Prautsch v. Rasmussen
Cases that cite this one
4 later published cases cite this decision.
- Purington Paving Brick Co. v. Metropolitan Paving Co. (8th Cir. 1925)
- Schultz v. Andrus (Wis. 1922)
- National Knitting Co. v. Bouton & Germain Co. (Wis. 1909)
- Seibert v. . Dunn (N.Y. 1915)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
In a number of cases in this court contracts which in all essential features were like the contract in question have been held to be entire contracts, requiring full performance before payment of the consideration is due, notwithstanding the fact that the contracts did not provide for payment in a lump sum, but for measurement of the consideration by quantities or units. McDonald v. Bryant, 73 Wis. 20, 40 N. W. 665; Boutin v. Lindsley, 84 Wis. 644, 54 N. W. 1017; Warehouse & B. S. Co. v. Galvin, 96 Wis. 523, 71 N. W. 804; Widman v. Gay, 104 Wis. 277, 80 N. W. 450. See, also, Baker v. Higgins, 21 N. Y. 397; Mount v. Lyon, 49 N. Y. 552; Shinn v. Bodine, 60 Pa. St. 182;
This consideration renders it certain that there is no error in the judgment of which the plaintiff can complain.
By the Court. — Judgment affirmed.