Van Valkenbuegh v. City of Milwaukee
Van Valkenbuegh v. City of Milwaukee
070rehearing
A motion for a rehearing in this action was granted February 3, 1914, and in deciding the case as resubmitted the following as the action of the court, was filed May 1, 1914:
When this cause was first disposed of there was no forgetfulness of decisions or óf principles as regards sidewalks being required and construction thereof and payment therefor enforced under the police' power. Counsel for the city are not at fault in any respect because of not having done their full work when the case was presented before. The facts were well understood; but the court was of the opinion that the sole authority of the contractor was the order of the board of public works to construct a sidewalk containing about 480 feet; that any construction beyond that was in excess of authority, and, therefore, the levying of a tax to pay therefor was in the nature of making a gift to the contractor which would not be legitimate. However, on reconsideration of the case, the court is constrained to hold that the order, substantially for a six-foot instead of a fifteen-foot walk, was a mere irregularity which it was competent for the board of public works to correct by providing for an assessment to cover the cost of the walk actually constructed and which the order to the contractor, but for inadvertence, would have-called for. It seems that the ordinance under which the walk was relaid called for a fifteen-foot walk in case of a reconstruction. The contract for the construction contemplated the building of a walk in conformity to the ordinance in re
The judgment appealed from is, therefore, reversed, and the cause remanded with directions to dismiss the same with ■costs.
Opinion of the Court
The following opinion was filed November 18, 1913:
Plaintiff challenges the finding of fact in. defendant’s favor as to the latter having appropriated the former’s lumber which came from the old walk. If the court erred in. respect to that, plaintiff should have had judgment for such lumber. He also complains of the finding to the effect that the old sidewalk was replaced by the new one because of the former being defective, — the theory being that,, if the old sidewalk was in such good condition that there was no reason for replacing it other than because the board of public works favored cement walks, the displacement was-illegal. Those matters are ruled in defendant’s favor because the record does not satisfy us of the findings being against the clear preponderance of the evidence.
Assuming for the case that counsel is right as to the limit of authority to replace the old with new sidewalks, the record does not convince us, clearly, that the board of public works failed to observe such limitation. Whatever conditions precedent to the right of the board to act existed, in the absence of pretty clear evidence to the contrary, we must assume that it kept within the scope of its authority. So far as it was required to pass upon matters of fact, as for example whether the old sidewalk was out of condition, or its being out of condition was so liable to occur that its replacement by a new walk was reasonably necessary, its judgment is conclusive if it rests on any reasonable basis. To overturn such judgment would require a case showing a clear abuse of authority. However, here, as indicated, there is a finding that the old sidewall?:, on the day when it was taken up, was defective and we do not see our way clear to overrule that decision.
The defendant’s appeal challenges the recovery by plaint
Counsel denominates the call in the order made by the board of public works for a six instead of a fifteen-foot walk as a mere clerical mistake; and insists that it was in no .sense jurisdictional. It may be that a six-foot walk was ordered when a fifteen-foot should have been, but the difficulty can hardly be called a clerical mistake. The order was a final •discretionary act of the board of public works. It' doubtless specified just what it intended to at the time. The contractor had no authority to proceed other than upon the order and was limited thereby. It is not perceived why he was not a mere voluntary actor as to whatever he did beyond the scope of such order.
By the Court. — The judgment is affirmed.
Dissenting Opinion
(dissenting). By a city ordinance, which, when reasonable and within the legislative jurisdiction of the common council, has the same force as a statute, this sidewalk was required to be fifteen feet wide like other sidewalks in that part of the city. The board of public works ordered a sidewalk built without specifying the width, but in describing its area evidently computed this upon a width of six feet. The contractor built a fifteen-foot sidewalk as the ordinance required and the lotowner paid for the same and now sues to
Reference
- Full Case Name
- Van Valkenbuegh v. City of Milwaukee, Respondent Same v. Same
- Status
- Published