Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC
Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC
Opinion of the Court
This matter comes before the Court on the Joint Motion to Dismiss (the "Motion to Dismiss") filed by Respondents Powhatan Energy Fund, LLC ("Powhatan"), Houlian "Alan" Chen ("Chen"), HEEP Fund, Inc. ("HEEP Fund"), and CU Fund, Inc. ("CU Fund") (collectively, "Respondents"). (ECF No. 95.) Respondents contend that the Federal Energy Regulatory Commission ("FERC" or the "Commission") brought this action beyond the applicable statute of limitations, that FERC does not have the authority to seek disgorgement as a civil penalty, and, assuming disgorgement is available, that it is also barred by the statute of limitations. (Mem. Supp. Mot. Dismiss 1, ECF No. 96.) FERC opposed the Motion to Dismiss, and Respondents replied. (ECF Nos. 99, 106.) Accordingly, the matter is ripe for disposition.
The Court dispenses with oral argument because the materials before it adequately present the facts and legal contentions, and argument would not aid the decisional process. The Court exercises jurisdiction pursuant to 16 U.S.C. § 823b(d)(3)(B)
*686and
I. Factual and Procedural Background
An earlier decision by this Court concluded that its de novo review of FERC's imposition of penalties required application of the Federal Rules of Civil Procedure and the Federal Rules of Evidence. Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC ("FERC I "),
A. Factual Background
Respondents consist of Chen and various financial entities on whose behalf Chen traded energy for the approximately two months at issue in this case, between June 1, 2010, and August 3, 2010 (the "Two-Month Alleged Manipulation Period"). Chen owns the entirety of Respondents HEEP Fund and CU Fund. Respondents conducted financial trades through the wholesale electricity market administered by PJM Interconnection, LLC ("PJM"), an organization that operates various electricity markets throughout the Mid-Atlantic. Certain energy trades qualified market participants to receive a payment, known as a "Marginal Loss Surplus Allocation," or MLSA, which PJM distributed to customers making certain trades. (Am. Compl. Ex. 1 ("Penalty Order") ¶ 2, ECF No. 93-1.) FERC alleges here that, during the Two-Month Alleged Manipulation Period, Respondents "designed and implemented a fraudulent ... trading scheme to receive excessive amounts of MLSA payments," by manipulating "day-ahead" and "real-time" energy trades to engage in wash trades: "trades that are pre-arranged to cancel each other out and involve no economic risk." (Id. ¶¶ 3, 6.)
FERC became aware of Respondents' purportedly manipulative activities after PJM received two complaints from a market participant about someone "trying to game the system." (Id. ¶ 26.) In August 2010, in response to these complaints, PJM submitted a "referral" to the Commission's Office of Enforcement ("Enforcement"), alerting the Commission to Respondents' allegedly fraudulent behavior and setting off the investigations that ultimately resulted in this action.
On August 5, 2014, almost one year later, four years after the Commission began investigating Respondents, and more than four years after the Two-Month Alleged Manipulation Period, the Office of the Secretary issued a Notice of Alleged Violations. Settlement discussions failed, and Enforcement issued Respondents a notice of its "intent to recommend the initiation of a public proceeding against Respondents" (the "Notice"). Respondents replied to the Notice on September 24, 2014. The Notice and Respondents' opportunity to reply constituted the first procedural requirement with which the Commission had to comply in the investigation and penalty assessment process.
The OSC alleged Respondents violated the statute and regulation forbidding the use of manipulative behaviors in connection with the purchase or sale of electric energy:
CU Fund: $10,080,000 civil penalty; $1,080,576 disgorgement;
HEEP Fund: $1,920,000 civil penalty; $173,100 disgorgement;
Powhatan: $16,800,000 civil penalty; $3,465,108 disgorgement; and,
Chen: $1,000,000 civil penalty.
(OSC 1, ECF No. 93-2.) The OSC also recommended that: (1) HEEP Fund, CU Fund, and Chen be jointly and severally liable for disgorgement of unjust profits; (2) HEEP Fund, Powhatan, and Chen be jointly and severally liable for disgorgement of unjust profits; (3) HEEP Fund and Powhatan be jointly and severally liable for the penalties against HEEP Fund; and, (4) HEEP Fund and Powhatan be jointly and severally liable for the penalties against Powhatan.
The OSC directed Respondents to show cause within thirty days why they should not be found to have engaged in manipulative trading and required to disgorge profits and be assessed the proposed civil penalties. The OSC also ordered Respondents to elect either a formal hearing before an administrative law judge ("ALJ") prior to the assessment of a penalty, pursuant to 16 U.S.C. § 823b(d)(2), (the "Default Option"), or to proceed under 16 U.S.C. § 823b(d)(3)(A), (the "Alternate Option"), under which the Commission would "promptly" assess penalties upon a finding of violation.
The Commission extended Respondents' deadline to respond once, on December 31, 2014, granting Respondents until February 2, 2015, to respond to the OSC.
After cross-briefing
Because of its findings, and pursuant to 16 U.S.C. § 823b(c),
CU Fund: $ 10,080,000 civil penalty; $1,080,576 disgorgement;
HEEP Fund: $1,920,000 civil penalty; $173,100 disgorgement; and,
Powhatan: $16,800,000 civil penalty; $3,465,108 disgorgement;
Chen: $1,000,000 civil penalty.
*690(Penalty Order ¶¶ 164, 174, 187, 190.) The Commission also agreed with the OSC recommendations regarding joint and several liability, and therefore held: (1) HEEP Fund, CU Fund, and Chen jointly and severally liable for disgorgement of unjust profits; (2) HEEP Fund, Powhatan, and Chen jointly and severally liable for disgorgement of unjust profits; (3) HEEP Fund and Powhatan jointly and severally liable for the penalties against HEEP Fund; and, (4) HEEP Fund and Powhatan jointly and severally liable for the penalties against Powhatan.
The Commission ordered the payment of all penalties and profit disgorgement within sixty days, and directed PJM to "establish a method to resettle and distribute the resettled MLSA Payments .... [and] to provide reimbursement of MLSA payments ... to those entities identified as a result of PJM's proposed methodology." (Id. at 88.) Respondents failed to pay the penalties within 60 days, and, pursuant to § 823b(d)(3)(B),
B. Procedural Background
On July 31, 2015, FERC filed this action seeking an order affirming and enforcing the Commission's Penalty Order. (ECF No. 1.) Respondents filed motions to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6).
After the parties submitted cross-briefs discussing the meaning of this Court's de novo review procedure under § 823b(d)(3)(B), the Court denied the initial motions to dismiss without prejudice and ordered additional briefing. (ECF No. 44.) The parties then filed supplemental briefs, and a great deal of supplemental authority. (ECF Nos. 52, 53, 55, 68, 69, 70, 78, 79, 80, 82, 83, 84, 85, 88-1.) On December 28, 2017, the Court issued FERC I , ruling that Respondents were entitled to a trial de novo governed by the Federal Rules of Civil Procedure and the Federal Rules of Evidence. (ECF Nos. 89, 92.) The Court ordered FERC to file an Amended Complaint, and set a schedule by which Respondents should file their responsive pleadings to the Amended Complaint. (ECF No. 92.) Respondents timely filed their Motion to Dismiss. (ECF No. 95.)
II. Analysis
As with the Court's determination on the meaning of the de novo review procedure under 16 U.S.C. § 823b(d)(3)(B) in FERC I , the Motion to Dismiss presents an issue of first impression in this District, *691and one which neither the Supreme Court of the United States nor the United States Court of Appeals for the Fourth Circuit has addressed.
FERC disagrees with each of Respondents' arguments. Pertinent here, FERC asserts that its claim in this Court accrued, for statute of limitations purposes, only when Respondents failed to pay the penalty within sixty days of the Commission assessing it via the Penalty Order. FERC also argues that the Commission's ordered disgorgement is remedial and not subject to any statute of limitations, and the Court may order disgorgement under its inherent equitable powers.
No clear answer exists for any of these issues, but the outcome materially impacts the parties' rights and responsibilities. If FERC prevails, all penalties remain timely and Respondents could be liable for more than $28 million dollars in civil penalties and more than $4 million dollars in disgorgement. On the other hand, if Respondents present the correct interpretation, FERC cannot maintain a suit for enforcement of the penalty assessment order as to the vast majority of the dates within the Two-Month Alleged Manipulation Period, substantially reducing the monetary value of this action.
The atypical statutory scheme for assessing a penalty under the Alternate Option of § 823b has generated prolonged litigation before this Court and other courts addressing FERC's attempts to assess and enforce assessed penalties pursuant to that statute. Statutes, more commonly, presume enforcement after a formal agency adjudicative process pursuant to the Administrative Procedures Act ("APA"). See, e.g., Fed. Energy Regulatory Comm'n v. City Power Mktg., LLC ,
However, considering the plain language of the relevant statute of limitations in the context of the process by which FERC assesses civil penalties, and mindful of the long-established principle that courts may not interpret statutes contrary to the plain language, the Court finds that the action currently before it accrued sixty days after Respondents failed to pay the Penalty Assessment Order. FERC's action in this Court therefore falls well within the five-year statute of limitations.
Further, given the fact-intensive nature of determining whether disgorgement constitutes a penalty, the Court cannot determine on the record before it whether the ordered disgorgement operates as a penalty falling within the language of the statute of limitations. Regardless, the Commission had the authority to order disgorgement, and this Court has the inherent equitable power to affirm or modify that order as to the disgorgement. Given the Court's finding that FERC commenced this action within five years of the date on which it accrued, the action seeking affirmance of the order of disgorgement would be timely even if the disgorgement did amount to a penalty. The Court will therefore deny Respondents' Motion to Dismiss.
A. Relevant Legal Standards
1. Federal Rule of Civil Procedure 12(b)(6)
Although the Motion to Dismiss presents a pure question of law for the Court, the Court remains mindful of, and will apply, the familiar standard for ruling on a motion to dismiss for failure to state a claim. "A motion to dismiss under Rule 12(b)(6) tests the sufficiency of a complaint; importantly, it does not resolve contests surrounding the facts, the merits of a claim, or the applicability of defenses." Republican Party of N.C. v. Martin ,
The Federal Rules of Civil Procedure "require[ ] only 'a short and plain statement of the claim showing that the pleader is entitled to relief,' in order to 'give the defendant fair notice of what the ... claim is and the grounds upon which it rests.' " Bell Atl. Corp. v. Twombly ,
2. Fundamental Principles of Statutory Interpretation
The Court must employ traditional principles of statutory interpretation to construe the governing statute of limitations.
*693The purpose of statutory interpretation is "to try to determine congressional intent." Dole v. United Steelworkers of Am. ,
The Court must look to the statute as a whole in determining the meaning of individual words because "the meaning of statutory language, plain or not, depends on context." King v. St. Vincent's Hosp. ,
When "the terms of [a] statute are unambiguous on their face, or in light of ordinary principles of statutory interpretation," judicial inquiry normally ends. United States v. Morison ,
[i]f the language is ambiguous, in that it lends itself to more than one reasonable interpretation, [the court's] obligation is to find that interpretation which can most fairly be said to be imbedded in the statute, in the sense of being most harmonious with its scheme and the general purposes that Congress manifested.
United States v. Joshua ,
*694B. Section 2462 Serves as the Governing Statute of Limitations
No party contests, nor could they, that § 823b lacks an independent statute of limitations, meaning that the general, catch-all statute of limitations for civil fines and penalties applies here. See 3M Co. v. Browner ,
Except as otherwise provided by Act of Congress, an action, suit or proceeding for the enforcement of any civil fine, penalty, or forfeiture, pecuniary or otherwise, shall not be entertained unless commenced within five years from the date when the claim first accrued if, within the same period, the offender or the property is found within the United States in order that proper service may be made thereon.
The Court begins "with the language of the statutory text," and gives those words undefined by Congress "their ordinary, contemporary, common meaning." See Midgett ,
*695Robinson v. Shell Oil Co. ,
1. Section 2462, More Readily Applicable to Standard Administrative Procedures, Fits Imperfectly with the Alternate Option
Because the Alternate Option apparently lacks a statutory analogue, the catch-all statute of limitations meant to apply to more common administrative procedural schemes does not fit perfectly. Several difficulties arise when trying to apply § 2462 to the statutory scheme of § 823b. First, the Alternate Option presents an administrative scheme to which neither the parties nor the Court can identify an analogue.
Although aspects of all parties' positions make sense, the Court must turn to the plain language in § 823b. FERC's position conforms to the plain meaning and accepted definition of "accrue." Under the Alternate Option, FERC clearly lacks the authority to "institute an action ... for an order affirming the assessment of the civil penalty" until two events have occurred: (1) the Commission must have assessed the penalty, by order; and (2) sixty days must have elapsed without payment of the civil penalty. Unless and until both events happen, FERC has no right to commence any action in a district court. It runs counter to the definition of "accrue" that a claim could accrue before a party has the right to initiate an action.
*696Respondents' position, however, seemingly comports well with the overall structure of § 823b. The Court in this action adjudicates de novo the propriety of the civil penalty assessment, which flows directly from the alleged violations, making it commonsensical that the claim would accrue at the time of the violation. Furthermore, this district court action under the Alternate Option functions as the equivalent of an adjudication before an ALJ under the Default Option-an action that clearly accrued at the time of the purported violations. Finally, given the lack of statutory or regulatory requirements for the Commission's penalty assessment under the Alternate Option, and the Commission's near-exclusive control over the speed with which the penalty assessment order issues, the possibility exists that the intended "prompt[ ]" penalty assessment might not be prompt after all.
Although FERC's interpretation could result in some conflict with the purposes of statutes of limitation, the reading Respondents advocate plainly conflicts with the generally accepted plain meaning of "accrue." The Court may not rewrite the statute to result in a meaning it finds more desirable. Ali ,
2. The Relevant Statutory Phrases in the Statute of Limitations
The Court must determine how
a. "An Action, Suit, or Proceeding"
FERC plainly commenced "an action, suit[,] or proceeding" within the meaning of § 2462 by filing its Complaint in this Court.
b. "For the Enforcement of Any Civil Fine, Penalty, or Forfeiture"
Binding precedent requires this Court to conclude that § 2462 applies to any of FERC's efforts to impose or enforce any civil fine, penalty, or forfeiture. Because, by its plain language, § 2462 governs this action to the extent FERC seeks "the enforcement of any civil fine, penalty, or forfeiture."
i. The Court Has Authority to Order Disgorgement of Profits
No dispute exists that the Commission had the authority to assess civil penalties against Respondents, or that the Court has the authority to affirm that assessment. Respondents, however, challenge the Court's authority to order disgorgement of profits. Under the plain statutory language of the Alternate Option and well-established principles of federal court authority, the Court has the power to assess civil penalties and to order disgorgement of profits.
Although Respondents contend that the Commission had no authority to order disgorgement in the Penalty Order, they acknowledge that, in this federal district *698court action in which the Court reviews de novo the law and the facts involved, "judicial, not agency, authority" is implicated. (Mem. Supp. Mot. Dismiss 26.) Regarding the Court's authority to order disgorgement, Respondents argue that 16 U.S.C. § 823b
limits the Court's jurisdiction to the civil penalty assessment. The limited scope of [ § 823b ], the lack of any express statutory grant of authority for FERC to seek disgorgement in this action, and the lack of any express statutory authority even for FERC to administratively order disgorgement, together all compel the conclusion that FERC's disgorgement claims must be dismissed.
(Id. at 27.) Respondents' argument ignores the language of the statute and well-established principles of courts' authority.
This Court, after conducting a de novo review of the law and facts involved, has "jurisdiction to enter a judgment enforcing, modifying, and enforcing as so modified, or setting aside in whole or in [p]art " the Penalty Order. 16 U.S.C. § 823b(d)(3)(B) (emphasis added) (footnote omitted). Section 823b does not limit the Court's jurisdiction in the drastic way Respondents contend. The Court may enforce the Penalty Order; modify the Penalty Order and enforce it as so modified; or set the Penalty Order aside in whole or in part.
Courts have "inherent equitable powers ... [and] those equitable powers assume an even broader and more flexible character" when public-rather than merely private-interests are at stake. Porter v. Warner Holding Co. ,
[T]he comprehensiveness of this equitable jurisdiction is not to be denied or limited in the absence of a clear and valid legislative command. Unless a statute in so many words, or by a necessary and inescapable inference, restricts the court's jurisdiction in equity, the full scope of that jurisdiction is to be recognized and applied.
ii. The Disgorgement of Profits in the Penalty Order May Not Constitute a "Fine, Penalty, or Forfeiture"
Because assessing whether an order disgorging profits acts as a penalty is a highly fact-intensive inquiry, the Court cannot, at this early stage and on the record before it, determine whether the Commission's order of profit disgorgement *699constituted a penalty, bringing it within the plain language of § 2462. The Court must deny the Motion to Dismiss to the extent it seeks dismissal of the ordered disgorgement of profits as barred by the statute of limitations.
A " 'penalty,' as the term is used in § 2462, is a form of punishment imposed by the government for unlawful or proscribed conduct, which goes beyond remedying the damage caused to the harmed parties by the defendant's action." Johnson v. SEC ,
Importantly, whether disgorgement constitutes a penalty is a "fact-intensive inquiry," because a " 'penalty,' as the term is used in [§] 2462, is a form of punishment ... which goes beyond remedying the damage caused to the harmed parties." SEC v. Alexander ,
Respondents contend that the disgorgement of profits included in the Penalty Order, which holds Respondents jointly and severally liable (in different iterations) for each of the disgorgement payments, "is punitive in nature, and is subject to § 2462" as both a penalty and a forfeiture. (Mem. Supp. Mot. Dismiss 28-29.) FERC counters that "the ordered disgorgement is entirely restitutionary" because, "once paid, the disgorgement amount will be returned to the victims of Defendants' fraud." (Resp. Mot. Dismiss 25, ECF No. 99.)
Despite the joint and several liability the Penalty Order seeks to impose, the Court cannot determine on the current factual record whether the disgorgement the Commission ordered constitutes a "civil fine, penalty, or forfeiture" and thus falls within the scope of § 2462. The terms of the Penalty Order itself appear to indicate that the disgorgement was assessed for purely remedial-and not penal-purposes. The Penalty Order required Respondents to "distribute [their] unjust profits, plus interest, to PJM," which would thereafter "establish a method to resettle and distribute the resettled MLSA payments." (Penalty Order 88.) The Commission further directed PJM to identify "market participants that would have received higher MLSA payments in the absence of Respondents' activity," and "provide reimbursement of MLSA payments, and any available interest" to the market participants PJM identified who had been *700harmed. (Id. ) This method for redistributing the MLSA payments to market participants who would otherwise have received the payments, and which the Commission had deemed Respondents wrongfully received, was directed at "restoring the status quo and ordering the return of that which rightfully belongs" to the legitimate market participants. Tull ,
However, the Commission also assessed disgorgement in way that made different groups of Respondents jointly and severally liable for the ordered disgorgement. As Respondents argue, this type of disgorgement could operate in a way that does not merely restore the status quo, but might place some of the Respondents in a position worse than the position they occupied before their alleged fraudulent trading. See Tull ,
Although the Commission reviewed a voluminous record and made extensive factual findings, it remains for this Court to conduct a review de novo of the law and the facts involved. See 16 U.S.C. § 823b(d)(3)(B). Given the complicated nature of the energy trading scheme, the potentially convoluted relationship among all Respondents, and the fact-intensive nature of the Court's inquiry into whether disgorgement could constitute a penalty, the Court cannot determine at this stage whether the ordered disgorgement amounted to a penalty. While the Court finds this action within the statute of limitations, the Court will also deny the Motion to Dismiss to the extent it seeks to dismiss FERC's claims for disgorgement as barred by the statute of limitations because the factual record before the Court cannot conclusively establish whether the ordered disgorgement operated as a penalty bringing it within the plain language of § 2462.
*701c. "When the Claim First Accrued"
Because the relevant action for purposes of the statute of limitations question before the Court is FERC's suit in this Court for an order affirming the Penalty Order, in order for FERC's action to fall within the statute of limitations, it must have been "commenced within five years from the date when the claim first accrued."
i. The Language of § 2462
Although § 2462 does not lend itself readily to application to the Alternate Option of § 823b, the Court must interpret the statutory language in light of the principle that "Congress intends the words in its enactments to carry 'their ordinary, contemporary, common meaning." Pioneer Inv. Servs. Co. ,
"In common parlance a right accrues when it comes into existence." Gabelli ,
At times, however, the ordinary, common, and natural reading of statutory language does not easily translate to the situation before a court. As at least one court addressing claim accrual in the context of agency action has noted that, although the concept of accrual "appears to be a straightforward formulation, there may be complications: 'The statutory period may begin either when the defendant commits his [or her] wrong or when substantial harm matures. This choice, unnecessary where the two events are simultaneous, becomes complex where considerable time intervenes ....' " 3M ,
The Court faces that complex choice. Given the structure of § 823b, the largely onesided nature of investigations the Commission undertakes, and the unusual procedural pathway an action under the Alternate Option follows, a substantial length of time could separate the point at which "a defendant's [prohibited] conduct occurs," Gabelli ,
ii. The Two Procedural Pathways in § 823b for Assessing a Civil Penalty
In interpreting how § 2462 applies to the action at bar, the Court remains mindful of "the hazards inherent in attempting to define for all purposes when a 'cause of action' first 'accrues.' " Crown Coat ,
Turning to the statute at issue, Section 823b(d) sets forth two paths
As determined in FERC I , the Default and the Alternate Options both envision, at some point, an adversarial proceeding encompassing procedural protections. Under the Default Option, the propriety and amount of the civil penalty is adjudicated before an Administrative Law Judge in accordance with the Administrative Procedures Act. Under the Alternate Option, the adjudication occurs before a federal district judge in accordance with the Federal Rules of Civil Procedure and the Federal Rules of Evidence. On January 12, 2015, Respondents elected the Alternate Option, meaning that Respondents elected to have the propriety and amount of the penalty adjudicated before a federal district court.
The structure of the statute itself demonstrates the intent that adversarial adjudication of the penalty occur either in the administrative context-under the Default Option-or in the judicial context-under the Alternate Option. First, Section 823b(d)(4) allows the Commission to "compromise, modify, or remit, with or without conditions," any civil penalty imposed "at any time prior to a final decision by the court of appeals under [the Default Option] or by the district court under [the Alternate Option]." 16 U.S.C. § 823b(d)(4). By allowing the Commission to modify the penalty it imposed at any time before either a final decision under the administrative Default Option or a judicial decision under the Alternate Option, the statute itself describes district court adjudication as an alternate track for reaching the same result as the administrative option: a final adjudication on the merits.
A second provision of § 823b even more clearly illustrates a statutory scheme allowing for two alternate paths for civil penalty adjudication. Section 823b(d)(5) provides that, if a party fails to pay a penalty assessment "after it has become a final and unappealable order under [the Default Option], or after the appropriate district court has entered final judgment in favor of the Commission under [the Alternate Option], the Commission shall institute an action" in a district court to recover the penalty amount. 16 U.S.C. § 823b(d)(5). In this enforcement action,
Finally, two similarities between the Default Option and Alternate Option also indicate an intention of different paths meant to arrive at the same destination. First, both are commenced by issuance of the notice of proposed penalty under 16 U.S.C. § 823b(d)(1).
Thus, several aspects of § 823b indicate a statutory intent that the initial adversarial penalty adjudication occur either before an ALJ or before a district court: (1) the path to adjudication in either forum begins with the notice required by § 823b(d)(1) ; (2) the Commission may modify its penalty assessment at any time before the adjudication in either forum completes; and, (3) the Commission institutes an enforcement action for a penalty left unpaid after the completion of adjudication in either forum.
However, under the Alternate Option, the statute provides no method by which FERC could bring an action in district court before alleged violators fail to pay the assessed penalty under the Alternate Option. Thus, although the structure of § 823b indicates an intent that the adversarial administrative proceeding under the Default Option and the adversarial judicial proceeding under the Alternate Option pave different avenues to equivalent destinations, the statute dictates that those avenues begin at different times, and FERC exercises differing amounts of control over the time at which each avenue commences.
An administrative adjudication under the Default Option, like traditional administrative ALJ proceedings, begins when FERC issues the OSC, which provides the requisite notice under § 823b(d)(1) -which FERC, under the statute, can do at any time.
In contrast, a judicial adjudication begins only after: (1) FERC issues an OSC; (2) the alleged violator has chosen the Alternate Option; (3) a penalty has been assessed by order; (4) sixty days have elapsed without the violator paying the assessed penalty; and, (5) FERC has instituted a suit in a district court for an order enforcing the civil penalty. FERC exercises only some control over the timing of the process leading to adversarial adjudication under the Alternate Option.
Because FERC had no statutory authority to initiate this action until the first four of these events occurred, only then were "the factual and legal prerequisites for filing suit ... in place," 3M ,
iii. Relevant Caselaw
Each of the parties argues that caselaw strongly supports its position. And although the parties acknowledge that neither the Fourth Circuit nor the Supreme Court has directly addressed this issue-and therefore no decision binds this Court-the parties each fail to place the square pegs of the cases they rely on into the round holes of the administrative scheme at bar, or to even acknowledge that no perfect "fit" exists. The cases that the parties have cited and the Court has identified fall into three general categories, none of which parallels the situation before this Court.
First, the parties identify cases addressing enforcement actions after traditional administrative adjudications, similar to those that occur under the Default Option. See *705United States v. Meyer ,
The parties also point to cases involving enforcement actions against the United States after mandatory administrative proceedings. See Crown Coat Front Co. v. United States ,
Finally, the parties refer to cases addressing enforcement actions by the United States under statutes requiring no prior administrative process. See Unexcelled Chem. Corp. v. United States ,
a. Enforcement Actions after a Traditional Administrative Adjudication
One group of cases interpreting the meaning of § 2462 are those in which a government agency sues in district court for the enforcement of a civil penalty that was imposed through an adversarial administrative adjudication-a process similar to the Default Option. The Meyer line of cases presents the enticingly simple rule that, when a statute mandates administrative proceedings before a court action may commence, § 2462 provides one five-year time limit within which the administrative proceedings must commence, and another, separate five-year time limit after the conclusion of the administrative proceedings within which judicial proceedings must begin. This reasoning, although attractive in its simplicity, cannot govern here. The administrative processes in cases following Meyer contain important procedural safeguards absent from those in the Alternate Option, meaning that the concerns for abuse and delay that drove much of the Meyer court's decision do not present themselves in the Alternate Option. Under the Alternate Option, the investigation and assessment period is subject to few statutory or regulatory requirements and is almost exclusively within the Commission's control.
In the end, the parties overstate the holdings of this line of cases. Meyer and cases following it have stated generally that when a statute that "authorizes the assessment of a penalty provides for an administrative procedure for assessing that penalty, the statute of limitations at § 2462 does not begin to run until 'the penalty has first been assessed administratively.' " United States v. Godbout-Bandal ,
Meyer involved a suit under the Export Administration Act ("EAA"), *706
Meyer elected a hearing, and, "after two years of skirmishing, the administrative law judge ... assigned to the matter rendered an initial decision[, the ALJ found] ... Meyer to have transgressed the EAA" and assessed a $5,000 civil penalty. Meyer ,
Not only did the Meyer court apply § 2462 to an administrative decision in a different procedural context than the one before this Court, but Meyer's reasoning also partially relied on the specific procedural mechanism through which the enforcement action came before it. The Meyer court expressed concern with "the manifold opportunities for ... delay which inhere both as a matter of trial tactics and in the innards of the administrative process." Meyer ,
*707Few of the administrative occurrences with which the Meyer court expressed concern exist in this case. Under the Alternate Option, the "imperatives of the ... APA ..." never apply.
Other cases either follow or parallel Meyer , and similarly involve enforcement actions initiated after a typical agency adjudication similar to proceedings under the Default Option. See Godbout-Bandal ,
*708Because the action before the Court contains crucial procedural differences from the process the Meyer court evaluated and that raised many of the concerns driving the Meyer court's decision, the reasoning of Meyer or other cases like it cannot control.
b. Enforcement Actions Against the United States after Requisite Administrative Proceedings
A second line of cases on which the parties rely also involves circumstances sufficiently different from those the Court faces here that the reasoning of those cases fails to govern. The Crown Coat line of cases involves enforcement actions against the United States after mandatory pre-filing administrative proceedings over which the plaintiff exercised no control. Courts following the reasoning of Crown Coat express concern with the requisite administrative proceedings that can consume the entire statute-of-limitations period, and reason that, because the plaintiffs in those cases have no control over the speed of the administrative proceedings, inequity would follow if the statute of limitations commenced at the time of the underlying violation. Crown Coat cannot control here. Although the administrative proceedings of the Alternate Option, like those with which the Crown Coat court was concerned, would have taken close to all of a five-year statute of limitations period, unlike plaintiffs in cases similar to Crown Coat , the plaintiff in this action (FERC) exercised substantial-indeed, nearly exclusive -control over the nature and speed of the administrative proceedings.
In Crown Coat , a private contractor sued the United States under the Tucker Act for the adjustment of a government contract which expressly conditioned the contractor's right to sue on administrative exhaustion. Crown Coat ,
*709administrative determination."
Like Meyer, Crown Coat does not dictate this Court's determination of the statute of limitations issue before it. Although Crown Coat found that the right of action there, like here, meant the right to file a civil action in the United States Courts, it did so addressing a statutory scheme meaningfully different from § 823b. Crown Coat , like Meyer , evaluated a statutory scheme in which the party against whom the statute of limitations might run (the contractor plaintiff in Crown Coat and the government defendant in Meyer ) was required to comply with and wait for the termination of administrative proceedings over which the party had no control.
In contrast, the Commission almost exclusively controls the amount of time the administrative proceedings take under the Alternate Option. And although, as evinced by the instant case, proceedings before choosing the Alternate Option can take all-or close to all-of the five-year statute of limitations period, unlike in Crown Coat , the amount of time consumed by administrative activity was largely (if not entirely) within the Commission's control. Cases like Crown Coat , which involve suits brought by individuals subject to requisite administrative proceedings out of their control, provide this Court with little guidance. Cf. McMahon v. United States ,
The action before the Court contains fundamental procedural differences from those driving the Crown Coat decision. Although the underlying administrative activities were lengthy, FERC exercised near-exclusive control over the timing of that process. Unlike in Crown Coat , FERC could control whether the entire statute-of-limitations period could run before FERC was able to issue a final Penalty Order. The Court cannot find that the reasoning of Crown Coat controls.
c. Enforcement Actions by the United States When No Prior Administrative Process Was Required
The final group of cases interpreting § 2462 to which the parties direct the Court also involves statutory conditions so different from § 823b that these cases cannot direct this Court's analysis. The Unexcelled line of cases addresses circumstances in which statutes allowed but did not require administrative procedures as a *710necessary prerequisite to bringing a case in district court. Courts following the Unexcelled line of reasoning rely on the non-mandatory nature of the earlier administrative action to conclude that those claims accrued at the time of the alleged violation. Unexcelled cannot control here, though, because FERC had no authority to bring suit in this court until a specified period of time after Respondents failed to pay the assessed Penalty Order. For FERC, administrative proceedings did constitute a necessary prerequisite to bringing this case in this Court.
In Unexcelled , the Supreme Court interpreted the applicability of a statute of limitations to a suit by the United States for violations of the Walsh-Healey Act,
The Supreme Court sided with Unexcelled, holding that " 'the cause of action accrued' within the meaning of [
[T]he Walsh-Healey Act provides that the Attorney General may bring suit to recover moneys owed the United States. The fact that due deference to the administrative process should make a court hold its hand until the administrative proceedings before the Secretary of Labor have been completed, is a matter of judicial administration and of no relevancy here. The statutory liability accrued when the minors were employed. It was from that date that the period of limitations began to run.
*711Unlike the United States in Unexcelled , FERC was statutorily mandated to provide some sort of administrative process to Respondents-either through the Default Option or the Alternate Option. No other right to sue, by the Attorney General or any other entity, exists in § 823b. FERC, unlike the United States in Unexcelled , could not "have brought suit without first resorting to administrative remedies." Crown Coat ,
C. FERC Timely Commenced the Instant Action
Although the parties' positions each have strengths, the Court cannot find that this district court action accrued at the time of Respondents' alleged violations even given the extended timeframe of non-adversarial agency actions that preceded the filing of a Complaint here. The Court must so conclude because the reading Respondents advocate conflicts with the generally accepted plain meaning of "accrue." Based on the plain meaning of the word "accrue," under which accrual occurs "when the factual and legal prerequisites for filing suit are in place," 3M ,
The Court acknowledges that aspects of Respondents' arguments seem more consistent with the overall statutory scheme of § 823b and the purposes of statutes of limitations. But the Court is "not at liberty to rewrite [a] statute to reflect a meaning [it] deem[s] more desirable. Instead, [courts] must give effect to the text Congress enacted." Ali ,
III. Conclusion
For the foregoing reasons, the Court will deny Respondents' Motion to Dismiss. An appropriate Order shall issue.
Section 823b(d)(3)(B) provides that, if an assessed civil penalty is not paid within sixty calendar days,
the Commission shall institute an action in the appropriate district court of the United States for an order affirming the assessment of the civil penalty. The court shall have authority to review de novo the law and the facts involved, and shall have jurisdiction to enter a judgment enforcing, modifying, and enforcing as so modified, or setting aside in whole or in [p]art, such assessment.
16 U.S.C. § 823b(d)(3)(B) (footnote omitted).
"The district courts shall have original jurisdiction of all civil actions arising under the Constitution, laws, or treaties of the United States."
Because Respondents' Motion to Dismiss argues that FERC brought this action outside of the statute of limitations, the facts underlying Respondents' two months of allegedly manipulative trading have little relevance. As background, the Court offers a brief description of the underlying facts of Respondents' allegedly manipulative trading.
PJM conducted its own investigation, which took approximately four months. On January 6, 2011, PJM's Independent Market Monitor submitted an additional referral to Enforcement. PJM's Independent Market Monitor compared Respondent's actions to wash trades and to Enron's manipulative trading.
See Enforcement of Statutes, Regulations[,] and Orders ,
No statute or regulation requires the Commission to conduct a formal-rather than informal-investigation. See 18 C.F.R. § 1b.5 ("The Commission may, in its discretion , initiate a formal investigation by issuing an Order of Investigation." (emphasis added) ).
The Notice was mandated by regulation, but not by statute. See 18 C.F.R. § lb. 19 (stating that the Enforcement staff investigating a violation "shall , unless extraordinary circumstances [exist]... notify the entity [under investigation] that the Investigating Officer intends" to recommend the initiation of a penalty assessment process, "provide sufficient information and facts to enable the entity to provide a response," and "present [any response timely submitted] to the Commission together with the Investigating Officer's recommendation." (emphasis added).)
The next day, the Commission issued an Order Revising Show Cause Order. (See Am. Compl. Ex. 2 ("OSC"), ECF No. 93-2.) The initial Order to Show Cause had notified Respondents only that the Commission intended to impose civil penalties. (See OSC 1-2.) The Order Revising Show Cause Order clarified that the Commission contemplated imposing disgorgement of profits and civil penalties. (Revised OSC 1.) The Court will refer to the Order Revising Show Cause Order, the Order to Show Cause and Notice of Proposed Penalty, and the Enforcement Staff Report and Recommendation attached to the OSC collectively as the "OSC."
A regulation governs the contents of the required notice. Under
The notice of proposed penalty will:
(1) Include the amount of the proposed penalty;
(2) Include a statement of the material facts constituting the alleged violation; and[,]
(3)[ ] Inform the person of the opportunity to elect in writing within 30 days of receipt of the notice to have the procedures of [the Alternate Option] (in lieu of those of [the Default Option] ) apply with respect to the assessment....
Congress passed Section 824v as part of the Energy Policy Act of 2005, Pub L. No. 109-58,
16 U.S.C. § 824v(a), as relevant, prohibits the direct or indirect use of manipulative or deceptive devices "in connection with the purchase or sale of electric energy or the purchase or sale of transmission services subject to the jurisdiction of the Commission." 16 U.S.C. § 824v(a).
18 C.F.R. § lc.2(a) prohibits entities, in connection with the purchase or sale of energy or transmission services subject to the Commission's jurisdiction, from: (1) "us[ing] or employ[ing] any device, scheme, or artifice to defraud;" (2) making untrue or misleading statements of material fact, or omitting facts in a way that is untrue or misleading; and, (3) engaging "in any act, practice, or course of business that operates or would operate as a fraud or deceit upon any entity." 18 C.F.R. § 1c.2(a).
When a respondent has elected to proceed without a full agency hearing pursuant to the Alternate Option, "the Commission shall promptly assess such penalty, by order, after the date of the receipt of the notice ... of the proposed penalty." 16 U.S.C. § 823b(d)(3)(A) ; see
Nothing in the record or the parties' briefing indicates that Enforcement had any statutory or regulatory entitlement to reply to Respondents' response.
The Court finds no authority indicating that statutes or regulations required the Commission to grant this extension. Indeed, the Commission denied Respondents' second request for an extension, instead granting Respondents the opportunity to "file supplemental answers by February 9, 2015." (Penalty Order ¶ 32 n. 65.)
On February 2 and February 9, 2015, Respondents provided their answers to the OSC. On March 2, 2015, Enforcement staff replied to Respondents' answers, and Respondents submitted various additional responses on March 18, 2015, April 14, 2015, and April 23, 2015. Because the March 18, 2015, April 14, 2015, and April 23, 2015 filings were not permitted, the Commission did not consider them in its ruling.
16 U.S.C. § 823b(c) states, in pertinent part:
(c) Civil penalty
Any licensee, permittee, or exemptee who violates or fails or refuses to comply with any rule or regulation under this subchapter, any term, or condition of a license, permit, or exemption under this subchapter, or any order issued under subsection (a) [of this section] shall be subject to a civil penalty in an amount not to exceed $10,000 for each day that such violation or failure or refusal continues. Such penalty shall be assessed by the Commission after notice and opportunity for public hearing.
16 U.S.C. § 823b(c).
16 U.S.C. § 823b(d)(3)(B) states in part: "(B) If the civil penalty has not been paid within 60 calendar days after the assessment order has been made under subparagraph (A), the Commission shall institute an action in the appropriate district court of the United States for an order affirming the assessment of the civil penalty." 16 U.S.C. § 823b(d)(3)(B).
Federal Rule of Civil Procedure 12(b)(6) allows dismissal for "failure to state a claim upon which relief can be granted." Fed. R. Civ. P. 12(b)(6).
The Court also sees no directly on-point decisions from any other United States Courts of Appeal. The parties have identified none. Instead, each of the parties relies on decisions addressing analogous issues, which the Court will address later in this opinion.
To date, two federal district courts have decided the issue at bar, reaching opposite conclusions. Compare Fed. Energy Regulatory Comm'n v. Barclays Bank PLC , No. 2:13cv02093,
The origins of § 2462"date back to at least 1839, and it took on its current form in 1948." Gabelli ,
In 1948, Congress revised much of Title 28, including
This dictate becomes especially important in this opinion's later discussion of disgorgement. See infra n. 27.
Because § 2462 is "generally applicable to all federal agencies," and Congress did not delegate any administrative authority to the Commission to interpret it, the Court owes no deference to FERC's reading of the statute. Fed. Energy Regulatory Comm'n v. Barclays Bank PLC , No. 2:13cv02093,
Many compare, unpersuasively, the Alternate Option to the enforcement provision of Natural Gas Policy Act (the "NGPA"),
But the NGPA enforcement provision differs from the FPA enforcement provision in important ways. First, the NGPA contains no equivalent of the FPA's Default Action. Rather, § 3414 provides one singular route to a penalty assessment. The Commission first "provides notice of the proposed penalty."
Second, the NGPA enforcement provision contains its own statute of limitations. Section 3414(b)(6)(D) states that "[n]o person shall be subject to any civil penalty under this paragraph with respect to any violation occurring more than 3 years before the date on which such person is provided notice of the proposed penalty under subparagraph (E)."
Although the Commission issued its Penalty Assessment Order within five months of Respondents' election to have the Alternate Option apply, labeling the earlier administrative actions "prompt" seems generous. Here, the Commission conducted a nearly five-year investigation into two months of allegedly manipulative trading. During that investigation, without any APA or other procedural constraint to do otherwise, the Commission retained authority to compel the production of documents and testimony. Respondents had no equivalent right to process or discovery, or to control the pace of the investigation.
The investigation and penalty assessment process imposed few statutory or regulatory requirements or limits on the Commission. And, although promptness is not at issue in this case, no statute or regulation dictates or defines what would constitute a "prompt" penalty assessment, as the Alternate Option requires.
FERC argues in the alternative that the proceedings initiated by its Order to Show Cause amounted to the "action suit, or proceeding for the enforcement of any civil fine, penalty, or forfeiture" to which § 2462 refers. Under this interpretation, because the Commission issued the Order to Show Cause well within the five-year time limit, FERC asserts that the statute of limitations has not run on its claims. Because the Court finds that FERC's cause of action in this Court accrued sixty days after Respondents failed to pay the Penalty Assessment Order, it need not address this alternative argument.
Federal Rule of Civil Procedure 3"governs the commencement of all actions, including those brought by or against the United States[,] or an officer or agency thereof." Fed. R. Civ. P. 3 advisory committee's notes to 1937 adoption (emphasis added). Rule 3 provides that "[a] civil action is commenced by filing a complaint with the court." Fed. R. Civ. P. 3.
Although not at issue currently, nothing in the statutory language necessarily indicates that the Court could not order additional penalties or remedies not included in the Penalty Order.
Respondents also contend that the ordered disgorgement amounts to a forfeiture and thus "is subject to § 2462 because, by its plain terms, the limitations bar applies to actions for 'enforcement of any civil fine, penalty, or forfeiture, pecuniary or otherwise.' " (Mem. Supp. Mot. Dismiss 29 (quoting
But the historical interpretation of the catch-all limitations statute suggests otherwise. The Supreme Court, interpreting the Revised Statute § 1047,
[t]he words "penalty or forfeiture" ... refer to something imposed in a punitive way for an infraction of a public law, and do not include a liability imposed solely for the purpose of redressing a private injury, even though the wrongful act be a public offense, and punishable as such.
Meeker v. Lehigh Valley R.R. Co.,
The Court need not disagree with the Eleventh Circuit to reach this conclusion. The Fourth Circuit has acknowledged that, at least when the Securities and Exchange Commission (the "SEC") orders disgorgement of profits, it can serve a punitive function. "The purpose of disgorgement is not to compensate investors, but to force the defendant into giving up unjust enrichment he received as a result of his illegal activities." SEC v. Gotchey ,
Regardless, the fact-intensive inquiry necessary to determine whether the ordered disgorgement constitutes a penalty subject to § 2462 is not amenable to a determination at this early stage.
FERC suggests alternatively that two "mandatory waiting periods" exist in the statute, and the Court should toll any statute of limitations for those two lengths of time, if the Court finds that the statute of limitations begins to run from the date of the violation. According to FERC, this tolling would render its action timely as to the entire Two-Month Alleged Manipulation Period. Because the Court concludes that the claim accrued sixty days after Respondents failed to pay the Penalty Assessment Order, the Court does not address this argument.
As earlier noted, the atypicality of the Alternate Option has confounded a series of courts as to the proper route for judicial review under the Alternate Option. It would seem advisable for Congress or FERC to clarify the expected procedure, including addressing whether an internal statute of limitations would provide guidance to affected parties.
This statutory subsection parallels the subsections under which many of the courts addressing the applicability of § 2462 to administrative actions and deciding when a claim for the enforcement of a civil penalty "accrues" under § 2462 operated-another aspect of § 823b that complicates this Court's analysis of the statute of limitations issue.
Here, the Commission satisfied this statutory notice requirement when it issued the Order to Show Cause. See
At the time period relevant to the Meyer court's determination, the EAA was codified at
Under the governing regulation, the charging letter included a statement that "there [wa]s reason to believe" a violation occurred; set forth "the essential facts" about the violation; referred to the specific regulatory provisions involved; and gave Meyer notice that he would be subject to sanctions.
The Meyer decision cited to
This section of the EAA, under which the United States sued in Meyer has similarities to the § 823b(d)(5), which directs the Commission to institute an action for a civil penalty recovery if a party fails to pay a penalty assessment "after it has become a final and unappealable order under [the Default Option], or after the appropriate district court has entered final judgment in favor of the Commission under [the Alternate Option]." 16 U.S.C. § 823b(d)(5).
The Meyer court's holding, although not expressly limited to the procedural framework before it, relied heavily on that context.
In a situation like that at bar, when the [DOC] issues a charging letter, the imperatives of the Administrative Procedure Act (APA) come into play. From that point on, the timing of the case is largely beyond the Department's control. Additionally, regulations which implement the APA's adjudicatory rules, designed to ensure procedural fairness, afford the private litigant a wide range of protections during the administrative processing of his case.... At the time of this case's administrative development, there were no temporal constraints governing the duration of these pre-hearing proceedings; no limits existed as to the time administrative adjudication might take, or as to when an ALJ had to render his decision. Moreover, even after the ALJ has issued an initial decision, the [DOC] cannot necessarily sue to enforce the resultant penalty; the respondent enjoys a right of appeal to the Assistant Secretary of Commerce for Trade Administration. These kinds of procedures necessarily take time; indeed, in the instant case, administrative activity consumed over three years.
Id. at 919-20 (emphasis added) (footnotes omitted) (citations omitted).
At least five district courts across the country have, in six decisions, likewise relied on Meyer in actions procedurally similar to the one before the Meyer court-actions coming to those courts after adversarial administrative procedures similar to the Default Option of § 823b, meaning they are unlike the Alternate Option this Court faces. The Court in United States v. Worldwide Indus. Enters., Inc. found that "under the plain meaning of [§] 2462, the limitations period for [§] 503(b)(4) of the Communications Act beg[an] at the time the forfeiture order [was] issued, not when the underlying violation occur[red]."
The Supreme Court in Crown Coat , like the Meyer court, relied on the specific procedural processes with which the plaintiff had to comply.
To hold that the [statute of limitations] runs from the completion of the contract ... would have [an] unfortunate impact. The contractor is compelled to resort to administrative proceedings which may be protracted and which may last not only beyond the completion of the contract but continue for more than [the statute of limitations period]. If the time bar starts running from the [contract] completion date, the contractor could thus be barred from the courts by the time his administrative appeal is finally decided. This would be true whether he wins or loses before the board of appeals. Even if he prevailed there and was granted the equitable adjustment he sought, the Government would be immune from suit to enforce the award if more than six years had passed since the completion of the contract. This is not an appealing result, nor in our view, one that Congress intended. The [statutory scheme] evidences a congressional purpose to insure adequate judicial review of administrative decisions on claims arising under government contracts; it is very doubtful that it anticipated no review at all if administrative proceedings, compulsory on the contractor , continued for more than six years beyond the contract's completion date.
Id. at 514 (emphasis added).
In relevant part, § 255
provides a two-year statute of limitations for any action commenced on or after the date of the Act "to enforce any cause of action for unpaid minimum wages, unpaid overtime compensation, or liquidated damages, under the Fair Labor Standards Act of 1938, as amended, the Walsh-Healey Act, or the Bacon-Davis Act[;]" [§ 255 ] also provides that "every such action shall be forever barred unless commenced within two years after the cause of action accrued[.]"
Unexcelled ,
Indeed, the statutory scheme under which Unexcelled had accrued liability to the United States provided that "the party responsible for a breach or violation ... is liable to the Federal Government for ... liquidated damages."
Reference
- Full Case Name
- FEDERAL ENERGY REGULATORY COMMISSION v. POWHATAN ENERGY FUND, LLC
- Cited By
- 2 cases
- Status
- Published