Arkoosh v. Sorrenson
Arkoosh v. Sorrenson
Opinion of the Court
This action was commenced by the plaintiffs, in the District Court of Salt Lake County to recover a certain carload of ore which, it is alleged in the complaint, the defendant, Sorren-son, had wrongfully removed from certain mining claims, and which ore it was alleged belonged to the plaintiffs. The defendant denied the plaintiff’s right to or ownership of the ore sued for, and claimed to be the owner thereof by virtue of a certain contract entered into between him and the plaintiffs, which contract he set forth in full as a part of his answer. The defendant also set up a counterclaim in which he claimed damages for the alleged breach of the contract aforesaid by terminating defendant’s rights thereunder and by excluding him from the mining claims mentioned in said contract, and therefore preventing him from ultimately acquiring ownership of the forty per cent, interest in the mining claims mentioned in the contract. At the hearing the court sustained plaitiffs’ motion for a nonsuit against defendant’s counterclaim, and after all the evidence was'submitted by. both sides it, upon plaintiffs’ motion, also directed the jury to return a verdict in favor of plaintiffs to the effect that “said plaintiffs are entitled to the car of ore in dispute, and to the
The principal difference between the parties arises out of the terms of the contract pleaded by the defendant. Omitting the formal or introductory parts, and those portions not material, the contract reads as follows:
“Now, therefore, it is agreed by the respective parties hereto for and in consideration of the premises herein contained as follows: The said parties of the first part agree to transfer to the said part of the second part at the end of one year from the date hereof, and upon the completion of all of the work and labor to be performed by the
"It is further agreed that the said party of the second part shall have the right to dispose of all of the ore encountered and excavated within the four lines of said tunnel, but party of the second part shall not be allowed to stope any veins, lodes, or ledges without the agreement in writing of the parties of the first part.
“It is further provided that the said party of the second
“And it is further agreed between the parties hereto that, if the said party of the second part shall fail to perform the work and labor within the time and in the manner herein-before specified, or shall fail to comply with the terms of this contract in any manner, then the same shall immediately cease and become null and void, and all the rights of the party of the second part hereunder shall terminate.” (Italics ours.)
The plaintiffs at the trial contended: (1) That the defendant had failed to comply with the terms of the contract aforesaid, and therefore they had elected to and had terminated the same, and the defendant thereby had lost all rights under it; and (2) that the ore in question had been mined and taken from a portion of the mining claims from which the defendant had no right to take or remove ore. The plaintiffs at the trial proved that the defendant did not ‘ ‘ have employed in the construction of said tunnel at least four men per day working twenty (20) days per calendar month.” The defendant conceded at the trial, and conceded, through his counsel, at the hearing, that during some of the time he had less than four men working in said tunnel. Indeed, he admitted that during part of th§ time he had only one man working therein. He contends, however, that eight hours constitute a shift; that a shift constitutes a day; and that when the eight-hour shifts that were worked in the tunnel are all added together he did, in fact, work what he calls “twenty shifts” in each calendar month. In arriving at that result he, however, is compelled to have one man work more than a shift each day. In that connection he contends that some days one man worked more than eight hours, and thus worked more than one shift. He therefore insists that he is entitled to add all of the shifts together, and if by doing so he,,did work eighty shifts in each
Defendant’s counsel, however, vigorously argues that the court erred in directing a verdict for the plaintiffs for the ore in question. As appears from the contract, the defendant was entitled to all the ore he “encountered and excavated
We do not see how the trial court could escape from the foregoing conclusions, and hence it did not err in directing a verdict in favor of the plaintiffs for the ore in question. If the matter, however, be viewed in the light of the evidence, we cannot see what could have been submitted to the jury, and for that reason the result would still have been the same.
In view that plaintiffs were entitled to recover the ore in question, as a matter of law, for the reasons stated, the other errors complained of by the defendant, whichever way decided, could not affect or change the result, and hence we need not consider them.
The judgment is therefore affirmed, with costs to the plaintiffs.
070rehearing
A petition for a rehearing is filed in which counsel for appellant insists that we have seriously erred in our conclusions. He says:
“This court is wholly in error in the statement contained in its opinion that the car of ore in question ‘was not taken from any one of the smaller tunnels.’ Positive testimony of two witnesses produced by appellant upon the trial is that-said ore was taken from another and smaller tunnel, the ore being encountered after driving a 4x5-foot tunnel a distance of from 4 to 6 feet.”
If counsel were correct in his statement that two witnesses had unconditionally testified as indicated in the foregoing quotation, then, in view that the court directed a verdict against appellant, there would be merit to counsel’s contention. The witnesses referred to, however, in describing the place where the ore was taken from, left no .room for doubt that it was not taken from a “tunnel” driven by the appellant as provided in the contract, but that it was “stoped” from an old drift or tunnel, and was therefore taken from a place where the appellant had no right to take ore. The situation, therefore, is not, as is assumed by counsel, that there is some substantial evidence in favor of the party against whom a verdict was directed, but it is a case where the testimony of the party’s own witnesses shows that he has taken the very thing he claims as his from his adversary’s property, and therefore has no right thereto.
The next contention that the ore in question was “mined' and extracted long prior to any alleged forfeiture of the contract” is entirely immaterial, in view that the ore was removed from a place where appellant never had any right to take ore.
The next, and only other, contention, in view of the foregoing, is also immaterial.
The petition should therefore be denied. Such is the order.
Reference
- Full Case Name
- ARKOOSH v. SORRENSON
- Status
- Published