Nevins v. Scace
Nevins v. Scace
Opinion of the Court
The plaintiff sought to recover of defendants $1,739.86, less certain payments, for drawing plans and specifications for a hospital which defendants contemplated building on Seminary Hill, in Centraba, Washington, and also, $1,260 for like services for a hospital to be constructed in the down-town district of the same city. He claims to have performed these services at the request of the defendants, for which he was to be paid for each set of plans an amount equal to 3% of the cost of construction of the building, and that the cost of constructing under the first plans would have been $57,900, and under the second plans, $42,000. He admits the payment by defendants to him of $950, which he applied on account of the first plans, thus leaving due him $789.86 for them, and $1,260 for the second plans.
Defendants admitted that both sets of plans had been drawn by the plaintiff for them, and that they had agreed to pay him for his services an amount equal to 3% of the construction cost, but they claim that the plaintiff guaranteed that the hospital to be erected under the first plans would not cost in excess of $40,000, and that the lowest bid for constructing under them was an amount in excess of $57,000, and that because of such excessive cost they were unable to, and did not use the first plans, and ought not to be required to pay for them. They admit, however, that they con
It is first contended that the court erred in taking from the jury the consideration of the item of $1,000 damages on account of the excavation made under the first, or Seminary Hill, plans. The testimony showed that these plans provided for an excavation under the kitchen and part of the dining room of the hospital. The appellants not only made this excavation but also excavated for a large cesspool, and a long drain leading thereto, "which latter were not covered by the plans. The testimony showed that the appellants had paid $1,300 for all of this excavation, but no evidence was introduced showing the cost of the excavation provided for by the plans and specifications. The appellants introduced but one witness on this feature of the case, and he was wholly unable to segregate the cost of the
It is next claimed that the appellant was entitled to a new trial because the verdict was inconsistent with any theory of the case as presented to the jury, either by the testimony or the instructions of the court. Their argument is that if the jury found for the respondent only on account of the second plans, liability for which was admitted, then the verdict could only have been for $210; but if the jury found for respondent on account of both the first and second plans, then the verdict must have been for an amount twice as large as that returned by the jury. While it is difficult for us to tell how the jury arrived at the amount of its verdict, it is perfectly plain that they allowed recovery, at least in part, on both sets of plans. But courts cannot grant new trials simply because they are unable to follow the minds of the jury in arriving at its verdict. In the case of Haefele v. Brackett, 95 Wash. 625, 164 Pac. 244, we said:
*219 “But we do not understand that a verdict will be set aside as within the rule of mistake or compromise or that it is impossible under the theory of either party, unless it shows upon its face that the jury has given way to passion or prejudice or has acted in willful disregard of its duty to consider the testimony, and a true verdict rendered.”
There is nothing on the face of this verdict which shows that the jury refused to follow the evidence. The most that can be said is that if the jury meant to find for the respondent for both plans drawn by him, then their verdict could have been for a larger sum. But, in this respect only, the respondent could complain. Appellants will not be heard to complain because the verdict against them was not large enough. A careful reading of the record convinces us that the judgment should be affirmed.
Parker, C. J., Mackintosh, Fullerton, and Holcomb, JJ., concur.
Reference
- Full Case Name
- John R. Nevins v. Lee A. Scace
- Status
- Published
- Syllabus
- Damages (3, 106)—Certainty as to Amount—Evidence—Admissibility. Upon an issue as to damages through an architect’s breach of contract in the preparation of plans and specifications for a hospital building, which could not be constructed within the estimate, an item of damages in the sum of $1,000 for costs of excavating the basement for the building, prior to discovery of inability to bring the expense of construction within the estimate, was properly withdrawn from the jury, where the excavation also included a cesspool and a long drain leading thereto, which were not included in the plans, and the defendants were unable to segregate the cost of the cesspool and drain items from the excavation. New Trial (19)—Verdict Contrary to Evidence—Power of Court. The inability of the court to follow the minds of the jury in arriving at a verdict upon conflicting claims of the parties is not a ground for the granting of a new trial.