De Mattos v. Jordan
De Mattos v. Jordan
Opinion of the Court
The opinion of the court was delivered by
For a former opinion in this cause, see 15 Wash. 378 (48 Pac. 402), where it was reversed and remanded for a new trial. In so doing, the court said :
“ In view of the fact that a new trial must be awarded, we deem it proper to observe that appellant can, under the terms of the contract, only recover such of the expenses incurred by him for furnishing materials or finishing the work as shall have been audited and certified by the architect. Ho estimates of the architect were required after the contractor abandoned his contract, but it was explicitly agreed that the expenses incurred by the owner for materials and labor should be audited and certified by the architect and that his certificate should be conclusive upon the parties. The purpose of this provision was to protect the sureties against excessive and unjust charges for work and material, and it was agreed that the certificate of the architect should he conclusive as to the amount of expenses incurred by the owner. It is evident that in no event can appellant recover more than the amount of damage he has sustained by reason of the default of the contractor.”
It is next contended by the respondent that the certificates could be furnished at any time; and several years after the completion of the work, and after the action was commenced, a written certificate was obtained, but this came too late, for it was necessary to obtain it in the first instance, under the contract, as a basis for the claim against the sureties.
It is also contended by the respondent that the sureties are estopped from alleging a non-compliance by the plaintiff with the contract in this particular, because they had previously denied any liability on the bond; but we fail to see how this matter should estop them from resist
Reversed and remanded, with instructions to dismiss.
Andees, Gordon and Dunbar, JJ., concur.
Reference
- Full Case Name
- James P. De Mattos v. R. C. Jordan
- Cited By
- 7 cases
- Status
- Published
- Syllabus
- BUILDING CONTRACT-CERTIFICATE OF ARCHITECT-LIABILITY OF SURETIES ON BOND—ESTOPPEL. Under a clause in a building contract, providing that the expenses incurred by the owner for furnishing materials and finishing the work abandoned by the contractor should be audited and certified by the architect, the sureties on the building bond cannot be rendered liable for sucb expenditures unless the architect’s certificate is made in writing. Where such certificate is obtained several years after the completion of the work, and subsequent to the commencement of an action against the sureties, it comes too late, as it should have been obtained in the first place, as a basis for the claim against the sureties. The fact that sureties on a building contractor’s bond had denied liability upon the bond would not estop them from alleging the owner’s failure to furnish the architect’s certificate of expenditures, where the building had been completed by the owner after abandonment by the contractor.