Forristal v. City of Milwaukee
Forristal v. City of Milwaukee
Opinion of the Court
The charter of the defendant contains this provision: The board of public works “ shall reserve in every
The learned counsel for the plaintiff did-not insist that the provision which made the board arbiters to determine the
But the plaintiff’s counsel says it did not appear from the evidence offered on the trial that the board ever determined, in a proper way, the amount which the plaintiff had earned on his contract. This position is not sustained by the record. Exhibit C, offered . in evidence, showed that the board had made an equitable adjustment of the amount due the plaintiff on his contract. It is true, this exhibit is not very formal, and does not set forth all matters which Blodgett and Cas-grain say the board considered in making its award or decision. But it clearly shows that the board made an equitable adjustment of what was due the plaintiff on his contract, in view; of the fact that he failed to perform in every particular. The above witnesses, who were members of the board in 1881, clearly explain just how that body reached the conclusion it did in making its final estimate or allowance. The record itself which was made does not show all these matters, but it is sufficiently full to answer the requirements of the law. It was suggested on the argument, by plaintiff’s counsel, that the board only had the power to adjust and determine all questions as to the amount earned under a contract where the contract was terminated and the work was relet to other contractors. But this construction of the provision is clearly wrong. The language used gives the board power to adjust, etc., all questions under any contract with the city. The words used are comprehensive, and vest the power in the board to adjust in case of all contracts. It was further said that the trial court erred in allowing, against objection, oral testimony of the proceedings of the board. But, as we understand the bill of exceptions, the records of
The contract stated that the work was to be done according to the rules and specifications of the board on file in the office of said board. These specifications provided that no allowance would be made for. sprinkling street cross-walks. The intersections of the roadway were to be paid for at the regular contract price per lineal foot. In estimating the lineal feet sprinkled, the board omitted fifteen feet for every sidewalk crossing, allowing nothing for street cross-walks, but only for roadway intersections. This was because the sidewalks on each side of the street are fifteen feet wide. Mr. Blodgett explained to bidders that the object of this rule of measurement was to have the sidewalk spaces between the curb line and the lot line free from water; therefore only the intersections of the streets proper between the curbs would be estimated. The county court charged that this method adopted by the board of - estimating what was included in the street crossings, with regard to lineal feet which the plaintiff was required to sprinkle, was correct. This charge was excepted to by plaintiff’s counsel, but we think it was in accordance with the terms of the contract.
The contract required the sprinkling to be done from the 21th day of May, 1881, to the 15th day of November following, unless the contract should be “sooner termvnated by ■order of the board.” The board did in fact terminate the contract on and from the 31st of October, and gave the plaintiff due notice thereof. The county court ‘held in respect to this that the board had the right to terminate the contract for good and sufficient reasons. This charge is objected to; but it seems to us plain that the court was correct in holding that the board had the right to terminate the contract for cause under the reserved clause. Whether the board could do so arbitrarily without cause is a question which
Nor did the court err in ruling-that if the board determined the amount which the plaintiff had earned on his nontract, and this amount was allowed him, and ready to be paid- in city orders previous to the commencement of the suit, the plaintiff was not entitled to recover. The contract was payable in city orders, and orders for the proper amount, it appeared, had been issued and were ready for delivery.
Other exceptions were taken on the trial, and are relied on. here for a reversal of the judgment. "We do not deem it necessary to notice them seriatim. The view which we have taken of the power of the board, under the charter, to decide .all questions as to the proper performance and to determine the amount earned by the plaintiff on his contract, renders many of these questions quite immaterial. The court undoubtedly erred in submitting several questions to the jury after it appeared that the board had made its determination of the amount justly earned by the plaintiff, which, both by the charter and the contract, was to be final as between the parties. Rut this was not an error of which the plaintiff can ■complain.
By the Court.— The judgment of the county court is affirmed.
Reference
- Full Case Name
- Forristal v. The City of Milwaukee
- Status
- Published