Childs Lumber & Manufacturing Co. v. Page
Childs Lumber & Manufacturing Co. v. Page
Opinion of the Court
The opinion of the court was delivered by
This is a second appeal of this cause. The opinion on the former appeal will be found in 28 Wash. 128 (68 Pac. 373), where will be found, also, a full statement of the pleadings in the cause, and the facts giving rise to the controversy between the parties. After the cause had been remanded on the former appeal, the plaintiff (appellant here) amended its reply, in which it substantially admitted the allegation in the defendant’s answer to the effect that it had failed to deliver the materials agreed to be furnished at the time named in the contract, and that the defendant A. J. Page had determined the amount of the loss and damage sustained by the defendants thereby in the sum of $515, and had served written notice thereof on the plaintiff, but sought to avoid the effect of the admission by pleading certain matters in defense thereof, which may be epitomized as follows: (1) That whatever delay occurred was caused by the defendants; .(2) that the delay was not caused by any fault of the plaintiff; (3) that time of performance had been extended by the mutual agreement of the parties, though not for the entire time of the delay; (4) that prior to the institution of this action the plaintiff had brought an
The appellant insists that one clause alone of the contract entered into between the parties, viz., article 8 (28 Wash. 132, 68 Pae. 373), is applicable to the matter now in dispute between them, and that this clause authorizes the owner to fix the amount of the damage caused by delays only, which alone it is required by the contract to arbitrate; and that it is open to it to litigate in the courts the question of its liability for such damage, and hence it has the right to litigate in the courts the several matters set out in its reply as a defense to the claim. Heading article 8 of the contract by itself, some support, doubtless, can be found for this contention; but it is a familiar principle-that a contract must be read as a whole, and its meaning gathered from the whole instrument, and not from any particular part thereof. So reading this contract, there is little doubt as to its meaning. However awkward or cumbersome its language may be, it is clear that it was in
Other questions suggested by tbe appellant are concluded by what we have said above, and, as we find no error in tbe record, tbe judgment will stand affirmed.
Mount, Hadley, Anders and Dunbar, JD, concur.
Reference
- Full Case Name
- Childs Lumber and Manufacturing Company v. Flora R. Page
- Cited By
- 1 case
- Status
- Published
- Syllabus
- CONTRACTS-CONSTRUCTION-ARBITRATION. A single clause of a building contract giving the owner the right to fix the amount of the damages owing to delay, and, upon dissent by the contractor, requiring arbitration, must be construed in connection with the other clauses, and does not limit the arbitration to that point, where it is apparent that all matters in dispute are to be arbitrated. SAME-PLEADINGS-ADMISSIONS IN REPLY. Where the contract permits the owner to fix the damages for delay and requires arbitration if the contractor dissents, and the reply admits that the damages were fixed, the plaintiff cannot avoid the effect of such admission by showing that the delay was not its fault, that the time had been extended, or that the claim was in bad faith, where those defenses had not been submitted to arbitration or any attempt made to arbitrate; and judgment is properly given on the pleadings for the amount claimed, less the damages fixed.