Anderson v. McDonald
Anderson v. McDonald
Opinion of the Court
The opinion of the court was delivered by
— The respondent, for himself and as the assignee of five other persons, brought this action against appellant to recover for amounts alleged to be due from appellant to respondent and his assignors on account of certain work done by them upon the construction of that portion of the line of the Seattle and Montana railroad commonly known as the “Chuckanut Out-Off.” The complaint alleges that appellant, as a contractor, had undertaken to perform certain constructive work along the line of said road, which included the approach and tunnel hereinafter mentioned; that respondent and his assignors entered into a verbal contract with appellant, whereby they undertook, at agreed prices, to excavate and construct an approach from a given point to a certain proposed tunnel as located by said railroad company, and also to bore, excavate, and construct as much of said tunnel as lies between said approach and the center of the tunnel; that they entered upon said work, and diligently prosecuted the same until on or about the 3d day of October, 1901, during which time they hired other men to assist in the work, for whose labor appellant paid upon the verbal request of respondent; that about said last-named day, the said railroad company, through its engineer in charge, changed the line of said road so that another and different approach to said tunnel was established, and which in large part required the abandonment of the approach as originally located; that on or about said day respondent and his assignors received knowledge of said change, and also that the relocation required the approach to be made much longer, deeper, and wider than that which they had under
It is assigned that the court erred in refusing to grant a nonsuit. It is contended by appellant that his first contract was made with a partnership of twelve persons, and that the evidence of respondent did not establish the abrogation of that contract by the consent of all the members of said copartnership. There was evidence introduced by
“When the appellant failed to pay cash when due, according to the terms of the contract, the respondents were at liberty either to stop all work under the contract and sue for the recovery of the resulting damages, or to proceed with the work to completion, notwithstanding the breach.”
A further breach was also sufficiently shown, as against a motion for nonsuit, by testimony that appellant refused to permit the work to proceed under the new contract after it had been begun. We think no error was committed in denying the motion for nonsuit.
It is assigned that the court erred in instructing the jury that, if they found that the respondent and his associates commenced to labor under the alleged new contract, and that appellant afterwards refused to permit them to proceed further, they should then find against appellant for the amount unpaid for work done under both contracts at the rate per day agreed upon in the new one. It is urged that this instruction was erroneous, for the reason that there was no evidence showing that appellant ever refused to permit the parties to proceed. We find testimony in the record to the effect that appellant told the parties that he had taken charge of the work himself; that he would
Error is assigned upon an instruction which was to the effect that much evidence had been admitted concerning the old contract, and that the purpose thereof was to enable the jury to better understand the entire relations of the parties and the condition of their minds at the time the old contract is said to have been abrogated and the new one made. The objection to this instruction is urged upon the ground that it is a comment upon the evidence, and that it excluded from the consideration of the jury the affirmative defense wherein appellant claims that respondent and his assignors are indebted to him. We think the instruction is not susceptible to the criticism that it is a comment upon the facts, especially in view of other instructions in which the court told the jury that any reference made to the facts was not intended as an intimation of any opinion of the court as to the facts in the case, and that they were the sole judges thereof. Furthermore, we do not understand appellant to seriously contend that he has a right to recover over in this action under his said affirmative defense, hut rather that it was interposed simply as a defense. In any event, the court submitted all the testimony thereunder to the jury, in order that they might consider it for the purpose of determining if a new contract was made. The jury, by its verdict, having found from all of the evidence that such new contract was made, no right of recovery over could rest in appellant. Such right would he inconsistent
It is urged that error was committed in denying the motion for new trial. The verdict was for just half the amount demanded in the complaint. Appellant contends that, if respondent is entitled to recover at all, he is entitled to recover the full amount, and that the jury must have reached its verdict hy some compromise agreement, or by resorting to chance of somle kind. One of the issues in the case was, however, the amount of time actually spent by respondent and his associates upon the work. Appellant testified that a portion of the men were often intoxicated, and incapacitated for doing the work. Under that testimony we shall not undertake to say that the jury were not justified in reducing the time and in returning the verdict which they did. The jury heard the conflicting evidence, and passed upon it. Such being their province, we shall not, for mere conflict of evidence, disturb the verdict. Herrman v. Great Northern Ry. Co., 27 Wash. 472 (68 Pac. 82, 57 L. R. A. 390); Johnston v. McCart, 24 Wash. 19 (63 Pac. 1121); Swadling v. Barneson, 21 Wash. 699 (59 Pac. 506). The record shows evidence upon which to found the verdict. The trial court heard the witnesses testify, and was better qualified than is this court to judge of the weight that might properly be accorded by the jury to the testimony of the several witnesses. We shall therefore not disturb the ruling upon the motion for a new trial.
The judgment is affirmed.
Pullerton, O. J., and Mount, Dunbar and Anders, J.T., concur.
Reference
- Full Case Name
- Ed. Anderson v. A. V. McDonald
- Cited By
- 1 case
- Status
- Published
- Syllabus
- CONTRACTS — BREACH — NONSUIT. In an action to recover for a breach of contract, a motion for nonsuit was properly denied, where it appeared that defendant had contracted with twelve laborers, as a partnership, for their services in excavating and tunneling along a railway line, that, upon a change in the route, six of the men quit work and refused to return, but that the others continued work under a new agreement whereby they were to receive a- stated amount of cash for work done under the partnership contract and were to be paid days’ wages for their future labor, and that defendant had committed a breach of such contract by refusing to make the cash payments, or to permit them to go on with the work after they had entered upon it under the new contract. SAME. Where a contract contemplates the making of cash payments for labor performted, the refusal to make such payments constitutes a breach, for which suit may be maintained. SAME. Where defendant, after entering into a contract for the services of plaintiff’s assignors, and upon the performance of which they had entered, told them that he had taken charge of the work himself, that there was nothing more for them to do, and that he would not pay them another cent, his conduct amounted to a refusal to permit them to proceed, and constituted such a breach as to warrant a recovery for the amount unpaid for services rendered. INSTRUCTIONS-HARMLESS ERROR-COMMENT ON FACTS. Error of the court, if any, in referring to the facts in a case in charging a jury was cured by further instructions in which the jury were told that any reference made to the facts was not intended as an intimation of any opinion of the court, and that they were the sole judges of the facts in the case. SAME. An objection that an instruction excludes from the consideration of the jury one of the defenses of defendant, constitutes harmless error, where all the evidence introduced was submitted to the jury and their verdict was equivalent to an affirmative finding adversely to defendant’s contention. NEW TRIAL-IMPROPER VERDICT. The fact that the jury gave a verdict for just one-half of the am'ount claimed in an action for work under a contract providing a stipulated rate of wages is not ground for new trial, where one of the issues in the case was the amount of time actually spent by plaintiff and his assignors upon the work, defendant claiming that a portion of the men were often intoxicated and thus incapacitated for doing their work.