An agreement was entered into between the appellees and the appellant in this case, similar to those which were entered into between the appellees and the appellant in the case just decided, of The Baltimore & Ohio Rail Road Company v. Polly, Woods & Co., except that in this case the work to be done was on the 161st and 162d sections of said road. The agreement bears date on the 20th day of January 1851, the work was to be completed on or before the first of June 1852, and the prices agreed to be paid for the different kinds of work were generally different from the prices agreed to be paid for similar work in that case.
The work was finished on the 1st of December 1852. The monthly and final estimates were made of the quantity, character and value of the work, as provided for in the said agreement.
In June 1853 the appellees instituted an action of assumpsit against the appellant. The declaration contained but two counts, to wit, the indebitatus count, and the account stated. No bill of particulars appears in the copy of the record which is before this court; though it is probable that one was filed with the declaration. After various proceedings were had in the action, a verdict was found for the appellees on the
The first error assigned in the petition for the supersedeas, is the rejection by the court of .three special pleas which were offered by the defendant. They are similar to the three special pleas which were offered and rejected in the case of The Baltimore & Ohio Rail Road Company v. Polly, Woods & Company; except that the first special plea in this case avers full payment of the amount ascertained by the final estimate. And for reasons assigned in that case, I amCof opinion that the court did not err in rejecting the three special pleas in this.
The second assignment of error is founded on .the defendant’s second bill of exceptions. On the trial of the cause, the plaintiffs having offered evidence of work done by them for the defendant, proposed to examine a witness (Charles De Hass) as to the amount and value of the work; and thereupon the defendant objected to the admissibility of such evidence, and offered to prove that the whole of said work was done’under a written contract, duly executed' by the plaintiffs and defendant (and set out in hcec verba in the bill of exceptions) ; and that a final estimate of said work had been made according to the provisions of said contract; which objection the court overruled, and the defendant excepted.
The question presented by this assignment of error, is the same in effect with the question presented by the second assignment of error in the case above referred to: and for reasons given in that case, I am of opinion that the court did not err in overruling the objection above mentioned.
1st; that if they believe from the testimony that the work, &c. set out in the first count of the declaration, and charged in the bill of particulars, was done by the plaintiffs under the said written contract; then although they may further believe from the testimony that no proper and sufficient final estimate of said work has been made by the engineer charged with that duty, according to the terms of the contract, the plaintiffs are yet not entitled to recover under said first count, unless they further show that, after a demand or other proper exertions on their part, they have been unable to procure such a final estimate as is required by the contract.
3d; that if they believed, &e. (as above); and further, that in accordance with said contract, a final estimate of said work, &c. has been made out by said engineer; and that the fall amount of said estimate has been paid by the defendant to the plaintiffs; then, in the absence of any proof of fraud or other misconduct on the part of said engineer, they ought to find for the defendant so far as said first count is concerned.
These instructions the court refused to give; but in lieu thereof, or of the second and third, gave the following :
“ The contract between plaintiffs and defendant, provides for the performance of certain kind of work for the defendant, and the mode and times of ascertaining the quantity and nature of such work as the same shall have been executed, and fixes the compensation for each respective kind. The contract provides for embankment, earth excavation, loose rock excavation, and solid rock excavation; and the character of these different kinds of work, besides this general classification, are again more specially defined in the contract. From the general language used in their classification, and from the very nature of the subject, it is apparent that at no stage of the work, where there is any gradual change in the character of the material to be removed, there can be a precise ad-measurement or ascertainment, by any agency or method which might have been adopted, of the quantity,, and especially of the character of either or each class; but something must be left to the judgment of one or the other party, or to some proper substitute. Hence,
“This mutual agent having been provided by the contract, you should receive and adopt his estimates as correct, and the onus or burden of proof to impeach them is thrown upon the plaintiffs. But it is competent for the plaintiffs to show that those estimates are produced by fraud and corruption, or they may show mistake or error, patent or open to inspection on the face of the estimates; but that it is not competent by extraneous proof, to show mere error of classification or ascertainment of quantity. You are to ascertain whether there was a waiver of the contract by the parties; and for this purpose you will weigh all the circumstances of the transaction, the relative position of all the parties, and any-other circumstances of forbearance or oppression which you may find touching this matter in the testimony, to ascertain the fact and character of this waiver, and to what extent there has been any deviation or alteration therefrom by common consent, viz : in the time of performance and in the joint mode of executing the same by the plaintiffs and the defendant.
“ That in the presence of fraud or patent error, the final estimate of the engineer, as in the case of monthly estimates, is not conclusive, but to be governed by the like principles of investigation herein given you in charge. But in ascertaining whether there was any fraud or corruption on the part of the resident engineer, you will weigh all the testimony before you, treating the estimates of the resident engineer as frima facie correct, and consider opinions, knowledge and facts of the scientific witnesses as delivered in testimony on either side, and give them such weight as in your judgment they may be justly entitled to. If you find no fraud or corruption in the resident engineer, nor any error and mistake on the face of the estimates, you should find for so much and to such extent in favor of the defendant. If, on the other hand, you find mistake and error on the face of those esti
The three instructions asked for by the defendant are very much like the first three instructions asked for by the defendant in the case of The Baltimore & Ohio R. R. Co. v. Polly, Woods & Co. before referred to. The first instruction in this case is identical, in substance at least, with the first in that; and for reasons assigned in that, I think the Circuit court did not err in refusing to give it. It is stated in the bill of exceptions that the plaintiffs offered evidence tending to impeach the final estimate. They might have impeached it by proving fraud in the engineer in making it out; though certainly such proof ought to have been very clear to have had that effect. If so impeached, I think, as I said in that case, that it was not incumbent on the plaintiffs to show that they demanded, or used other exertions to procure any other final estimate.
The only difference between the second instruction asked for in this case and the second asked for in that, is, that while both treat the giving or offering to give a release as a condition precedent to the action, the words “ upon their receiving the full amount of final estimates properly made out,” &c. are inserted in the latter, but not in the former. These words are of some importance, and their insertion in the second instruction asked for in this case would have rendered it less objectionable in form than it is. But still I think the refusal of the court to give the instruction was calculated to mislead the jury, and make them believe that, under no circumstances and with no qualification,
The third instruction asked for in this case is the same, in substance, with the third asked for in that, and ought to have been given in the form in which it was asked for. The only question as to the propriety of doing so arises from the fact that it does not expressly appear from the bill of exceptions that any evidence was offered to prove payment of the amount of the final estimate, or any part thereof; and therefore it may be said that the instruction involves an abstract proposition. This ground was not relied on by the Circuit court, nor was it taken by the counsel of the appellees, in the argument before this court, doubtless because there was in fact evidence before the jury of the payment of the whole amount of the final estimate. It was not expressly stated in the bill of exceptions that evidence of the fact had been offered, probably because the fact was not denied. It was not one of the controverted questions in the case. But though it was not so stated, I yet think it sufficiently appears that there was evidence of payment before the jury to authorize the giving of the instruction. There was evidence before them that the monthly estimates required by the contract were regularly made; and the object of requiring them was, that four-fifths of the amount of each, as made, might be paid to the plaintiffs. The amount of the verdict is not one-third as large as the amount of the final estimate.
I also think the Circuit court erred in giving the instruction which it did in lieu of the second and third instructions asked for by the defendant. The instruction given was very long and complicated, and calculated to mislead the jury. The second and third in
“If the jury believe from the evidence that the contract offered in evidence was entered into between the parties, that the work, &c. set out in the first count of the declaration, was done, &c. under and by virtue of that contract, and that a final estimate was made according to the said contract, and without fraud; then the plaintiffs are not entitled to recover under the said first count:
1st; without proving that before this action was instituted they gave or offered to give to the defendant, upon receiving the balance appearing to be due on the said final estimate, a release under seal from all claims or demands whatsoever growing in any manner out of the said contract. Nor
2d; if the jury believe from the evidence that before the action was instituted the amount of said final estimate was paid by the defendant to the plaintiffs.”
The plaintiffs also excepted to the instruction given by the court; but I do not think it was prejudicial to them. I do not mean to deny the correctness of any of the legal propositions stated therein. Most if not all of them may be correct; though I express no opinion as to that. I consider the instruction objectionable, as a substitute for the second and third asked for
But for other errors before mentioned, I think the judgment ought to be reversed, the verdict set aside, and the cause remanded for a new trial.
Judgment reversed.