Tazewell Coal & Iron Co. v. Gillespie
Tazewell Coal & Iron Co. v. Gillespie
Opinion of the Court
delivered the opinion of the court.
The facts of the case are fully and accurately stated in (Tazewell Coal and Iron Co. v. Gillespie, 113 Va. 134, 75 S. E. 757) the opinion handed down in January last, and need not be repeated here. The conclusion then reached was that in no view of the case could the mutual innocent mistake of the parties be corrected and appellants granted specific performance of the contract alleged to have been made in 1889, without imposing an unwarranted hardship upon the appellees by giving, as a result of changed conditions, the appellants more and the appellees less than the spirit and intent of their contract entitled them to.
The burden is upon the appellant company to show itself entitled to a decree for the specific performance of the contract it seeks to enforce. The circuit court held that it had not sustained this burden, and we are by no means satisfied, as we must be, that there was error in that conclusion. It is now more than twenty years since the innocent mutual mistake sought to be corrected was made. Many material changes have in the meantime taken place in the situation of the parties and in the subject mattér of the contract, so that the original intention of the parties cannot, at this late day, be enforced without grave danger of doing great injustice to the appellees.
We have carefully considered the arguments submitted upon the petition to rehear, and are of opinion that the appellees cannot now be placed in substantially the same position they would have occupied if there had not been
Affirmed.