EAST BENCH IRRIGATION COMPANY v. State
EAST BENCH IRRIGATION COMPANY v. State
Dissenting Opinion
I dissent for the same reasons mentioned in my dissent in 2 Utah 2d 170, 271 P.2d 449.
Opinion of the Court
What provisions should be included in the district court’s judgment is the question raised by this appeal. The State Engineer rejected the applications of the respondents, who are the plaintiffs in this action, to change the place of diversion and the place and manner of use of the waters of the South Fork of the Sevier River. The district court on appeal reversed that decision and we affirmed its holding that the applications should be approved but reversed some other provisions of that judgment.
Upon the remand, each side prepared and" submitted to the district court findings, conclusions and judgment in accordance with its views, and after full argument the trial court prepared, signed and entered its own findings which differed in some respects from all of the proposals. The court’s
There are two kinds of applications which the State Engineer must approve or reject and his decision may he appealed to the courts: one is an application to- appropriate unappropriated public waters, and the other is an application to change the place of diversion or the place or use of water.
The State Engineer is an executive, not a judicial officer. His decision on such an application may be based on his views of very complicated questions of law and fact, but he does not adjudicate either the law or the facts in the case and it is doubtful that the legislature, under our Constitution, has authority to confer upon the State Engineer the power to make such an adjudication. He is not required to be trained in or to be qualified to pass on such ques
Since the engineer's decision to approve or reject such an application is based on his views of the law as applied to the facts which he finds reason to believe exist or may result from the approval of such application, the legislature appropriately provided for an appeal to the courts from his decision, where such questions of law and fact may be adjudicated.
Such an appeal is taken by commencing an action in the district court, where a trial de novo is provided for on all issues which could have been raised under the application to the State Engineer. Such action is strictly limited to the trial of such issues as could have been raised before the engineer, and an appeal to this court is provided from the decision of the district court. The decision of these courts on such appeal from the State Engineer’s decision has the same effect and no more on the rights of the applicants to proceed with their proposed project as the same decision of the engineer would have had without an appeal.
However, we must not lose sight of the fact that there are a number of reasons why some questions which are considered by the courts in cases on an appeal from the engineer’s decision are not necessarily adjudicated by the courts’ decisions in such cases.
One such issue which cannot be adjudicated on such an appeal is the extent or priority of rights which the applicant hopes to acquire under such application. This for the obvious reason that an adjudication of such rights is premature for no cause of action for the adjudication of such rights can accrue at that time. Before a cause of action can arise to adjudicate that the applicant has established or perfected the' rights which he seeks under such application, his application must first be approved and thereafter .by compliance with its terms and provisions he must perfect the rights which he seeks under the application, and until this has occurred a suit to adjudicate that he has such rights is premature. For until after his application is approved he can acquire no rights under such application.
Another reason why issues considered by the courts on such appeals are not adjudicated in such actions is that often the rights of the protestants and sometimes some rights of the applicants have been adjudicated in a previous action. In such cases there is no necessity for a readjudication, but the court is bound by the previous adjudication. Even in cases where such rights have not been previously adjudicated it is often unnecessary for such an adjudication because the decision of such courts on appeal, the same as the decision of the State Engineer from which the appeal is taken, is based only on a finding that there is reason to believe that rights may be acquired in accordance with the application and not on an adjudication of such issues. This is true as to almost every issue of fact involved in such a case, the courts’ decisions in such cases being based only on a finding of reason to believe that such facts do or may exist if the application is approved rather than a finding of such facts.
However, there are issues in every appeal from the engineer’s decision which must be adjudicated. The court must adjudicate whether there is reason to believe that some rights may be acquired under such application without impairing vested rights of others.
Before discussing the detailed provisions that should be embodied in the judgment, we again call attention to the fact that the approval of such an application may be required even though the court only finds reason to believe that many facts involved exist or will result from the operation under such approval. In the findings of fact the trial court found as facts many propositions which it was only necessary to find that there was reason to believe that such were the fact or that such would be the fact under the operation of the proposed changes. The better practice would seem to be to only find reason to believe such facts exist where that is all that is required, particularly where the fact in question deals with the effect of the operation under the applications.
We will indicate what provisions the judgment should contain by approving, re
We approve paragraphs 1, 2 and 4 of respondents’ proposed “Amended Judgment and Decree.” Paragraphs 1 and 2 approve all of the applications which are before this court. Paragraph 4 authorizes the respondents to proceed to construct the necessary works to put the proposed changes into operation. However, we direct the addition of the following words to the end of that paragraph: “and in accordance with the provisions of and subject to the limitations contained in this judgment.”
We also approve paragraphs 3 and 4 of the proposed "Decree” of appellants, except that such paragraphs should be amended as hereinafter pointed out. Paragraph 3 states that appellants have a vested right to the same flow of water past the Kingston Measuring Station in the same quantity as it would have done without the proposed changes, with the same hourly changes as would have occurred under the old system. Our previous decision did not require the hourly fluctuations. To try to duplicate the hourly fluctuations would greatly complicate the administrative problems without benefiting anyone, so this paragraph should be amended so as to eliminate that requirement, and require only the same quantity of water per day as would have flowed past that station but for the proposed changes. Paragraph 4 also contains the same provision for hourly fluctuations and it should also be amended to eliminate that requirement.
Paragraph 4 requires the State Engineer and the Sevier River water commissioners to determine “from day to day” the quantity of water that would flow past Kingston absent such changes, “and to cause such quantity of water as so determined to actually pass” such station “on the same day” as would have passed such station without such changes. This provision is all right where it is possible to enforce it while making the most accurate determination possible of the daily quantity of water which would have passed such station without such changes. Our previous decision did not require a “from day to day” determination of such quantity of water, nor a separate determination for each day unconnected with the preceding and following days. We required an advance determination of such quantity of water so as to allow time to arrange for the required flow at the station on the day in question, leaving it up to the engineer and commissioners how far in advance and the number of days which should be determined in one figuring. We recognized that changes might occur between the time of the first determination and the end of the day, for
Paragraph 5 of appellants proposed “Decree” provides that “the State Engineer should not permit the construction of such Hatch Town Reservoir until it has been shown, by actual drainage of the lands of plaintiffs and substantial changes in the use of the waters by plaintiffs, that water savings have been effected * * This requires a demonstration of a saving in the amount of water consumed before the reservoir can be constructed. Our previous decision does not justify such a provision and such provision would work a hardship on respondents. It would require respondents to actually effect such saving of water consumed and then turn the water so saved over to appellants to use during the time required to build the reservoir and other diverting works necessary to effect the proposed changes. We reject such a requirement.
However, our previous decision required the approval of the application strictly on condition that the respondents make the changes suggested by their testimony, from which the trial court found reason to believe that the changes could be made without increasing the amount of water consumed thereunder, and that such approval would under those conditions, give the respondents the opportunity under the control of the State Engineer to experiment and demonstrate that such changes could be made without impairing vested rights. Under such holdings the judgment should provide that the proposed changes in place of diversion and place and manner of use of respondents’ waters shall not be made until they show to the satisfaction of the State Engineer that by following the changes proposed in their testimony they can make a saving in the amount of water consumed on their presently operated property. The judgment should also provide that when or if the applied for changes go into operation, the State Engineer shall enforce the requirement that the same quantity of water must pass the Kingston Measuring Station as would have passed that station without such changes in accordance with his determination, and that he may require the respondents to turn down to the lower users all of the water available to them
We also approve the provisions of paragraph 8 of respondents’ proposed “Amended Judgment and Decree” requiring the State Engineer to keep permanent records reflecting the computations and determinations of the flow past Kingston, and to make such records available for inspection to all parties for a reasonable time. There is some ambiguity, probably from inadvertence, in the last sentence of that provision, which should be corrected. We also approve paragraphs 9, 10 and 11 of respondents’ proposed “Amended Judgment and Decree.”
Case reversed and remanded with directions to enter judgment in accordance with the views expressed in this opinion. Costs to appellants.
. East Bench Irr. Co. v. Deseret Irr. Co., 2 Utah 2d 170, 271 P.2d 449.
. See sections 73-3-2, 3, 5, 6, 7, 8, 10, 14 and 15, U.C.A.1953.
. See Provo Bench Canal & Irr. Co. v. Linke, 5 Utah 2d 53, 296 P.2d 723, and cases cited in note 1 therein.
. See sections 73-3-14 and 15, U.C.A.1953.
. See United States v. District Court, Utah, 238 P.2d 1132; Id., Utah, 242 P.2d 774.
.- See-cases cited in-note 5.
. See cases referred to in note .3.
. See cases referred to in note 3.
. See cases cited in note 3.
. Tanner v. Bacon, 103 Utah 494, 136 P.2d 957.
Reference
- Full Case Name
- EAST BENCH IRRIGATION COMPANY Et Al., Plaintiffs and Respondents, v. STATE of Utah, Joseph M. Tracy, State Engineer of the State of Utah, Deseret Irrigation Company, Et Al., Defendants and Appellants
- Cited By
- 17 cases
- Status
- Published