Permitted FRAPs Retention..............................................1196
B. Global Cannot Maintain A Claim for Breach of the Implied Covenant Premised on Paramount’s Withholding of Funds Because the Undisputed Facts Show that Paramount Acted in an Effort to Perform the Contracts, Not in Bad Faith.....1197
ORDER 1197
At all relevant times prior to October 2012, Global owned and operated multiple fitness centers in multiple states.
In 2008, Global and FRAI executed eight location-specific contracts (the “2008 Contracts”):
In its Amended Complaint, Global contends that Paramount breached one or more of the Contracts, and the covenant of good faith and fair dealing implied therein, “by refusing and/or failing to provide the Member[] Account Data” and “by withholding the funds associated with the membership dues and it’s [sic ] servicing of the Member Accounts” (the “Withheld Funds”) following Global’s termination of the Contracts.
Paramount filed its Motion on Breach on August 4, 2014, both as it pertains to the Member Account Data and the Withheld Funds. On September 4, 2014, Global filed its opposition brief
STATEMENT OF UNDISPUTED MATERIAL FACTS
The below collection of undisputed material facts is distilled from the above listed filings. Paramount’s Motion on Breach provided a statement of facts
An email was sent to counsel with a summary set of undisputed facts on April 24, 2015.
I. Breach of Contract
A. Element 1: The Contracts
1. Global and FRAI executed multiple contracts with each other regarding services pertinent to the management of certain member accounts data.
2. Each of the Contracts between Global and FRAI contain, inter alia, the following notice provision: “One party may make any notice required under this Agreement by providing written notice sent certified mail, return receipt requested to the other party addressed to the last known address....”
4. Each of the Contracts further states that “[fjunds may be held during [the 45-day termination period] to offset returned payments or extra fees.”
B. Element 2: Global’s Performance Under the Contracts
5. On September 11, 2012, Keith Traw-ick, on behalf of Global, sent an email to Paramount stating:
Pursuant to the terms of our agreement with you, dated September 11, 2009, 45 day notice is hereby given for the termination of the Agreement. As we discussed, the clubs have been sold [via an Asset Purchase Agreement (“APA”) ] to [Fitness & Sports Clubs, LLC (“L.A. Fitness”) ] and at this time, we are unsure of the exact closing date. As specific information becomes available, we will let you know. It is our understanding that you guys will continue to provide service until the official closing date.40
6. Global sent the foregoing “notice” of termination via email,
7. Global’s first attempted written termination of any of the Contracts addresses only Contracts dated September 11, 2009.
8. Assuming Global’s September 11, 2012 email was a valid termination notice, pursuant to the Contracts’ 45-day notice requirement, the Contracts would have remained in full force and effect until at least October 26, 2012.
9. Paramount called the notice “official” in internal e-mails.
10. Upon receipt of the notice, Paramount began cooperating with Global fitness concerning the termination.
12. Paramount engaged in numerous emails and telephone calls with both Global Fitness and L.A. Fitness regarding the transfer of the Member Account Data for all thirty-six clubs.
13. Six days earlier, on September 5, 2012, Global and L.A. Fitness had executed the APA.
14. The first date that Global made a written request to Paramount to transfer all of the Member Account Data that it was processing for Global was October 3, 2012, via email.
15. On October 9, 2012, Global sent Paramount a letter demanding that all Member Account Data be transferred from Paramount to Global that same day.
16. Paramount ceased all servicing under the Contracts on October 25, 2012.
C. Element 3: Paramount’s Performance Under the Contracts
17. On October 11, 2012, Paramount provided to Global all of the data that Paramount had been processing under its contractual relationship with Global.
19. In its Amended Complaint, Global alleges, inter alia, that (a) Global “performed its obligations” under the Contracts and (b) Paramount breached one or more of the Contracts by (i) “refusing and/or failing to provide the Member[] Account Data” and/or (ii) “withholding the funds associated with the membership dues and it’s [sic] servicing of the Member Accounts.”
D. Element 4: Damages
20. For purposes of the instant Breach Motion only, Paramount does not challenge Global’s ability to proffer evidence in support of damages and thus there are no material facts necessary to this element for purposes of this Breach Motion.
II. Breach of the Implied Covenant of Good Faith and Fair Dealing
21. Preceding paragraphs 1 through 20 are incorporated by reference as if fully set forth herein anew as all such undisputed material facts pertain equally to Global’s breach of the implied covenant of good faith and fair dealing claim.
SUMMARY JUDGMENT STANDARD
Summary judgment is proper “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
APPLICABLE LAW
The parties agree that, pursuant to the express terms
ANALYSIS
In its Amended Complaint, Global alleges, inter alia, that Global “performed its obligations” under the Contracts and that Paramount breached one or more of the Contracts and the covenant of good faith and fair dealing implied in the Contracts by “refusing and/or failing to provide the Member[] Account Data” and “withholding the funds associated with the membership dues and it’s [sic] servicing of the Member Accounts.”
I. Global’s Claim for Breach of Contract
To sustain a claim for breach of contract under Utah law, Global bears the burden to prove the following elements: (1) a contract; (2) Global’s performance under the contract; (3) breach of the contract by FRAI; and (4) damages.
Global has argued that only one of the 2009 Contracts controls the parties’ relationship, .that Global’s performance was sufficient under the Contracts to state a claim for breach of contract, that Paramount breached the Contracts by not transferring the Member Account data (although that ground for breach was voluntarily dismissed while this motion was pending), and by withholding funds. As discussed more fully below, (A) the 2008, 2009, and 2011 Contracts were all valid and enforceable at the time of Global’s notice of termination; (B) Paramount had the contractual right to retain the Member Account Data, and Global did not have the right to demand the transfer of that data, although Global’s demands did not constitute breaches of the Contracts; (C) Paramount has no defense to breach of contract based on the form of Global’s notice of termination; (D) both parties performed the Contracts sufficiently to state claims for breach, but both parties’ breached the Contracts; and (E) the parties’ liability
A. The 2008, 2009, and 2011 Contracts Between Global and FRAI Were All Unambiguously Valid and Enforceable as a Matter of Law When Global Terminated the Contracts.
Global and FRAI executed twelve Contracts regarding services pertinent to the management of the Member Account Data: eight location-specific contracts in 2008, two contracts that do not identify specific locations in 2009, and two location-specific contracts in 2011.
For the reasons discussed below, the presumption that one of the Contracts entirely supersedes any of the others is incorrect, and all of the Contracts were valid and in force at the time Global gave notice of termination. This analysis is facial, based solely on the language of the Contracts, finding no ambiguity that would allow the review of parol evidence. Neither Paramount nor Global has ever asserted or argued that any of the Contracts, or any of the provisions thereof, are ambiguous, facially or otherwise.
In the Existing Locations Agreement dated September 11, 2009,
COMPANY engages CONTRACTOR for a fee determined as 5.8% of COMPANY’S Visa/MC transactions; 5.8% of non-bank cards (Amex, Disc, etc.), 3.8% on ACH receipts, 2% of client received payments/paid to client, and 6% of mail in payments excluding cash down payments and cash sales. This pricing applies to all locations currently with Paramount Acceptance until all conversions to Paramount Acceptance are completed as of December 1, 2009. As of December 1, 2009, all locations subject to this agreement shall be subject to the pricing set forth in the “Engagement and Fee” section of the “New Location” agreement,74
There is no facial ambiguity in the foregoing provision. On the contrary, it explicitly specifies that (1) the “pricing” provisions apply to “all locations currently with Paramount” and (2) as of December 1, 2009, all locations subject to the Existing Locations Contract, including but not limited to the 2008 Contracts, would then be subject to the pricing set forth in the Engagement and Fee section of the New Location Agreement.
The parties’ location-specific 2011 Contracts continued to govern the parties’ contractual relationship for the Buckhead and Dublin locations, respectively, prior to termination.
Finally, the remaining provisions of the Contracts, to the extent they are material to this Order, are facially unambiguous. Global has never asserted or argued ambiguity with respect to any of the parties’ Contracts, either in whole or in part.
1. FRAI Had the Unambiguous Contractual Right to Possess, Maintain, and Process the Member Account Data Throughout the Duration of the 45-Day Termination Period.
In its Amended Complaint, Global alleges that Global “performed its obligations” under the Contracts and that Paramount breached one or more of the Contracts and the covenant of good faith and fair dealing implied in the Contracts by “refusing and/or failing to provide the Member! ] Account Data.”
Paramount filed its Motion on August 4, 2014, seeking summary judgment on Global’s breach of contract and breach of the implied covenant claims as it pertains to, among other things, transfer of the Member Account Data. On September 4, 2014, Global filed a motion to voluntarily dismiss, with prejudice, its breach of contract claim as it relates to the transfer of the Member Account Data.
Nevertheless, possession of the Member Account Data, including the Billing Information, was fundamental to Paramount’s performance of the Contracts. .Although the Contracts are silent as possession, the primary purpose of the Contracts would be wholly frustrated if they did not grant to Paramount the necessary right and obligation to possess this data. Therefore, because the Contracts allow the parties to “terminate this Agreement at any time for any reason upon ¿5 day prior written notice,”
This contract construction applies to many of the issues and motions. Moreover, Global’s Amended Complaint repeatedly recites allegations consistent with it.
2. Global Had No Express Contractual Right to Demand Transfer of the Billing Information Prior to October 26, 2012, but Its Demands Did Not Constitute a Breach of the Contracts
On September 11, 2012, Keith Trawick, on behalf of Global, sent an email to Paramount stating:
Pursuant to the terms of our agreement with you, dated September 11, 2009, 45 day notice is hereby given for the termination of the Agreement. As we discussed, the clubs have been sold [via the APA] to L.A. Fitness and at this time, we are unsure of the exact closing date. As specific information becomes available, we will let you know. It is our understanding that you guys will continue to provide service until the official closing date.96
Assuming Global’s September 11, 2012 email was a valid termination notice, pursuant to the Contracts’ 45-day notice requirement, the Contracts would have remained in full force and effect until at least October 26, 2012.
Notwithstanding the reality that Global had no contractual right to demand delivery of the Member Account Data until after October 26, 2012, on October 3, 2012, Global made a written request to Paramount demanding that all of the Member Account Data that Paramount was processing for Global be transferred on to Global October 5, 2012. When transfer did not occur, on October 9, 2012, Global again demanded that all of the Member Account Data be transferred from Paramount to Global with a deadline of that same day. Under an injunctive order on October 11, 2012, Paramount provided to Global all of the Member Account Data that Paramount had been processing under the Contracts, 15 days before the contractual termination period would have expired.
Consistent with the above construction of the Contracts, Global had no express contractual right to demand transfer of the Member Account Data and Billing Information. However,' although Global could not unilaterally end Paramount’s possession, there is no contractual prohibition to prevent Global from requesting that Paramount do something beyond the rights and obligations embodied in the Contracts. Therefore, Global’s acts of requesting or demanding the early transfer do not constitute a breach of the Contracts.
Equally, Paramount was not obligated to transfer the Member Account Data on October 5, October 9, or at any time prior to October 26, 2012. Put differently, FRAI was entitled to exercise its contractual rights to retain the Member Account Data until October 26, 2012 and, therefore, FRAI did not breach the parties’ Contracts by withholding the Member Account Data until October 11, 2012. Indeed, such conduct is within FRAI’s express and unambiguous contractual rights.
C. Paramount Has No Defense to Breach of Contract Based on Global’s Notice of Termination of a 2009 Contract via Email Because That Notice Was Sufficient under the Contracts, and Paramount Waived the Right to Notice of Termination of the Parties’ Remaining Contracts.
Paramount’s Motion on Breach states, in defense to Global’s breach of contract and breach of the implied covenant claims, that Global never gave proper
As mentioned above, each of the Contracts between Global and FRAI contains the following Notice provision: “One party may make any notice required under this Agreement by providing written notice sent certified mail, return receipt requested to the other party addressed to the last known address....”
Here, it is undisputed that, on September 11, 2012, Keith Trawick, on behalf of Global, sent an Email to Paramount giving “notice” of termination.
Beyond that, Paramount waived any requirement that the notice be “certified mail, return receipt requested to the other party addressed to the last known address.” Waiver is defined as “the intentional relinquishment of a known right.”
It is undisputed that Global’s termination notice addresses only the a contract dated September 11, 2009, not the 2008 or 2011 Contracts. Nevertheless, Paramount knew of the Notice provision within the Contracts, knew that it had received notice in the form of an Email limited to one of the 2009 Contracts but did nothing subsequent to the September 11, 2012 notice that was inconsistent with Paramount’s recognition of a termination of all the Contracts.
There are many indicia of Paramount’s knowing intention to relinquish the right of proper notice under the Contracts. Upon receipt of Global’s notice, Paramount
No one claims the Contracts survived beyond 45 days following Global’s September 11, 2012 notice, and Paramount was not prejudiced in any way by receiving the notice of termination by email. Thus, even if Global might otherwise have breached the parties Contracts by failing to specifically refer to the 2008 and 2011 Contracts in the September 11, 2012 email, that breach was waived by Paramount through its conduct.
D. Both Parties Performed Under the Contracts Until Simultaneously Breaching them: FRAI Breached the Parties’ Contracts by Withholding Funds Beyond the 45-Day Termination Period While Global Breached the Parties’ Contracts by Failing to Pay Termination Fees.
In its Amended Complaint, Global alleged that Global “performed its obligations” under the Contracts and that Paramount breached one or more of the Contracts and/or the covenant of good faith and fair dealing implied in the Contracts by “withholding the funds associated with the membership dues and it’s [sic] servicing of the Member Accounts.”
1. Global Breached the Contracts by Failing to Pay Contractually Required Termination or Exit Fees.
It is undisputed that each of the Contracts states that “[f|unds may be held during [the 45-day termination period] to offset returned payments or extra fees.”
Similarly, the Term provisions of the 2009 and 2011 Contracts each state that if Global “terminates this agreement [then FRAI] shall be entitled to its costs of providing additional information or reports for the transfer of data to [Global] or its agent, such costs not to exceed $2500.”
Finally, as matter of law, the “extra fees” referenced in the Term provisions of each of the parties’ Contracts refers specifically to the “Extra Payment” provisions of the Contracts.
2. Paramount Breached the Contracts by Withholding Funds Beyond the 45-Day Termination Period.
It is undisputed that on October 11, 2012. Paramount transferred the Member Account Data to Global. At that time, the parties had not resolved issues of setting the reserve amount or determining the amount of termination fees and other payments that Global needed to pay upon termination.
While the total amount of Withheld Funds that Paramount owes to Global remains to be determined at trial, Global is unambiguously contractually entitled to the owed funds as a matter of law, although they may be offset by chargebacks,
3. Neither Party’s Breach Excused the Other Party from Performing; Damages Remain to be Determined.
In order for either party to sue-. ceed on a claim for breach of contract, it must show, among the other elements of breach of contract, that it performed under the Contracts.
Accordingly, Global’s breach of contract claim as to the Withheld Funds survives Paramount’s Motion on Breach.
E. Conclusion: Global and Paramount Are Both Liable for Breach of Contract; Damages and Offsets Remain to Be Determined at Trial.
Under the above conclusions of law, specifically that Global and FRAI both breached the parties’ Contracts and that neither party’s breach excused the other party from performing, Global’s breach of contract claim survives Paramount’s Motion on Breach. FRAI’s liability for breach of contract has been conclusively decided in this order. However, the amount of damages owed to Global for FRAI’s breach of contract remains to be determined at trial. Moreover, such damages, if any, must be determined alongside Paramount’s damages for Global’s breach of the Contracts in failing to pay required exit and termination fees. Damages will be tried before a jury as presently scheduled. Once damages are fully adjudicated at trial, the amounts will be offset, and motions will then be entertained regarding prevailing party status and an award of attorneys’ fees, if any.
II. Global’s Claim for Breach of the Implied Covenant of Good Faith and Fair Dealing
A covenant of good faith and fair dealing is implied in every contract.
For the reasons stated more fully below, summary judgment is GRANTED to Paramount on Global’s claim for breach of the covenant of good faith and fair dealing because (A) the Contracts permitted Paramount’s retention of the Member Account Data, and (B) no facts show that Paramount acted in bad faith in retaining the Withheld Funds.
A. Global Cannot Maintain A Claim for Breach of the Implied Covenant Premised on Paramount’s Retention of the Member Account Data Where the Contracts Permitted FRAI’s Retention.
' “The reach of the implied covenant of good faith and fair dealing extends no further than the purposes and express terms of the contract.”
Notwithstanding Global’s voluntary dismissal
Accordingly, Paramount’s Motion is GRANTED with respect to Global’s breach of the implied covenant claim premised on Paramount’s withholding of the Member Account Data.
B. Global Cannot Maintain A Claim for Breach of the Implied Covenant Premised on Paramount’s Withholding of Funds Because the Undisputed Facts Show that Paramount Acted in an Effort to Perform the Contracts, Not in Bad Faith.
As stated above, where a party to a contract takes action consistent with the contract, there is no breach of the implied covenant of good faith and fair dealing.
None of the facts Global says support bad faith are included in the undisputed record, but they still do not show bad faith. Global focuses on Paramount’s internal communication, purportedly showing that Paramount was concerned that cooperating with Global would result in Global not paying all of its termination and exit fees, etc. This is not evidence of bad faith: this is evidence of Paramount’s concern that the Contracts be performed. Paramount’s desire to see that its contractual rights are protected and that Global’s contractual obligations are met cannot constitute bad faith. Rather, it is evidence of a good faith effort to perform the Contracts. Both parties have stated that the Contracts are “not great,”
Accordingly, Paramount’s Motion is GRANTED with respect to Global’s breach of the implied covenant claim premised on Paramount’s withholding of funds to which Global may be entitled.
ORDER
IT IS HEREBY ORDERED that Paramount’s Defendants’ Motion RE Breach of Contract and the Implied Covenant
. Global Fitness Holding, LLC's Amended Complaint (“Amended Complaint”) ¶¶ 38-45, docket no. 71, filed March 19, 2014.
. Id. ¶¶ 46-52.
. Id. ¶¶ 53-60.
. Id. ¶¶ 61-66.
. Id. ¶¶ 67-73.
. See generally id.
. Amended Complaint ¶¶ 64-65.
. Id. ¶¶ 61-63, 65-66.
. Defendants' Motion for Partial Summary Judgment on Global's Promissory Estoppel Claim, docket no. 106, filed Aug. 4, 2014; Defendants’ Motion for Partial Summary Judgment RE Plaintiff's Conversion Claim and Supporting Memorandum, docket no. 108, filed Aug. 4, 2014; Defendants’ Motion for Partial Summary Judgment RE: Global’s Breach of Contract and Breach of the Implied Covenant Claims and Memorandum in Support Thereof ("Breach Motion”), docket no. 111, filed Aug. 4, 2014; Defendants’ Motion for Partial Summary Judgment on Global’s Tortious Interference Claim, docket no. 120, filed under seal Aug. 4, 2014; and Defendants' Motion for Partial Summary Judgment RE: Global’s Tortious Interference Claim for Lack of Causation and Memorandum in Support Thereof, docket no. 121, filed under seal Aug. 4, 2014.
. Global Fitness, LLC’s Motion for Voluntary Dismissal of its Breach of Contract Claim Against Federal Recovery Acceptance, Inc. as it Relates to the Transfer of Data, docket no. 132, filed Sept. 4, 2014 ("Motion for Voluntary Dismissal”).
. Defendants’ Motion for Partial Summary Judgment RE: Global’s Breach of Contract and Breach of the Implied Covenant Claims ("Paramount’s Motion on Breach”), docket no. 111, filed Aug. 4, 2014.
. Amended Complaint ¶ 7.
. Defendants' Amended Answer to Plaintiff's Amended Complaint and Counterclaim ("Counterclaim”) ¶ 19, docket no. 85, filed April 22, 2014. See also Paramount contracts ("Contracts”), attached as Exhibit A to Paramount's Motion on Breach, docket no. 111-2, filed on Aug. 4, 2014, also attached to the Declaration of David L. Mortensen in Support of Global Fitness Holding, LLC’s Memorandum in Opposition to Federal Recovery Services Inc.’s Motion for Partial Summary Judgment RE: Global's Breach of Contract and Breach of the Implied Covenant Claims ("Global's Exhibits on Breach”) as Exhibit F, docket no. 146-6; Exhibit H, docket no. 146-8; Exhibit J, docket no. 146-10; and Exhibit K, docket no. 146-11, filed Sep. 4, 2014.
. Amended Complaint ¶ 9.
. Counterclaim ¶ 19; see also Contracts (dated 2008).
. Amended Complaint ¶ 13; Counterclaim ¶ 23; see also, Contracts (dated 2009).
. Counterclaim ¶ 24; see also Contracts (dated 2011).
. Amended Complaint ¶¶ 14-16; see also Contracts.
. Amended Complaint ¶¶ 61-66, at Count IV, and ¶¶ 67-73, at Count V.
. Global Fitness Holdings, LLC's Memorandum in Opposition to Defendants' Motion for Partial Summary Judgment RE: Global’s Breach of Contract and Breach of the Implied Covenant Claims ("Global’s Opposition on Breach”), docket no. 143, filed Sep. 4, 2014.
. Global Fitness Holdings, LLC’s Motion for Voluntary Dismissal of its Breach of Contract Claim Against Federal Recovery Acceptance, Inc. As It Relates to the Transfer of Data ("Global's Motion to Voluntarily Dismiss Breach on Data Transfers”), docket no. 132, filed Sept. 4, 2014.
. Defendant's Memorandum in Response to Global Fitness Holdings, LLC's Motion for Voluntary Dismissal of its Breach of Contract Claim Against Federal Recovery Acceptance, Inc. as it Relates to the Transfer of Data (“Paramount’s Opposition to Voluntary Dismissal”), docket no. 167, filed Sept. 22, 2014.
. Memorandum Decision and Order Granting Plaintiff’s Motion for Voluntary Dismissal with Prejudice, docket no. 244, filed March 30, 2015.
. Reply Memorandum in Support of Defendants’ Motion for Partial Summary Judgment RE: Global’s Breach of Contract and Breach of the Implied Covenant Claims (“Paramount's Reply on Breach”), docket no. 168, filed Sep. 22, 2014.
. Paramount’s Motion on Breach at 4-10.
. Global's Opposition on Breach at 13-18, 20.
. Id. at 20-23.
. Global’s Exhibits on Breach, docket no. 146, filed Sep. 4, 2014.
. Paramount’s Reply on Breach at iv-xxx.
. Id. at xxx-xliii.
. Email from Judge Nuffer’s Chambers to counsel (Apr. 24, 2015), lodged as docket no. 272 on Aug. 31, 2015.
. Docket no. 247 (Minute Order); Transcript 4/27/15 38:22-51:12, docket no. 249, filed May 5, 2015.
. Id.
. See Contracts.
. Id. at section entitled "Notice”.
. Id. at section entitled "Term”.
. Id.; see also Deposition of Global dated May 1, 2014 (deponent: Coby DeVary) ("DeVary Deposition”) at 12:24-13:24, excerpts attached as Exhibit B to Paramount’s Motion on Breach, docket no. 111-3, filed under seal in docket no. 119-1, filed on Aug. 4, 2014, other excerpts attached as Exhibit R to Global's Exhibits on Breach, docket no. 146-18, filed Sep. 4, 2014.
. Contracts at section entitled "Term”.
. See id.
. See Sept. 11, 2012 email from K. Trawick to S. Nelson, et al. ("Sept. 11, 2012 Trawick Email”), attached as Exhibit C to Paramount’s Motion on Breach, docket no. 111-4, filed Aug. 4, 2014, also attached as Exhibit T to Global's Exhibits on Breach, docket no. 146-20, filed Sep. 4, 2014.
. See Sept. 11, 2012 Trawick Email.
. See Contracts at section entitled "Notice”.
. See Sept. 11, 2012 Trawick Email.
. Compare Contracts at section entitled "Term” with Sept. 11, 2012 Trawick Email.
. See Email from Glen Bendixen to Ren Rice and Todd C. Rasmussen dated Sep. 11, 2012 (“Sep. 11, 2012 Bendixen Email”), attached as Exhibit BB to Global's Exhibits on Breach, docket no. 146-28, filed Sep. 4, 2014 ("This is the official notice.”).
. Counterclaim ¶¶ 46-47, at 25-26; see also Declaration of Todd Rasmussen ¶ 5, attached as Exhibit CC to Global's Exhibits on Breach, docket no. 146-22, filed Sep. 4, 2014.
. Counterclaim ¶¶ 46-47, at 25-26.
. Id.
. DeVary Deposition at 68:3-9.
. See Oct. 3, 2012 email from K. Trawick to S. Nelson, et al. ("Oct. 3, 2012 Trawick Email”), attached as Exhibit D to Paramount's Motion on Breach, docket no. 111-5, filed Aug. 4, 2014, also attached as Exhibit V. to Global’s Exhibits on Breach, docket no. 146-22, filed Sep. 4, 2014 (“We are asking for a full cut of the data on Friday.... Please confirm. Also, we will need an additional (updated) cut of the same data on the date of the actual close, which we anticipate will be next week.”); see also Amended Complaint ¶28 ("On October 3, 2012, Global[] requested that Paramount transfer the Billing Data or final cut back to Global ....”); see also Oct. 9, 2012 correspondence from K. Trawick to G. Bendixen ("Oct. 9, 2012 Trawick Letter”), attached as Exhibit E to Paramount’s Motion on Breach, docket no. 111-6, filed Aug. 4, 2014, also attached as Exhibit QQ to Global’s Exhibits on Breach, docket no. 146-43, filed Sep. 4, 2014 (referencing Global’s initial request on October 3, 2012).
. See Oct. 9, 2012 Trawick Letter ("This data must be made available today, October 9th”).
. Deposition of Glen Bendixen ("Bendixen Depo.”), at 219:19-220:4, attached as Exhibit R to Declaration of David L. Mortensen in Support of Global Fitness Holding, LLC’s Memorandum in Opposition to Federal Recovery Services Inc.’s Motion for Partial Summary Judgment for Plaintiff’s Conversion Claim, docket no. 142-18, filed Sep. 4, 2014 ("[T]here must have been a point in time where, when we were calculating making us whole for the remainder part of the month, that the estimate was $120,000. But because the sale didn’t complete until the [25th] of October, we continued to service the accounts and — and continued to collect the fees during that period of time. So — ... During that entire period, we would have collected our normal fees.”)
. See Oct. 11, 2012 Forwarded Email from K. Trawick to S. Horton-Salcedo, et al. ("Oct. 11 Forwarded Email”), attached as Exhibit F to Paramount’s Motion on Breach, docket no. 111-7, filed under seal in docket no. 119-2, filed Aug. 4, 2014, also attached as Exhibit DD to Plaintiff’s Exhibits in Opposition to Motion RE Breach, docket no. 146-30, filed Sep. 4, 2014 ("The PAC data is available on your FTP site.”); see also Deposition of L.A. Fitness dated Apr. 22, 2014 (deponent: Kathy Poison) (“Poison Depo.”) at 189:9-190:14, excerpts attached as Exhibit G to Paramount’s Motion on Breach, docket no. 111-8, filed under seal in docket no. 119-3, filed Aug. 4, 2014 (acknowledging that Paramount transferred the Member Account Data on October 11, 2012); Deposition of Keith Trawick dated Mar. 18, 2014 ("Trawick Depo.”) at 262:19-23, excerpts attached as Exhibit H to Paramount’s Motion on Breach, docket no. 111-9, filed Aug. 4, 2014 (acknowledging that Paramount transferred the Member Account Data on October 11, 2012).
. See various emails between the parties and their counsel ranging from October 5, 2012 to October 10, 2012 showing the exit terms were not resolved ("Exit Term Emails”), collectively attached as Exhibit K to Paramount’s Motion on Breach, docket no. 111-12, filed Aug. 4, 2014; also attached to Global’s Exhibits on Breach as Exhibit X, docket no. 146-24; Exhibit Y, docket no. 146-25; and Exhibit NN, docket no. 146-40, filed Sep. 4, 2014.
. Amended Complaint ¶¶ 61-66, at Count IV, and ¶¶ 67-73, at Count V.
. Fed.R.Civ.P. 56(a).
. Universal Money Ctrs., Inc. v. Am. Tel. & Tel. Co., 22 F.3d 1527, 1529 (10th Cir. 1994) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986)) (internal quotation marks omitted).
. Universal, 22 F.3d at 1529.
. Id. (quoting Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986)).
. Id. (quoting Anderson, 477 U.S. at 256, 106 S.Ct. 2505 (internal quotation marks omitted)) (both emphases in original).
. Id. (quoting Anderson, 477 U.S. at 252, 106 S.Ct. 2505 (internal quotation marks omitted)).
. See Contracts at section entitled "Enforcement”.
.See Paramount's Motion on Breach at 4, 9-10 (citing the legal elements under Utah law) and Global’s Opposition on Breach at 13, 19-20, 23 (same). See also Global's Motion for Partial Summary Judgment on Paramount’s Fraud and Negligent Misrepresentation Counterclaims at 14 n. 42, docket no. 66, filed Mar. 4, 2014 (“the various contracts between the [parties] contain a choice of law provision favoring Utah law ..., [t]hus, there is no dispute that all contractual claims shall be governed by Utah law.”).
. See Amended Complaint ¶¶ 61-66, at Count IV, and ¶¶ 67-73, at Count V.
. Bair v. Axiom Design, L.L.C., 20 P.3d 388, 392 (Utah 2001).
. Christiansen v. Farmers Ins. Exch., 116 P.3d 259, 261 (Utah 2005).
. Fairbourn Commercial, Inc. v. Am. Hous. Partners, Inc., 94 P.3d 292, 295 (Utah 2004).
. Id.
. See Contracts.
. See Amended Complaint ¶¶ 61-66, at Count IV, and ¶¶ 67-73, at Count V.
. See, e.g., Global's Opposition on Breach at 5-8.
. See id. See also Global’s Motion to Exclude any Testimony of Thomas Klc Regarding His Legal Interpretation of the Contracts, docket no. 212, filed Jan. 16, 2015 at 2 (The crux of Global and Paramount's breach of contract dispute is "whether one set of terms governs all of the clubs [or whether multiple contracts] ... govern contemporaneously. Global Fitness believes that this is a legal question of contract interpretation to be decided by the Court without parol evidence." (emphasis added)).
. See Contract (dated September 11, 2009), the Existing Locations Agreement.
. Id. at section entitled "Engagement and Fee” (emphasis added).
. Id.
. Id.
. Id.
. Id.
. See Contracts (dated 2009).
. See Contracts dated 2008 at section entitled ''Term."
. See id. (dated 2011).
. Plaintiff's Opposition RE Breach of Contract and the Implied Covenant, docket no. 143, filed Sep. 4, 2014.
. See Contracts at section entitled "Term”.
. Id.
. See id. at section entitled "Notice”.
. See id. at section entitled "Term”.
. Id.; see also id. at section entitled "Extra Payment”.
. See Amended Complaint ¶¶ 61-66, at Count IV, and ¶¶ 67-73, at Count V.
. See generally Global’s Motion to Voluntarily Dismiss Breach on Data Transfers (seeking to voluntarily dismiss, with prejudice, only Paragraph 64 of Count IV of Global’s Amended Complaint, i.e., "Paramount breached the Agreement by refusing and/or failing to provide the Member! ] Accounts] Data”).
. See generally Paramount’s Opposition to Voluntary Dismissal.
. Memorandum Decision and Order Granting Plaintiff's Motion for Voluntary Dismissal with Prejudice, docket no. 244, filed March 30, 2015.
. Id.
. See Contracts at section entitled "Term” (emphasis added).
. Id.; id. at section entitled "Contractor’s Duties”; Declaration of Todd Rasmussen in Support of Defendants' Memorandum in Opposition to Global Fitness Holdings, LLC’s Motion for Partial Summary Judgment, docket no. 168-2, filed Sept. 22, 2014, ¶¶ 6-7.
. See Amended Complaint ¶¶ 39, 48, 50, 54, 62, 64, 68, 70, 72, and 75.
. Sept. 11, 2012 Trawick Email.
. Paramount’s Motion on Breach at 15-16.
. Id.
. See Contracts at section entitled "Notice” (emphasis added).
. See Sept. 11, 2012 Trawick Email.
. See Contracts at section entitled "Notice” (emphasis added).
. Soter’s, Inc. v. Deseret Fed. Sav. & Loan Ass’n, 857 P.2d 935, 939-40 (Utah 1993).
. Meadow Valley Contrs., Inc. v. State DOT, 266 P.3d 671, 682-83 (Utah 2011).
. Soter’s, 857 P.2d at 940-42.
. See Sept. 11, 2012 Bendixen Email.
. Counterclaim ¶¶ 46-42, at 25-26.
. See Amended Complaint ¶¶ 61-66, at Count IV, and ¶¶ 67-73, at Count V.
. See Paramount’s Motion on Breach at 19-20.
. Id.
. Id.
. See Contracts at section entitled "Term”.
. Id.
. 2008 Contracts at section entitled "Term”.
. Id.
. 2009 Contracts and 2011 Contracts at sections entitled "Term”.
. Id.
. Contracts at sections entitled "Term” and "Extra Payment”.
. See Exit Term Emails.
. Contracts at sections entitled "Term” and "Extra Payment”.
. See Exit Term Emails.
. See Contracts at section entitled “Term”.
. See Bair v. Axiom Design, L.L.C., 20 P.3d 388, 392 (Utah 2001).
. Contracts at sections entitled "Term” and “Extra Payment”.
. St. Benedict’s Dev. Co. v. St. Benedict’s Hosp., 811 P.2d 194, 199 (Utah 1991) (citing Bastian v. Cedar Hills Investment & Land Co., 632 P.2d 818, 821 (Utah 1981)).
. Id.
. Olympus Hills Shopping Ctr. v. Smith’s Food & Drug Ctrs., 889 P.2d 445, 450 (Utah Ct.App. 1994) (citations omitted); see Brehany v. Nordstrom, Inc., 812 P.2d 49, 55 (Utah 1991) (contract rights should be exercised in good faith); Res. Mgmt. Co. v. Weston Ranch and Livestock Co., 706 P.2d 1028, 1037 (Utah
. Simplot v. Chevron Pipeline Co., 563 F.3d 1102, 1113 (10th Cir. 2009) (deciding a breach of the covenant based on Utah law).
. Berube v. Fashion Centre, 771 P.2d 1033, 1046 (Utah 1989).
. Brown v. Moore, 973 P.2d 950, 954 (Utah 1998) (citing St. Benedict’s Dev. Co., 811 P.2d at 200) ("In determining whether a party has breached the covenant of good faith and fair dealing, we are not limited to an examination of the express contractual provisions; we will also consider the course of dealings between the parties.")
. Bichler v. DEI Sys., Inc., 220 P.3d 1203, 1207-08 (Utah 2009).
. Brown v. Moore, 973 P.2d 950, 954 (Utah 1998) (internal citations and quotation marks omitted).
. See Asael Farr & Sons Co. v. Truck Ins. Exch., 193 P.3d 650, 662 (Utah Ct.App. 2008).
. See U.S.A. United Staffing Alliance v. Workers’ Compensation Fund, 213 P.3d 20, 24-26 (Utah Ct.App. 2009).
. See Global’s Motion to Voluntarily Dismiss Breach on Data Transfers; Memorandum Decision and Order Granting Plaintiff’s Motion for Voluntary Dismissal with Prejudice, docket no. 244, filed March 30, 2015.
. See Amended Complaint ¶¶ 67-73, at Count V.
. See id.; id. ¶¶ 61-66 at Count IV.
. See U.S.A. United Staffing Alliance v. Workers’ Compensation Fund, 213 P.3d 20, 24-26 (Utah Ct.App. 2009).
. See, e.g., Transcript 4/27/15 66:1-2, docket no. 249, filed May 5, 2015.
. Docket no. Ill, filed Aug. 4, 2014.
Reference
- Full Case Name
- GLOBAL FITNESS HOLDINGS, LLC v. FEDERAL RECOVERY ACCEPTANCE, INC. and Federal Recovery Services, Inc.
- Cited By
- 8 cases
- Status
- Published