Adams v. Tri-City Amusement Co.
Adams v. Tri-City Amusement Co.
Opinion of the Court
delivered the opinion of the court.
C. E. Adams (hereinafter called the contractor) erected a theatre building in the city of Hopewell for the Tri-City Amusement Company, Inc. (hereinafter called the company) . After the completion of the structure the defendant filed his mechanic’s lien, claiming that there was a’balance •due him of $5,893, and thereafter instituted this suit to enforce such lien.
The history of the transaction appears to be, that the original contract in writing was entered into on February 2, 1916, and provided for the erection of a building at the price of $7,335; thereafter the company authorized the contractor to build a basement as an addition to the building for $4,407, and certain extra work was directed. The decree of the court which is complained of reduced the claim of the contractor to the sum of $1,977.60 and of this reduction the contractor is here complaining.
The walls, however, fell a second time, after the frame superstructure had been erected, and the larger part of the amount here in controversy grows out of the claim of the contractor for the additional cost of erecting these walls the third time. For the contractor it is shown that he had strictly followed the plans and instructions of the architect ; that after the accident there was a meeting of the directors ; and that at that meeting he told them that he could build a wall which would stand in that place, but that it would be necessary to make it three feet wide at the bottom, instead of eighteen inches, as the architect had planned, and that it should be gradually narrowed to the width of eighteen inches at the top; that he estimated the cost of the additional labor and material which would be required to make this change at from $1,200 to $1,600, and that he would undertake to do the work, which involved the removal of a large quantity of earth and the cleaning off of bricks of the old wall, as well as the additional material and labor, at its actual cost plus ten per cent, thereon; and that this was agreed to. In a short while he asked for some
“Hopewell, Va., August 21st, 1916.
“Mr. C. E. Adams,
Hopewell, Va.
“Dear Sir:
“You are hereby authorized to proceed with the following work as extra work at the Marcelle Building in Hopewell, Va.
“Re-erect the walls that caved in and take down walls that are not safe, at actual cost and 10 per cent, commission.
“Order Frames for the Theatre as per sketch furnished you same not cost more than $75.00 (5 frames in all).
“Order Electric Fixtures for Theatre as selected by me, same not to cost over $300.00 (10 Brakets, 5 Auditorium Ceiling Lights & 6 Lobby Lights, 4 Exit Lights.)
“Wire Building for six intercommunicating phones.
“Wire sidewalk for two street lights.
“The above electric fixtures are to be baught for us at cost price anad same is being done for us by you as an accommodation.
“Yours truly,
“TRI-CITY AMUSEMENT COMPANY, INC.,
“S. A. KIPPAS, Gnl. Mgr.”
He thereupon proceeded with the work, relying upon the assurance of that letter that he would .receive the actual cost of such re-erection with ten per cent, commission thereon added. This letter was promptly shown to Saunders, the treasurer of the company, and according to Kippas it was in substance authorized and directed by all of the other
It appears, however, that under one of the contracts the basement walls were to be water-proofed, and that because of the sudden caving in of the earth against the wall this was not done. There is also testimony tending to show that there were leaks in the roof and some other defects, though the building has been accepted and is in use by the company. For these defects there should be an allowance in favor of the company, and in our opinion this allowance should be $500.
The decree will, therefore, be amended, and the amount adjudged to be due the contractor increased from $1,977.60 to the sum of $5,393, with' interest thereon from the 13th day of January, 1917, and costs.
The cause will be remanded for such further proceedings as may be necessary to effectuate the views herein expressed.
Amended a\nd remanded.
Reference
- Full Case Name
- Adams v. Tri-City Amusement Company, Inc.
- Cited By
- 12 cases
- Status
- Published
- Syllabus
- •1. Working Contracts—Fall of Walls—Liability of Contractor.— The walls of a building, which was being erected pursuant to a written contract, fell, and it appeared from the evidence of the architect, who, under the plain terms of the contract, was the agent of the company (the landowner), to direct the work in its details, that although he was at first of the opinion that the falling of the walls was due to the fault of the contractor, he changed his opinion and in accordance with the agreement of the parties directed the re-erection of the walls at the joint expense of the company and the contractor. It was plain that the design of the wall was inadequate, by reason of the low, wet character of the ground, and for such a defect a building contractor could not be held responsible, for it is his duty to follow the plans and specifications furnished as his guide by the architect. 2. Working Contracts—Falling Walls — Agreement for Reconstruction.—Where through the faulty design of the architect a wall fell, it was claimed by the landowner that because the contract was for the erection of the complete building, the loss arising from such an accident should fall upon the contractor. But in the instant case, where the loss was caused, not by any fault of the contractor, but because of the defective plans of the architect, the walls having been re-erected by the direction of the architect, a settlement and agreement imposing half the cost upon the contractor and half upon the owner cannot be said to be inequitable. This adjustment of an unanticipated difficulty, in which the interests of the owner required some prompt adjustment is further supported by the testimony of the architect and the contractor to the effect that the president, general manager and directors of the owner were informed of and agreed to this division of the expense of such re-erection. 3. Working Contracts—Agent of Landowner—Authority of General Manager of Company.—A company which had entered into a contract for the erection of a building is chargeable with notice of a letter written by its general manager to the contractor authorizing certain extra work and providing for payment of the same, especially in consideration of the fact that the general manager was the original promoter of the company; that the pla'ns and contract for the building were originally made in his name; that he ordered many extras during the construction of the work; and that he did all these things with the knowledge of the president and directors. 4. Working Contracts—Arbitration and Award—Withdrawal from Arbitration.—A working contract provided for arbitration in case of disputes. Pursuant to this agreement, three building experts were chosen as arbitrators, and when they met the arbitrator chosen by the landowner, by its direction, withdrew. The other arbitrators proceeded with their investigation and awarded the contractor the full amount of his claim. The two arbitrators who made the award were examined as witnesses in the case, and a close scrutiny of their testimony failed to indicate the slightest bias or prejudice against the landowner. Held: That the record disclosed no sufficient justification for the withdrawal by the landowner from the arbitration. 5. Working Contracts—Implied Contract—Reconstruction.—When walls fell through a defect in the architect’s plans and there was no defect in the construction for which the contractor was responsible, the contractor is fairly entitled to recover the value of additional work done for the benefit and advantage of the landowner, and accepted and utilized by the landowner, even without an express contract for such additional work. 6. Working Contracts—Failure of Contractor to Perform.—Where under the working contract the basement walls were to be water-proofed, and because of the sudden caving in of the •earth against the wall, without fault of the contractor, this was not done, and . there were leaks in the roof and some other defects. Held: That in a suit to foreclose contractor’s mechanic’s lien, an allowance will be made for such defects and for the waterproofing of the basement walls. 7. Jurisdiction—Mechanics’ Liens—Receiver.—In a suit to foreclose a mechanics lien against a corporate owner in the Circuit Court of the city of Hopewell, the trial court, after determining the amount due, decreed that instead of enforcing the lien by further proceedings in the case, the complainant should intervene by petition in a suit then pending in the Corporation Court of the city of Hopewell, in which a receiver had been appointed who at that time held the property of the company. If the suit in the Corporation Court of the city of Hopewell was instituted before this suit, then there was no error in requiring the contractor to intervene by petition in that suit; but if this suit was first instituted, the Circuit Court of the city of Hopewell should proceed with this case and give the contractor complete relief by the enforcement of his lien against the property of the company; or for greater convenience one of the causes should be removed to the other court and both thereafter heard together.