Smith Mountain Supply v. Windstar Prop.
Smith Mountain Supply v. Windstar Prop.
Opinion
In these appeals, we determine whether the trial court erred in declaring invalid and unenforceable two mechanic's liens without allowing the lien claimant to present evidence that its inclusion in the memoranda of charges outside the 150-day limitation period in Code § 43-4 was an "inaccuracy" within the meaning of Code § 43-15.
I
The relevant facts are not in dispute. Smith Mountain Building Supply, LLC (Smith Mountain), supplied materials to a general contractor for the construction of a home on each of two properties owned by Windstar Properties, LLC (Windstar). Smith Mountain furnished materials to the jobs from June 24, 2005, to March 9, 2006. March 9, 2006 is the last day Smith Mountain supplied materials to the jobs. The 150-day limitation period prescribed by Code § 43-4, therefore, is October 10, 2005, through March 9, 2006.
Smith Mountain filed its memoranda of mechanic's lien on June 9, 2006. The amount claimed on one of the memoranda is $15,253.44. The amount claimed on the other of the memoranda is $51,835.34. The charges for materials properly recoverable during the 150-day limitation period are $1,422.80 and $13,593.65, respectively.
II
Smith Mountain filed two actions against Windstar to enforce its mechanic's liens. Windstar filed motions for summary judgment, asserting that the mechanic's liens sought to be enforced by Smith Mountain were invalid under Code § 43-4 because they included sums due for materials furnished more than 150 days prior to the last day on which materials were supplied to the jobs preceding the filing of the memoranda. Windstar relied upon
Carolina Builders Corp. v. Cenit Equity Co.,
Smith Mountain opposed the motions for summary judgment, asserting that its inclusion of sums due for materials furnished outside the limitation period is an inaccuracy that does not invalidate the liens under Code § 43-15 and that it was entitled to present evidence that its inclusion of such sums was an inaccuracy, rather than a mistake. Smith Mountain relied upon
Reliable Constructors, Inc. v. CFJ Properties,
The trial court heard the two actions together and, upon the pleadings, memoranda of the parties, and argument of counsel, granted Windstar's motions for summary judgment and dismissed Smith Mountain's actions to enforce the mechanic's liens. The trial court determined that the inclusion of sums for materials supplied outside the 150-day limitation period rendered the mechanic's liens invalid and unenforceable. The trial court also determined that Reliable Constructors did not apply. We awarded Smith Mountain this appeal.
III
Code § 43-4 provides, in pertinent part, that "no memorandum filed ... shall include sums due for labor or materials furnished more than 150 days prior to the last day on which labor was performed or material furnished to the job preceding the filing of such memorandum." Code § 43-15 provides as follows:
No inaccuracy in the memorandum filed, or in the description of the property to be covered by the lien, shall invalidate the lien, if the property can be reasonably identified by the description given and the memorandum conforms substantially to the requirements of §§ 43-5, 43-8 and 43-10, respectively, and is not wilfully false.
On appeal, Smith Mountain contends that it should have been permitted to present evidence to show that its inclusion of charges outside the 150-day limitation period was an "inaccuracy" within the meaning of Code § 43-15. Smith Mountain also contends that the two cases relied upon by the parties, Carolina Builders and Reliable Constructors, "reflect two divergent rationals [sic] which cannot be reconciled." Smith Mountain asserts that substantial compliance is the appropriate standard to apply in the present case.
Windstar contends that Code § 43-4 must be strictly construed and that Smith Mountain's inclusion of charges outside the limitation period renders its mechanic's liens unenforceable. Windstar also contends that Code § 43-15 is not applicable in, and that Reliable Constructors is distinguishable from, the present case.
IV
We do not agree with Smith Mountain that Carolina Builders and Reliable Constructors cannot be reconciled, and we agree with Windstar and with the trial court that, pursuant to Carolina Builders, the mechanic's liens sought to be enforced by Smith Mountain are invalid and unenforceable. Therefore, we will affirm the trial court's judgments invalidating the mechanic's liens.
In
Carolina Builders,
the builder filed a memorandum of mechanic's lien for sums owed to it for materials it had supplied for the construction of a residence.
In
Reliable Constructors,
a subcontractor that had supplied labor and materials for plumbing and mechanical work to a travel plaza construction project filed a memorandum of mechanic's lien, which it sought to enforce.
In reaching our holding in
Reliable Constructors,
we noted that "[t]he word `inaccurate' is defined as: `not accurate: as ... containing a mistake or error.'"
Id. at 282-83,
In the present case, Smith Mountain violated one of the prerequisites required by Code § 43-4 in order to perfect its mechanic's liens. Code § 43-15 has no application.
V
We hold, therefore, that the inclusion in the memoranda of charges for materials supplied outside the 150-day limitation period in Code § 43-4 rendered Smith Mountain's mechanic's liens invalid and unenforceable and that the trial court did not err in so ruling. Accordingly, we will affirm the judgments of the trial court.
Affirmed.
Reference
- Full Case Name
- Smith Mountain Building Supply, LLC v. Windstar Properties, LLC.
- Cited By
- 3 cases
- Status
- Published