By an act of the general assembly approved March 6,1874, the plaintiff in error, David A. Plecker, was authorized to erect a toll-bridge across North river at Mount Crawford, m the county of Rockingham, at or near the site of the former bridge; and for that purpose he is expressly authorized “ to purchase or condemn, in the mode ■ prescribed by law, a lot of ground not exceeding one acre for the erection of a toll-house, and so much land as may be necessary for the abutments and the construction of said bridge, and a convenient pass-way over the same.” The land on the west side of the river, where he proposed to erect the bridge, was owned by the defendant in error, Jackson Rhodes, and being unable to purchase from him the land necessary for the purpose, he says he instituted proceedings in the county court of Rocldngham to have so much as was necessary condemned in pursuance of the said act, which were resisted by the- said Rhodes, but resulted in the judgment of the court in his favor, and in the condemnation of so much of the said defendant’s land as had been laid off and set apart by the commissioners of the court for the purpose. And he says that he thereupon proceeded with the work of constructing and erecting the bridge, and had it nearly completed when the said defendant in error obtained a writ of error and supersedeas to the judgment of the county court from the “circuit court of Rockingham county, and the reversal of the same. And he comes to this court by writ of error and supersedeas to the judgment of the said circuit court for relief.
■ At the very threshold of the case we are confronted with the declaration that the legislature had not the
On page 592, after sayin'g that the state may authorize the construction of bridges over navigable waters, notwithstanding they may, to some extent, interfere with the right of navigation, he observes: “The legislature must always have power to determine what public ways are needed,” &c. This power of granting authority to individuals to erect toll-bridges has been exercised by the legislature of the state from a period perhaps coeval with the foundation of the government. We have instances of it in the construction of Mayo’s bridge over James river at Richmond, the bridge at Fredericksburg, over the Rappahannock, the bridge over James river at
But it is assumed by defendant’s counsel that the act authorizing the erection of the bridge in question is for private benefit, and that section 14, article 5, of the constitution of this state, by implication, prohibits the taking the private property of one individual for the private use or benefit of another. In general that may be sound in principle, but we do not think it is implied by the clause of the constitution referred to, or that it is a constitutional prescription. There are certainly exceptions to it, and when it comes in conflict with the maxim sic uiere tuo ut alienum non laedas, it is not true. One citizen is entitled to a right of way through his neighbor’s land, if it is the only way by which he can have access to his mill or to his court-house, &c. Hor is it sound if the conferring the privilege or benefit upon the individual, will be for the public benefit and convenience. The charter of companies for making turnpike roads and railroads, with special privileges, is for the benefit of the private individuals who undertake the enterprise, else they would not undertake it. But they are works which will be for the benefit of the community, or the state, or supposed to be, otherwise the legislature would not grant the chai’ter. And so the establishment of ferries is for the benefit of the individuals, to whom the franchise is granted. And in like manner the authority given to an individual for the construction of a toll-bridge across a river, is a franchise which is to benefit the individual to whom it is granted, else he would not undertake it; but it is granted to the individual in consideration of the convenience and benefit it will be to the public. All these exercises of the functions of sovereignty by the legislature, and the be
In accordance with this principle, the act of March 6th, 1874, was enacted, granting to D. A. Plecker authority to erect the toll-bridge in question, and investing him with franchises therein. Whilst the act authorizes him to “ purchase, or condemn in the mode prescribed by law, a lot of ground, not exceeding one acre, for the erection of a toll-house, and so much land as may be necessary for the abutments and the construction of the said bridge and a convenient pass-way over the same,” it directs no enquiry to be made by the courts as to the public benefits which would accrue from the erection of said bridge. There is no proof in the cause, if it would have been competent for the defendant to have offered such proof, that it would not be beneficial to the public. But if it were proper to go into such an enquiry, there is very strong presumptive evidence that it would be a very great convenience and benefit to the public. The bridge is to be erected over North river, a very considerable stream near the town of Mount Crawford, to furnish a pass-way over said river upon a public highway, near the site of a former bridge upon said highway, which is not now standing, and a slight change to be made in the old road so as to pass over the proposed new bridge. These facts tend strongly to show that it would be a great public convenience and benefit, and it must have been so regarded by Plecker or he would not have undertaken to construct it; for in proportion to the use and benefit to the public, it would be beneficial to him.
But it is objected that the plaintiff proceeded under chapter 56 of the Code, and not under chapter 52. The act of March, 1874, which authorizes him to condemn the land, does not require him to proceed under chapter 52 or 56, but to condemn it in the mode prescribed by law. Chapter 56 does prescribe the mode whereby the lands of private parties may be condemned for such purposes, and that mode was pursued in this case. But that act only authorizes a company incorporated for a work of internal improvement, the court of a county or the council of a town to condemn the land. It may with much force be argued that the plaintiff by the act of 1874 is chartered as a sole corporation for a work of internal improvement. He is invested with important chartered privileges as a sole corporation. He and his legal representatives are invested with power to collect tolls on all travel and transportation over sáid bridge, and the rate of the tolls is regulated by the act. And it is expressly reserved to the legislature to change and regulate hereafter the rate of tolls “prescribed by this charter.” The act calls it a “charter.” And it moreover provides that “all laws in force regulating toll-bridges shall apply to this act.” Those laws may be found in Code of 1878, ch. 64, §§ 25, 26, 27, 28, 29, 30; and they show that the proprietor of the toll-bridge is in some sense a public character, and that he holds the franchise under responsibilities to the state and under the regulations of law, and that the erection of a toll-bridge is not a matter exclusively of private interest, but that it is a work in which the public has an interest, and which is subject "to state'control.- • •
There are other assignments of error, which we are of ■ppinion are unsustained. We need only notice one of them—that the act of March 6, 1874, required D. A. Plecker to begin the bridge within six months from its date, and the time had expired before he gave notice to Rhodes of the motion in .this proceeding. The said notice was not necessary to the commencement of the bridge. That may have been commenced within six months. The getting of timbers or other material, we think, would have been a commencement within the meaning of the act. And before the twelve months had expired, within which time the bridge was required to be completed, the act was amended and re-enacted, to-wút: on the 15th of January, 1875, requiring the bridge to be completed within two years. If it was not entirely completed within that time, which is not shown by the evidence certified, the work was most probably retarded by the obstruction interposed by the defendant in error. The progress of the work was probably obstructed by him until the judgment of the county court against him and in favor of the plaintiff, on the 20th of May, 1875. He seems from thence to have made no opposition, and
Upon the whole, we are of opinion to reverse the judgment of the circuit court, and to affirm the judgment of the county court of Rockingham county.
Moncure, P., and Christian, J., concurred in the opinion of Anderson, J.
Staples and Burks, J’s, concurred in the conclusion, but not in all the views set forth in the opinion of Anderson, J.
The judgment was as follows:
This day came again the parties by their counsel, and the court having maturely considered the transcript of
Judgment of the circuit court reversed.