Dickerman v. Reeder
Dickerman v. Reeder
Opinion of the Court
Plaintiff brought this action to foreclose a mechanics’ lien, for the amount due him as contractor for the construction of a building at Ralston, in Adams county. The
The plaintiff first argues that the court erred in overruling the demurrers to the affirmative defenses which set up •counterclaims. The answer of the defendants, after admitting the contract alleged in the complaint and making certain general denials, alleged as an affirmative defense by way of counterclaim, as follows:
“That in the contract entered into between plaintiff and defendants it was agreed that he would complete the building and deliver the same to the defendants on or before December 1, 1908, and in. case of failure to deliver the said building "the said plaintiff agreed to pay stipulated damages in the sum of $5 per day, and on the 15th day of April, 1909, the date of bringing this action the said building had not been finished or delivered as per the contract, and by reason thereof the plaintiff is indebted to these defendants in the sum of $600.”
It is next argued that the court erred in receiving in evidence a copy of the plans and specifications. There is no merit in this contention, for the copy offered in evidence was identified as the specifications referred to in the contract. None were attached to the contract set up in the complaint,, although the plans and specifications were made a part thereof by express reference thereto, and it is not claimed that the copy offered was not correct. The evidence is sufficient to show that the copy offered is one of the originals.
It is next argued that the court erred in deducting $550' as stipulated damages, for delay in completing the building after the period provided for in the contract, being-one hundred and ten days at $5 per day. Such, contracts have frequently been enforced by this court. See, Jenkins v. American Surety Co., 45 Wash. 573, 88 Pac. 1112, and cases there cited. There is, therefore, no merit in the plaintiff’s appeal.
On the appeal of the defendants, it is argued that the-court erred in receiving in evidence the final certificate of the-architect, to the effect that the final payment was due. It appears that a bill for extras, amounting to $521.15, had been-, presented by the contractor to the architect' for approval.. The architect approved certain items amounting to $326.45, and rejected the other items for extras. The architect also-made deductions for imperfect work and work not done according to the contract, in the sum of $183, which amount was also deducted from the claim allowed for extras, thus.
The contract provides, at article 3, that, in case the owner and contractor fail to agree as to the amount to be paid or allowed for alterations, the determination of the amount shall be referred to arbitration. If it is conceded that the architect had no authority under the contract to fix the amount for extras, and the amount for defective work, and work not done,
The appeal of the defendants is therefore sustained, and the cause remanded with direction to the lower court to decree a foreclosure of the lien in favor of the plaintiff for $59.60, with costs and attorney’s fees as stated in the decree. The defendants will recover their costs on this appeal.
Rudkin, C. J., Dunbar, Crow, and Parker, JJ., concur
Reference
- Full Case Name
- H. R. Dickerman, and v. W. C. Reeder, and Crab Creek Lumber Company, Intervener
- Cited By
- 4 cases
- Status
- Published
- Syllabus
- Mechanics’ Liens — Foreclosure—Answer—Building Contracts Stipulated Damages. An answer in an action to foreclose a mechanics’ lien, setting up the affirmative defense of stipulated damages for delay under “the contract” to complete “the building,” is not demurrable for failure to set out the contract and more specifically describe the building, where the substance of the contract was stated. Appeal — Review—Pleading—Harmless Error. It is not reversible error to overrule a demurrer to an indefinite. or uncertain pleading. Evidence — Contracts—Specifications Referred to — Admissibility. In an action upon a building contract which expressly-made the plans and specifications a part thereof, although not attached, a copy identified as one of the original plans and specifications is properly admitted in evidence. Damages — Stipulated Damages — Delay. A contract for stipulated damages of five dollars per day for delay in the completion of a building is enforcible. Contracts — Building Contracts — Architect’s Certificate — Issuance — Waiver of Objections. In an action on a building contract, an architect’s final certificate of the completion of the building is properly admitted in evidence against the contractor, where, after cutting down the contractor’s bill for extras, the certificate was issued showing the completion of the building and the amount due, and was delivered by the architect to a third person to be delivered to the contractor when he should accept the allowance for extras, and thereafter the contractor did not seek arbitration as required by the contract in case of any dispute as to the amount allowed for alterations, since he thereby waived any objection to the allowance for extras and accepted the same. Same — Conclusiveness — Architect’s Certificate — Waiver. Where it is not claimed that an architect acted arbitrarily or fraudulently, it is error to allow in full a contractor’s claim for extras, where the final certificate of the architect, made a prerequisite to an action on the building contract, cut down the amount claimed by the contractor, and the contractor waived objection to the allowance by failing to seek arbitration as required by the contract in ease of any dispute.