Paul Hopkins & Son v. Seattle Scandinavian Fish Co.
Paul Hopkins & Son v. Seattle Scandinavian Fish Co.
Opinion of the Court
The opinion of the court was delivered by
On March 2, 1901, the respondents, doing business at Ballard, Washington, as the Ballard Boiler Works, entered into a contract in writing with the representative of the appellant by the terms of which they undertook to build for the appellant a marine boiler of the Clyde type, according to specifications set forth in the contract, for the sum of $900, to be paid in installments of $300 each; the first when the contract should be signed, the second when the boiler should be half completed, and the last on the completion and inspection of the boiler. It was specified that the boiler should be built of marine steel, properly tested and inspected, sufficient to stand the working pressure allowed by law on half-inch steel, and “to be completed within six (6) weeks after the arrival of the iron in Seattle.” The respondents finally completed the boiler about the middle of September, 1901, and were paid the first and second installments of the purchase price. The last installment was not paid, and the appellant filed a lien on the boiler and the boat into which it was placed to secure the balance of the contract price, together with a claim of $101.60 for work and material not included in the contract. This action was brought to foreclose the lien. The complaint was in the usual form. The appellant answered, putting in issue certain allegations of the complaint, and setting up by way of counterclaim a claim for damages in the sum of
The principal contention was over the question whether or not the boiler had been completed within the time limited by the contract. This time, it will be observed, was not definitely fixed. By the terms of the contract the respondents were to furnish the necessary material to complete the boiler, and were to complete it “within six (6) weeks after the arrival of the iron in Seattle.” The appellant construes this to mean that the respondents were obligated to use reasonable diligence in procuring the material necessary to complete the boiler, and are responsible to it for any damages it has suffered because of a delay in its completion, caused by their failure to use such diligence; and argues that it appears from their own testimony that by the exercise of only common diligence the materials could have been procured, and the boiler completed, long before it was turned over to it. The testimony on this point is to the effect that immediately upon the execution of the contract the respondents placed an order with a San Francisco house for the steel necessary for the construction of the boiler, and received within a reasonable time — on March 24, 1901 — the greater part required; all, in fact, except that necessary to be used in the construction of the flues. These were required by the contract to be constructed out of half-inch steel. Steel of the kind required of this thickness seems not to have been
This conclusion renders it unnecessary to discuss other questions suggested in the briefs. The judgment is affirmed.
Hadley, Anders, Mount and Dunbar, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.