Archer v. Franklin County School District No. 1
Archer v. Franklin County School District No. 1
Opinion of the Court
This action was brought by the plaintiff to recover an alleged balance on a contract for the construction of a school building for the defendant.
The plaintiff sued for the sum of $8,209.70. This sum was made up of three items: First, $3,500 for tearing down and rebuilding a brick wall; second, $4,333.90, the alleged balance due upon the contract; and third, $375.80 for extras. The defense was based upon the alleged grounds that the contract had not been completed in accordance with the terms thereof; that the plaintiff was entitled to no extras; that there was an offset of damages caused by defective work; and for delay in the construction of the building.
The First National Bank of Pasco was permitted to intervene in the case. This intervener alleged an assignment of $2,000 due to the plaintiff from the defendant, which assignment was accepted by the defendant. Upon the trial of the case, the court disallowed the claim of $3,500 for tearing down and replacing the brick wall; found that the plaintiff was entitled to extras amounting to $304.95; and that the defendant should recover damages by reason of the delay of the plaintiff in completing the building, in the sum of $336.
The plaintiff has appealed from that part of the judgment refusing to allow him $3,500 for tearing down the wall. The defendant has appealed from that part of the judgment finding that the building was completed in accordance with the contract, and that the plaintiff was entitled to recover for extras, and the refusal of the court to allow $25 per day for the time intervening between the time the contract was to be completed and when it was actually completed.
The intervener has appeared in this court and moved to dismiss the appeal upon a number of grounds. It is sufficient to say that the appeals of the plaintiff and the defendant do not affect the judgment of the intervener. It was conceded in the trial of the case that the intervener was entitled to a lien for $2,000 upon the judgment of the plaintiff, and no appeal was taken from that part of the judgment, and whatever judgment might be rendered here would not affect that judgment. The intervener, therefore, has no interest in the appeal. The motion is denied.
The contract between the plaintiff-and the defendant provided that the plaintiff should furnish all the materials and construct the building in accordance with the terms of the contract. The contract also provided that the brick which were to be placed in the walls of the building should be thoroughly wet before being laid in the walls. When the brickwork was started, the architect was upon the ground and called attention to the fact that the brick were not being wet. He was not upon the work again until some thirty days later. Part of the wall was constructed without wetting the brick. He thereupon ordered this wall torn down and replaced according to the contract. This was done, and the plaintiff now claims an extra amounting to $3,500 for this work. It is apparent that this is not an extra.’ If the work
The trial court allowed several items, amounting to $304.95 as extras. The contract provided:
“No alterations shall be made in the work shown or described by the drawings and specifications, except upon a written order of the architect, and when so made, the value of the work added or omitted shall be computed by the architect, and the amount so ascertained shall be added to or deducted from the contract price.”
It is not claimed by the plaintiff that any of these items, except one which amounted to $84, was made upon any order of the architect, or that they were agreed to as extras. The contract is specific as to the manner in which extras were to be furnished and if the items claimed by the plaintiff were extras, it was his duty under the contract to obtain a written order of the architect for the doing of these things as extra work. Not having done so, he cannot recover for any of the items, except the one ordered by the architect, amounting to $84. This is plainly provided for in the contract, and the contract of course must control. We think the court was in error when it allowed $304 for extras.
The defendant attempted to show that the building had not been completed at the time the action was brought by reason of the fact that an ornament, called a “cartouche,” which was provided for in the contract and which was to be placed on the top of the building in front containing the name of the building and a scroll or shield, was not constructed in ac
The judgment of the trial court is modified to the extent of deducting the difference between $304.95 and $84, which is $220.95, from the amount found due the plaintiff. Otherwise the judgment is affirmed. Neither party will recover costs on this appeal.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.