In re Construction & Operation of a Meteorological Tower
In re Construction & Operation of a Meteorological Tower
Opinion of the Court
¶ 1. Travis Belisle appeals the Public Utility Commission's (PUC)
¶ 2. The factual and procedural history is as follows. In 2010, Belisle consulted with Vermont Environmental Research Associates (VERA) to monitor the wind on top of the ridge on his property. On November 1, 2010, Belisle filed a document with the Swanton town clerk entitled "Declaration of Planned Community for Rocky Ridge." In the document, Belisle stated he "may develop ... an electrical generation wind farm" on his property. In January 2011, Belisle consulted with VERA for a proposal to install a meteorological tower on the property to see what the wind was like on the ridge. In January 2012, a tower standing 132 feet high and measuring six inches in diameter was installed on Belisle's property. Belisle did not obtain a CPG before the installation.
¶ 3. In July 2015, neighbors of Belisle filed a letter with the PUC alleging a meteorological tower had been constructed on Belisle's property. Shortly thereafter, the PUC directed DPS to investigate the neighbors' allegations. Later that month, DPS recommended that the PUC open an investigation regarding the construction of the tower without a CPG, which it did. A lengthy procedural history followed, ultimately resulting in DPS's filing a motion for partial summary judgment and Belisle filing a cross-motion for summary judgment. Belisle claimed the PUC lacked jurisdiction over his construction of the tower because he had no specific wind generating facility in mind at the time he constructed the tower, and thus no CPG was required under 30 V.S.A. § 246. Belisle argued that for a CPG to be required under § 246, a proposed tower must meet three elements: (1) the installation is temporary; (2) the installation is for the purpose of determining a particular location's suitability for a wind turbine; and (3) the future wind turbine will be grid connected. DPS claimed Belisle's admission that he constructed the tower to "see[ ] if the wind on the ridge would be right for wind turbines that generate electricity" was sufficient to trigger the need for a CPG pursuant to 30 V.S.A. § 246.
*1233¶ 4. The PUC granted DPS's partial summary judgment motion and denied Belisle's. In rejecting Belisle's position and his proposed standard for determining the need for a CPG in the meteorological-tower context, the PUC found that an intent to construct a meteorological tower to assess wind resources for a prospective wind project was sufficient to trigger the CPG requirement under § 246. The PUC reasoned that a CPG was required because Belisle "erected the tower ... for use in developing an electrical generation wind farm thus placing [him] under the [PUC]'s jurisdiction pursuant to Title 30" and that Belisle "did not obtain a [CPG] as required by 30 V.S.A. § 248 prior to erecting the tower." (Quotation omitted.) The PUC thus found Belisle in violation of §§ 246 and 248 and scheduled further proceedings to determine the appropriate penalty and remedial action.
¶ 5. An evidentiary hearing was held in September 2017 regarding the penalty to be assessed as a result of the violation and to consider what, if any, remedial action would be required. DPS asserted that the provisions of 30 V.S.A. § 246, which incorporate provisions of 30 V.S.A. § 248, made § 248 applicable to this permit violation. As a result, DPS further asserted the appropriate penalty should be assessed under 30 V.S.A. § 30(a)(1), which applies to violations of § 248. Although contesting any violation, Belisle claimed any appropriate penalty should be calculated under 30 V.S.A. § 30(a)(2), which he claimed applied to violations of § 246. A violation subject to § 30(a)(1) has a maximum penalty of $ 40,000, absent continuing violation, while a violation subject to § 30(a)(2) has a maximum penalty of $ 10,000. The PUC reasoned that because § 246 made the erection of a wind tower to determine the suitability of the site for a grid-connected wind generating facility subject to the supervision of the PUC under § 248, the penalty should be assessed according to § 30(a)(1). After considering the factors in § 30(c), which are applicable to any violation of § 30(a), the PUC imposed a fine of $ 10,000. The PUC also ordered remedial measures at the tower site.
¶ 6. Belisle appealed, renewing his argument that the PUC lacked jurisdiction over his establishment of the meteorological tower because no CPG was required by § 246 or otherwise and that if a CPG was required, then the PUC erred in calculating the appropriate penalty. He also makes claims of factual errors, which we will discuss in context throughout our analysis.
I. Standard of Review
¶ 7. As explained above, the PUC considered the matter at hand in two phases-first when granting partial summary judgment in favor of DPS on the issue of whether a violation had occurred and second with an evidentiary hearing when determining the appropriate penalty for Belisle's violation.
¶ 8. On appeal, this Court reviews the grant of summary judgment de novo, applying the same summary judgment standard as the PUC applies in the first instance-summary judgment is appropriate if there is no genuine issue of material fact and a party is entitled to judgment as a matter of law. Farrell v. Vt. Elec. Power Co.,
¶ 9. Regarding our review of legal issues within the PUC's area of expertise, this Court reviews PUC decisions with "great deference to the [PUC's] expertise and judgment," allowing for "a strong presumption of validity to the [PUC's] orders." In re UPC Vt. Wind, LLC,
¶ 10. Finally, the PUC's decision to set and impose a penalty is within its discretion and will be upheld as long as it "shows a thorough and fair evaluation of the various relevant factors." Citizens Utils. Co.,
II. Sections 246 and 248
¶ 11. First, Belisle argues that § 246 rather than § 248 of Title 30 governs the CPG requirements for the establishment of a temporary meteorological tower. Here, the PUC applied §§ 246 and 248 to determine whether it had jurisdiction over the matter at hand and whether Belisle's project required a CPG. To the extent that there has been confusion regarding whether to apply § 246 or § 248, or some combination of the two, when determining PUC jurisdiction and CPG requirements for temporary meteorological towers, we now clarify that § 246 governs such inquiries, and we reject the PUC's analysis to the contrary.
¶ 12. We begin with our principles of statutory construction. "The bedrock rule of statutory construction is to determine and give effect to the intent of the Legislature." In re C.S.,
¶ 13. Here we are construing both § 246 and § 248. The plain language of § 246 clearly indicates that § 246 governs the CPG process for meteorological towers. The title of § 246 is "Temporary siting of meteorological stations"; § 246(a) states, "in this section, a 'meteorological station'
*1235consists of one temporary tower ... to collect and record wind speed, wind direction, and atmospheric conditions"; and § 246(b) directs the PUC to establish "standards and procedures governing application for, and issuance or revocation of, a certificate of public good." Thus, according to our rules of statutory construction, we accept the plain language of § 246 and proceed no further.
¶ 14. What is less clear is whether § 246 governs temporary meteorological stations alone or whether § 248 also applies. Section 246 indicates that the PUC should create a separate, streamlined process governing CPGs for temporary meteorological towers, but it also references § 248 in doing so, drawing on § 248's criteria. 30 V.S.A. § 246(b). And § 248(a)(2)(A) directs that "no company ... may begin site preparation for or construction of an electric generation facility" without first obtaining a CPG.
¶ 15. Given this ambiguity, we must turn to the traditional tools of statutory construction to discern the intent of the Legislature. See Tarrant,
¶ 16. First, the language of § 246 indicates that it operates alone. As we explained, § 246 is not unambiguous, but its language strongly suggests that the Legislature did not intend § 246 to operate in conjunction with § 248. Rather, it appears that § 246 incorporates certain environmental criteria from § 248, but otherwise operates as an independent scheme. It references § 248's criteria in § 246(b), but it creates a distinct, independent process for obtaining a CPG, which is specifically designed for temporary meteorological towers.
¶ 17. This interpretation is further supported by the distinct nature of the projects approved pursuant to §§ 246 and 248. Temporary meteorological stations generate data, not electricity, and they may or may not require a CPG depending on whether they are intended to help develop a future grid-connected project. They do not pose the same risk of negative impacts as the grid-connected electricity-generation projects regulated by § 248. The PUC's 2010 Order acknowledges this distinction. See 2010 Order at 2 (explaining that "[t]he (PUC's) conditional waiver of § 248 criteria is based on the limited potential for impact presented by the majority of temporary meteorological stations under those criteria"); see also § 248(b) (listing criteria PUC must consider when issuing CPG for electricity-generating projects, including regional development, demand for electricity service, and stability and reliability of electricity system).
¶ 18. The penalty provisions under 30 V.S.A. § 30 also support our analysis. As explained above, violations of § 248 have significant impact on electricity-generation in Vermont. Accordingly, § 30(a)(1) provides a penalty scheme to account for the severity of these violations, allowing a maximum penalty of up to $ 40,000. In contrast, § 30(a)(2) requires a smaller penalty for violations of provisions with less impact, such as violations of § 246.
¶ 19. We also find it helpful to be mindful of the history of §§ 246 and 248. Section 248, originally enacted in 1969, establishes requirements for CPG approval for in-state electric transmission and generation projects.
¶ 20. Based on the language, history, and context of the statutory scheme as a whole, we conclude that the Legislature intended for § 246 to operate as an independent scheme from § 248. Therefore, § 246 governs our analysis as to whether a CPG was required for Belisle's temporary meteorological station. Additionally, failure to comply with § 246 would result in a violation of § 246, not § 248.
III. Whether Belisle's Project Is a "Temporary Meteorological Station" Pursuant to § 246
¶ 21. The next issue we must address is whether the PUC erred in granting DPS's motion for summary judgment based on the PUC's conclusion that Belisle's meteorological tower qualified as a "temporary meteorological station."
¶ 22. First, we must review both the definition of a "temporary meteorological station" pursuant to § 246 and the standard applied by the PUC to determine whether a project meets this definition. The standards and procedures the PUC promulgated in 2010 define a "temporary meteorological station" as "a temporary tower, which may include guy wires, and attached instrumentation to collect and record wind speed, wind direction, and atmospheric conditions, constructed or installed in order to determine the suitability of a site for the location of a grid-connected wind turbine." 2010 Order at 6 (emphases added).
¶ 23. Prior to § 246 and the 2010 Order, the PUC concluded that a meteorological tower that is "reasonably related" to the potential operation of a wind generation facility is within the jurisdiction of the PUC pursuant to § 248. UPC Wind Mgmt., LLC, No. 6884 at 6 (Vt. Pub. Serv. Bd. April 21, 2004), https://puc.vermont.gov/sites/psbnew/files/orders/2004/6884fnlorder.pdf [https://perma.cc/3FX9-B3BG] (adopting "reasonably related" standard articulated in Attorney General's 1971 advisory opinion, rather than more stringent *1240"directly related" standard, but concluding that when tower is "necessary precursor" to wind generation project it satisfies both standards); see also Vt. Elec. Coop., Inc., No. 7201 at 7 (Vt. Pub. Serv. Bd. Aug. 24, 2006), https://puc.vermont.gov/sites/psbnew/files/orders/2006/7201fnl.pdf [https://perma.cc/5ECH-K3 ZQ] ("[The] reasonably related standard governs the [PUC]'s review of Section 248 projects."). However, the "reasonably related" standard has not been applied consistently or clearly in reviewing §§ 248 and 246 applications. See Endless Energy Corp., No. 6154,
¶ 24. Following the enactment of § 246, the 2010 Order implicitly adopted the "reasonably related" test for use in § 246 applications, and the PUC has applied the "reasonably related" test in reviewing CPG requirements for temporary towers, including the matter at hand. See 2010 Order at 5 (explaining PUC retained § 3.1(b) of application to help application reviewers "determine whether a meteorological station is reasonably related to a potential generation facility, and thus under [PUC] jurisdiction" (emphasis added)); Meteorological Tower at 700 Kidder Hill Road in Irasburg, Vt., No. 8585 at 5 (Vt. Pub. Util. Comm'n June 22, 2018) (applying "reasonably related" standard in context of § 246 and stating that "[t]he purpose behind the construction of a MET tower is important for determining whether the [PUC] has jurisdiction over a tower because for jurisdiction to attach the tower must be 'reasonably related' to a generation facility"); Constr. & Operation of a Meteorological Tower in Swanton, Vt., No. 8561,
*1241¶ 25. In sum, we conclude that the application of the "reasonably related" standard in the context of § 246 proceedings comports with PUC precedent and the history of the relationship between §§ 248 and 246. A temporary meteorological tower is within PUC jurisdiction under § 246 if it is "reasonably related" to construction or establishment of a grid-connected wind generation facility.
¶ 26. As with many things, the devil is in the details. To date, neither the PUC nor this Court has expressly outlined a consistent method for determining when a temporary meteorological tower is "reasonably related" to a grid-connected wind generation facility. We do so here. To establish that a temporary meteorological tower satisfies the "reasonably related" standard and is within PUC jurisdiction under § 246, an objective review of the circumstances must demonstrate that the tower was constructed or installed to help determine the site's suitability for a grid-connected wind turbine. Such inquiries will be fact intensive and determined on a case-by-case basis. See Thompson v. Hi Tech Motor Sports, Inc.,
¶ 27. Based on the test outlined above and the undisputed facts before the PUC, we agree with the PUC's conclusion that, as a matter of law, Belisle's tower was "reasonably related" to the establishment of a potential grid-connected wind generation facility because an objective review of the circumstances surrounding the tower's construction demonstrates that it was established to help assess the site's suitability for a future grid-connected wind *1242turbine. The PUC considered Belisle's actions, both prior to and following the establishment of the temporary meteorological tower in 2012, as well as Belisle's statements both before and after the investigation started when determining the tower's relationship to a potential grid-connected wind facility. Several of Belisle's actions and outward manifestations of intent were of particular relevance to the PUC's analysis.
¶ 28. First, prior to erecting the tower, in November 2010, Belisle filed a document with the town clerk in Swanton, Vermont, entitled "Declaration of Planned Community for Rocky Ridge," which stated that Belisle "may develop ... an electrical generation wind farm" on his property. Second, in January 2012, Belisle received a proposal from VERA to install a meteorological tower. He established the tower at issue shortly thereafter. Finally, Belisle's stated purpose for erecting the tower was to determine "if wind on the ridge would be right for wind turbines that generate electricity." The PUC concluded that these facts, taken in context, demonstrated that Belisle's temporary tower was established to help assess the site's suitability for a potential grid-connected project.
¶ 29. Belisle argues that his project does not satisfy the "reasonably related" standard because he had no specific plans to create a grid-connected wind turbine in 2012 when he erected the temporary tower. We disagree-Belisle's declaration regarding plans for the Rocky Ridge Community, his consultation with VERA, his establishment of the temporary tower for data collection, and his statements regarding his purpose in erecting the tower establish as a matter of law that his tower was installed to help determine the site's suitability for a grid-connected wind project.
¶ 30. Belisle also argues that his statements made after the investigation started, which indicated that he had no specific plans to construct a grid-connected wind project at the time he established the temporary tower, are dispositive to our inquiry. In his prefiled testimony and responses to DPS's information requests, Belisle explained that he established the tower to "see what the wind was like on top of the ridge" and to "see if the wind on the ridge would be right for wind turbines that generate electricity." When asked directly if he installed the tower for the purpose of determining the suitability of the site for a grid-connected wind project, Belisle said, "No," and stated that he "had no specific plans or project in mind." The PUC concluded that these statements indicated that, though Belisle had no specific plans at the time he constructed the tower, he was curious about the type of wind on the ridge and he was open to discovering what type of project, if any, would be feasible-including a grid-connected wind project.
¶ 31. While project proponents' outward statements regarding their subjective intent behind establishing a temporary tower may be a factor in demonstrating whether a tower was constructed to assess a site's suitability for a potential grid-connected wind facility, such statements must be assessed objectively in the context of the entire project. To hold otherwise would enable a party to escape both an impartial assessment of the setting of the case under the "reasonably related" standard and summary judgment by simply denying any intent after the fact. Meiri v. Dacon,
¶ 32. The PUC correctly concluded that, even in the context of a motion for summary judgment and giving his statements full credence as the nonmovant, Belisle's denial does not create an issue of material fact considering the entire setting of the case. Drawing any doubts or inferences about Belisle's plans at the time he established the tower in his favor, Belisle's statements demonstrate that he had no specific plans for a grid-connected wind turbine, but he was considering a wind project on the ridge and using the temporary tower to determine what type of project would be feasible. Therefore, even taking his statements as true, the PUC had sufficient information to conclude that, regardless of Belisle's intent, the tower was constructed to establish the site's suitability for a potential grid-connected project. Taken in context of the entire case, Belisle's assertion that he did not have specific plans for a particular type of generating facility when he established the tower is insufficient to affect the outcome of the analysis or create an issue of material fact. O'Brien v. Synnott,
¶ 33. Based on Belisle's statements, actions, and outward manifestations of intent-including his application for the Rocky Ridge Community, his consultations with VERA, and his stated interest in determining what type of wind was available on the ridgeline for wind turbines-the PUC determined that Belisle's tower was "reasonably related" to determining the site's suitability for a grid-connected wind turbine. We conclude that, based on the circumstances, Belisle's tower meets the definition of a "temporary meteorological station" pursuant to § 246. Belisle's tower falls within the PUC's jurisdiction under § 246 and, accordingly, required a CPG prior to its construction. The undisputed facts established DPS was entitled to summary judgment.
¶ 34. Appellant challenges several of the PUC's evidentiary rulings and raises additional arguments opposing the PUC's jurisdiction, which we do not find persuasive.
¶ 35. First, Belisle contests certain facts that the panel determined were undisputed. He argues that the PUC's statement of undisputed fact that VERA was performing a "site suitability assessment" on the ridge has no support in the record. He also argues that the PUC's finding during the penalty phase that the data from the tower was "not dispositive of all project funding and development concerns," but "was necessary to design and finance the proposed Swanton Wind project," is erroneous because the data that the station collected were "not sufficient to design or finance a wind project" like Swanton Wind and "[a]dditional data" were needed. Belisle's statement of undisputed facts explained that he received a proposal from VERA to install a meteorological station on his property and that he erected the tower to collect data and see what the wind was like on top of the ridge. Therefore, whether VERA conducted a "site suitability assessment" does not impact the PUC's conclusion that Belisle was interested in using the temporary tower to assess the wind resources for a potential wind project on the ridge. The undisputed facts established *1244that DPS was entitled to summary judgment. Similarly, whether data from the tower were directly used to support the Swanton Wind project was discussed during the penalty phase, not the summary judgment phase, and does not impact our conclusion on the propriety of summary judgment on liability under § 246.
¶ 36. Regarding the PUC's jurisdiction pursuant to § 246, Belisle argues that if an owner does not have specific plans for a grid-connected electric-generation facility, then the owner cannot complete § 3.1(b) of the § 246 Application Form, exempting the project from § 246's requirements. See 2010 Order at 5 (outlining Application for a Certificate of Public Good for Temporary Meteorological Stations, Pursuant to 30 V.S.A. §§ 246 and 248, Section 3.1(b)). Section 3.1(b) allows property owners to "[p]rovide an explanation of the temporary meteorological station's relationship to the construction of an electrical generation facility that may be proposed for that location and a brief description of that facility."
¶ 37. Finally, Belisle argues that his project should not be penalized because "similar public-funded installations" through the Vermont Anemometer Loan Program (ALP) did not require a CPG. ALP was a program administered by the Vermont Technical College through a grant from the DPS in 2005 to fund wind-assessment equipment for residents, farms, and businesses considering installation of wind-power systems. However, the prior existence of the ALP, of which Belisle's tower was not a part, does not excuse Belisle's failure to comply with § 246's requirements to obtain a CPG for temporary meteorological towers, which occurred well *1245after the PUC issued clear guidance in the 2010 Order. Belisle was required to obtain a CPG for his tower, and a reading of § 246 or the 2010 Order would have notified him of this obligation.
IV. Penalty
¶ 38. The PUC determined that Belisle violated § 248 and assessed a $ 10,000 fine pursuant to 30 V.S.A. § 30(a)(1). Belisle advocates that if the PUC determined that he violated § 246, then it should have applied 30 V.S.A. § 30(a)(2) to determine the appropriate fine. We concur that § 30(a)(2) provides the civil penalty for violations of § 246, and we accordingly remand this issue to the PUC to recalculate the fine based on § 30(a)(2).
¶ 39. Section 30(a) of Title 30 provides two categories of civil penalties for violations of that title-subsections (a)(1) and (a)(2). Subsection (a)(1) applies when "[a] person, company, or corporation subject to the supervision of the [PUC] or [DPS] ... who fails within a reasonable time to obey a final order or decree of the [PUC], or who violates a provision of ... [section] 248 ... shall be required to pay a civil penalty as provided in subsection (b) of this section after notice and opportunity for hearing."
¶ 40. Subsection (a)(2) provides that "[a] person who violates a provision of chapter 3 or 5 of this title, except for the provisions of section 231 or 248 of this title, shall be required to pay a civil penalty after notice and opportunity for hearing."
If the [PUC] determines that the violation substantially harmed or might have substantially harmed the public health, safety, or welfare, the interests of utility customers, the environment, the reliability of utility service, or the financial stability of the company, the [PUC] may impose a civil penalty as provided in subsection (b) of this section. If the [PUC] determines that the violation did not cause or was not likely to cause such harm, the [PUC] may impose a civil penalty of not more than $ 10,000.00.
¶ 41. Here, the PUC applied subsection (a)(1) to determine the penalty for Belisle's violation. However, subsection *1246(a)(1) applies to violations of § 248 and not to violations of § 246. As explained above, Belisle's establishment of a temporary meteorological tower without obtaining a CPG is a violation of § 246 ; therefore, subsection (a)(2), not (a)(1), provides the appropriate civil penalty. We reverse and remand the issue of calculating the penalty to the PUC to determine whether "the violation substantially harmed or might have substantially harmed the public health, safety, or welfare, the interests of the utility customers, the environment, the reliability of utility service, or the financial stability of the company."
We affirm in part, and we reverse and remand in part for the PUC to recalculate and assess a penalty consistent with this opinion.
The PUC was previously known as the Public Service Board. See 2017, No. 53, §§ 9-13.
During the second phase, Belisle continued to argue that he was not subject to PUC jurisdiction and was not required to obtain a CPG. The PUC revisited this issue during the penalty determination and considered evidence submitted at the penalty hearing-essentially ruling on the issue twice, albeit more robustly at the penalty phase. Here, we affirm the PUC's summary judgment determination based solely on the undisputed facts before the PUC at the time of its first summary judgment determination. We note that while nothing in the evidence presented at the penalty phase alters our conclusion, it is irrelevant to our analysis.
While not defined by statute, "site preparation" includes physical acts to prepare the site for development, such as grading or disturbing the ground, clearing the area, managing erosion, and excavating. See, e.g., Muzzy v. Curtis,
In setting the CPG requirements for temporary meteorological stations, § 246 gives the PUC the authority to carve out exceptions from the criteria for obtaining a CPG outlined in § 248. Section 246 provides: "[a] meteorological station shall be deemed to promote the public good of the State if it is in compliance with the criteria of [§ 246 ] and the Commission's rules or orders." 30 V.S.A. § 246(b). Section 246 further specifies that:
In developing rules or orders, the [PUC] ... [m]ay waive the requirements of section 248 of this title that are not applicable to meteorological stations, including criteria that are generally applicable to public service companies as defined in this title. The [PUC] shall not waive review regarding whether construction will have an undue adverse effect on aesthetics, historic sites, air and water purity, the natural environment, and the public health and safety.
The PUC issued the 2010 Order Establishing Standards and Procedures in response to comments and requests for clarification of § 246 regarding the conditional waiver of the § 248 criteria, among other issues. The 2010 Order explained that the conditional waiver of § 248 criteria is based on the limited potential for impact presented by the majority of temporary meteorological stations under those criteria. The waiver should be conditional, not unconditional, to allow for review of a particular project if it was found to raise issues with respect to conditionally waived criteria. 2010 Order at 2.
In In re SolarCity Corp.,
Sections 219a and 8010 (regarding grid-connected renewable-energy systems) and § 246 (regarding temporary meteorological stations) in nearly identical terms authorize the PUC to establish CPG requirements and waive certain criteria under § 248. But they also differ significantly. Sections 219a and 8010 apply to grid-connected renewable-energy systems, which always require a CPG under § 248, whereas § 246 applies to temporary meteorological stations, which are not grid-connected and may or may not require a CPG depending on their purpose.
By the plain language of § 248(a)(2), it is a violation to construct an electricity-producing facility that connects to the electric grid without first obtaining a CPG. The petitioner in SolarCity (SolarCity) failed to comply with §§ 219a and 8010 and the associated regulations prior to installing electricity-generating solar panels. By failing to comply, SolarCity failed to obtain the required CPGs prior to construction. Thus, according to the plain language of § 248, SolarCity violated § 248 by constructing grid-connected electricity-generating systems without CPGs. In contrast, Belisle's temporary meteorological station does not generate electricity, and it may or may not require a CPG depending on whether it aided Belisle in determining whether the site was suitable for a grid-connected project. See infra, ¶¶ 26-27. A meteorological tower requires a CPG under § 246 if it is "reasonably related" to determining the site's suitability for the construction or establishment of a grid-connected, wind generation facility.
As explained above, applying the penalty provisions under 30 V.S.A. § 30 further supports this framework. Establishing temporary meteorological towers will not have the same kind of impact as solar panels-even small ones-that are connected to the grid. Accordingly, § 30(a)(2), which provides for lesser maximum penalties, applies to Belisle's violation of § 246, while § 30(a)(1), which provides for higher maximum penalties, applies to SolarCity's violation of § 248.
Belisle argues that he is not subject to the PUC's supervision under 30 V.S.A. §§ 203 or 209 and therefore cannot be penalized for violating § 246. However, § 246 governs the CPG requirements for establishing a temporary meteorological station, and 30 V.S.A. § 30(a)(2) explains that "[a] person who violates a provision of chapter 3 or 5 of this title, ... shall be required to pay a civil penalty after notice and opportunity for hearing." By erecting a tower that required approval under § 246, a provision of chapter 5 of Title 30, Belisle subjected himself to PUC jurisdiction under these statutes. Belisle's argument that he was not aware of these requirements and therefore should not be liable is without merit. That ignorance of the law does not excuse an individual or company from compliance with its provisions is " 'of unquestioned application in Vermont both in civil and in criminal cases.' " Citibank (S.D.), N.A. v. Dep't of Taxes,
The definition of "temporary meteorological station" provided in the PUC's 2010 Order differs from the definition of "meteorological station" under § 246(a). The 2010 Order specifies that a meteorological tower must be "constructed or installed in order to determine the suitability of a site for the location of a grid-connected wind turbine"-language not included in the statutory definition. Compare 2010 Order at 6, with 30 V.S.A. § 246(a). However, § 246 specifically grants the PUC statutory authority to "establish by rule or order standards and procedures governing application for" a CPG for meteorological stations. 30 V.S.A. § 246(b). The PUC did so here by electing to clarify the term "temporary meteorological station," and we defer to the PUC's construction of this term. See In re Korrow Real Estate, LLC Act 250 Permit Amendment Application,
The PUC found, and the parties do not dispute, that Belisle's tower was temporary.
Belisle argues that, instead of applying the "reasonably related" test, the PUC "contends that its Section 248 jurisdiction extends to any activity that is a 'necessary precursor' to a future potential electric generation project" based on the PUC's reliance during the penalty phase on its holdings in UPC Wind Management, LLC, No. 6884, in 2004 and Vermont Electric Cooperative, Inc., No. 7201, in 2006. In UPC Wind Management, LLC, the PUC adopted the "reasonably related" test to determine jurisdiction over temporary towers pursuant to § 248 but explained that if a temporary tower is a "necessary precursor" to a wind facility, then that tower also satisfies the "reasonably related" and "directly related" standards. No. 6884. The "necessary precursor" analysis suggests that all temporary towers are within PUC jurisdiction because all temporary towers have the potential to provide data for a future wind project. The PUC has departed from this analysis, correctly, in § 246 proceedings and applies the narrower "reasonably related" test-only those temporary towers that are "reasonably related" to a future wind generation project fall within PUC jurisdiction. The PUC's jurisdictional analysis conducted during the penalty phase of the proceedings is not relevant to our review of the PUC's summary judgment determination; therefore, any error in its application of the reasonably related standard was harmless.
We note that while subsequent plans for or development of a wind generation project may be a factor in this analysis, that alone is insufficient to support a finding as to the purpose for the tower. See Meteorological Tower at 700 Kidder Hill Rd. in Irasburg, Vermont, No. 8585 (denying DPS's summary judgment motion because property owner's subsequent installation of two net-metered wind turbines, standing alone without project proponent's outward manifestations of intent, was insufficient to directly demonstrate owner installed tower to assess viability of grid-connected turbines).
Belisle also argues that there is no evidence the Swanton Wind project, in which he was an investor and developer, was contemplated in 2012 and it was clear error for the PUC to use Belisle's subsequent actions as evidence of his intent. The PUC's consideration of the Swanton Wind project occurred in its "second pass" at this issue during the penalty phase; therefore, we do not consider it in our review of whether a violation of § 246 occurred. We are limited to the undisputed facts present before the PUC during its initial summary judgment determination.
The PUC determined that elements of Belisle's proposed undisputed facts eleven, thirteen, and fourteen regarding his ability to complete § 3.1(b) of the § 246 application were "immaterial because, even if true, they are not relevant to the legal question of whether [Belisle] was required to obtain a CPG prior to erecting the tower." Belisle argues that this conclusion was in error. However, any error in the PUC's findings of undisputed facts is harmless because, even considering Belisle's alleged facts, based on the circumstances and resolving all inferences and doubts in favor of Belisle, the temporary tower at issue was reasonably related to a grid-connected project.
Belisle's arguments that there is no evidence that his temporary tower caused substantial harm to any of the factors listed under § 30(a)(2) must be addressed on remand. Therefore, we do not address it here. Similarly, we decline to address Belisle's argument that the PUC's penalty was arbitrary and capricious.
Reference
- Full Case Name
- IN RE CONSTRUCTION & OPERATION OF A METEOROLOGICAL TOWER (Travis Belisle, Appellant)
- Cited By
- 3 cases
- Status
- Published