Richmond College v. Scott-Nuckols Co.
Richmond College v. Scott-Nuckols Co.
Opinion of the Court
delivered the opinion of the court.
While all of the work was done in the construction of a sewer and water system upon the property of the defendant at Westhampton, the contracts were let at separate times, under different specifications and upon competitive bidding. They might just as well have been entered into with three separate contractors as with one, and no refer-' ence is made in either one of the contracts to either of the others. They were, therefore, clearly independent and not interdependent agreements. All that is hereafter said must be read in view of this conclusion, which was contested by the defendant in several different methods before the trial court as well as here.
There was, as is usual in such controversies, a sharp conflict in the evidence, which we shall not review, because by the mandate of the statute, under the demurrer to the evidence rule, the defendant is here admitting the truth of all of the contractor’s evidence and all proper inferences therefrom which conflict with its own evidence.
It is only necessary to say, as to this specification, what was said as to the sixth and seventh grounds of demurrer in the case of Newton v. White, 115 Va. 849. 80 S. E. 561, and that is that it is no more than an assertion that the declaration is insufficient in law. The rule which' would apply under section 3271 in cases where the plaintiff moves the court to require the defendant to state the grounds of demurrer, requires that they shall be stated specifically, and that no ground shall be considered other than those so stated. Va. & S. W. Ry. Co. v. Hollingsworth, 107 Va. 364, 58 S. E. 572. The demurrer was submitted without argument, and the defendant did not present to the lower court, either in its demurrer or in argument, the specific ground here relied upon. It was properly overruled, because under section 3272 of the Code, “no defect or imperfection in the declaration, whether it has heretofore been deemed mispleading or insufficient pleading or not, shall be regarded unless there shall be omitted something so essential to the action or defense that judgment according to law and the very right of the cause cannot be given.”
It is claimed that the act of March 27, 1914 (Acts 1914, p. 641), providing that “in any suit or action hereafter instituted, the court may at any time, in furtherance of justice, upon such terms as may be just, permit any proceeding or pleading to be amended, or material supplemental matter to be set forth in an amended or supplemental pleading. The court, at every stage of the proceeding, must disregard any error or defect in the proceeding which does not affect the substantial rights of the parties,” is clearly not permissive but mandatory, as to such amendments, and that the word “may” as first used in that statute should be construed as an imperative.
We cannot agree with this suggestion. It is true that the trial courts must always permit amendments in furtherance of justice, and upon refusal to do so such action may be reviewed by this court; but such amendments are not matters of right, and should not be permitted to delay, impede or embarrass the administration of justice. So far as the amendment to the special plea of set-off refers to
These assignments raise substantially the same questions which wrere presented in various forms during the trial. The defendant claimed that it had the right to set-off and recover unliquidated damages, under Code section 3299, growing out of contract No. 2. This contract had been •fully performed and paid for before contract No. 3 had been let or commenced, and after the work done under contract No. 1 had been substantially performed. This contract No. 2 (as has been previously stated) was in no
We do not, of - course, mean that any improper inspection, either by Carneal & Johnston or by their assistant, could relieve the contractor of the obligation of the contract, but only that Moore having acted as the representative of the architects, by their direction, and with the knowledge and acquiescence of the defendant, the contractor was justified in accepting Moore as the duly authorized representative of the architects during construction. Moore," it must be rememberel, never issued any certificates upon which the payments were based, nor did he ever undertake to approve the completed work.
The vital questions involved are questions of fact. The defendant claimed that the contractor had failed to perform its contract, and that the engineers refused and were justified in refusing to approve and accept the work; and the evidence in the record to sustain these views is most impressive. These claims of the defendant were fairly and sufficiently presented to the jury in the instructions, and they were told that if the work had not been done according to the required specifications and had not been accepted,
Affirmed.
Reference
- Full Case Name
- Richmond College v. Scott-Nuckols Co., Inc.
- Cited By
- 14 cases
- Status
- Published
- Syllabus
- 1. Contracts—Working Contracts—Independent or Dependent Contracts—Case at Bar.—In an action by a contractor against a college for a balance due for material and labor done in the construction of water and sewer lines upon the college property, there were three separate contracts. While all of the work was done in the construction of such sewer and water system, the contracts were let at separate times, under different specifications and upon competitive bidding. They might just as well have been entered into with three separate contractors as with one, and no reference is made in either one of the contracts to either of the others. They were, therefore, clearly independent and not interdependent agreements. 2. Demurrer—General Demurrer—Specification of Grounds—Case at Bcur.—In an action of assumpsit brought by a contractor upon two contracts for work done in installing a water and sewer system on defendant’s land, the original declaration contained the common counts in assumpsit. The particulars of the claim and the amended declaration showed that the contractor was claiming a balance of $238.29 for work done under contract No. 1 ($8,050.61 having been paid thereon) ; $1,139.46 under contract No. 3 ($1,000 having been paid thereon), and $10 for sand and stone furnished. There was a general demurrer to the declaration and to each count thereof, which for specification stated, “that the several matters and things set out in the contracts made a part of said amended declaration and shown to be conditions precedent to a right of action and recovery, are not alleged or averred in such manner as to give plaintiff the right to sue, nor are such other matters alleged as legally excuse the failure to allege and aver such conditions precedent.” Held: That this specification was no more than an assertion that the declaration was insufficient in law. 3. Demurrer—Stating Grounds of Demurer—Section 3271 of the Code of 1901.—The rule which applies under section 3271 of the Code of 1904 in cases where the plaintiff moves the court to require the defendant to state the grounds of demurrer, requires that they shall be stated specifically, and that no ground shall be considered other than those so stated. 4. Working Cotracts—Declaration—Sufficiency.—Where the declaration of a contractor suing for a balance due on work done by him, sufficiently advised the defendant of the nature of the contractor’s claim, and although it did not in specific terms charge fraud or bad faith on the part of the architects who were required by the working contracts and specifications to approve the work, did so in substance, the declaration is sufficient under section 3272 of the Code of 1904. 5. Working Contracts—Architect’s Certificate—Excuse for Failure to Produce.—Actual fraud is not the only excuse which may be shown for failure of the contractor to produce the architect’s certificate, and it is well recpgnized that such a certificate is not necessary if it is capriciously or arbitrarily withheld. If the refusal of the certificate is based upon false or fraudulent information, failure to produce it does not bar a recovery. 6. Amendments—Acts 191b, p. GUI-—Whether Mandatory or Directory.—The act of March 27, 1914 (Acts 1914, p. 641), providing that the trial court “may” at any time permit any proceeding or pleading to be amended, is not mandatory but permissive. The trial courts must always permit amendments in furtherance of justice, and upon refusal to do so such action may be reviewed by the Supreme Court of Appeals; but such amendments are not matters of right, and should not be permitted to delay, impede or embarrass the administration of justice. 7. Amendments—Acts 191b, p. Gbl■—Whether Mandatory or Directory—Plea of Set-Off.—In an, action by a contractor for a balance due for work and labor done, defendant filed a special plea of set-off claiming damages for defective work done. After all the evidence in chief had been introduced on both sides, and during the examination of the witnesses put on by the plaintiff in rebuttal, the defendant moved for leave to amend its special plea of set-off by inserting an averment of the plaintiff's insolvency, and that plaintiff violated the contracts by doing its work under them in an unworkmanlike manner, and that plaintiff covered up and concealed from view such defective and faulty work, whereby defendant was misled. • Held: That the court correctly exercised its discretion in refusing to allow the plea to be amended at that time. 8. Set-Off, Recoupment and Counterclaim—Subject Matter of Set-Off.—Under section 3299, Code of 1904, defendant cannot avail himself of a plea of set-off and counterclaim unless such claim grows out of the contract sued on. Accordingly, in the instant case, it was held that where plaintiff, a contractor, sued defendant for a balance due for work done under two contracts, defendant could not set-off damages suffered by it under an independent contract with plaintiff, which had been fully and completely performed. 9. Working Contracts—Inspection by Engineer—Assistants of Engineer—Case at Bar.—Where a contract for installing a water and sewer system provided that the engineers of the property owners should be the sole arbitrators to decide all questions and disputes, while it is true that the engineers, upon final arbitration, could only act in person, yet it is not true that the engineers could not employ expert assistants to superintend and direct the construction in accordance with the contracts. Such work requires constant supervision and inspection during its progress, for it is soon concealed so as to make proper inspection thereafter impossible. There is no other practical method. And even if the contract did not warrant inspection and supervision by an assistant of the engineers, acquiescence, by the landowner in such action of the assistant would amount to a waiver of its right to require the engineers’ personal inspection and supervision. 10. Appeal and Error—Reversal—Verdict Contrary to the Law and the Evidence.—Although the Supreme Court of Appeals may have grave and reasonable doubts as to whether the jury have correctly interpreted conflicting parol evidence, this in a civil case is insufficient to justify a reversal on the ground that the verdiet is contrary to the law and the evidence. In order to justify, a reversal on that grounl, the verdict must be plainly against the evidence, or without evidence to support it.