Voight v. Nanz
Opinion of the Court
The sole issue on this appeal is whether the trial court erred in denying the defendant’s motion for directed verdict.
The verdict was submitted to the jury in the form of a single question as to how much money was owed to the plaintiff by the defendant. Neither party objected to the form of the verdict. Nor were any objections made on the record to any of the instructions given to the jury. The defendant on appeal claims that on the evidence adduced at the trial he was entitled to a directed verdict that he owed the plaintiff $2,277.16.
The undisputed testimony shows that the plaintiff discontinued work on the defendant’s apartment building before all the work called for under the written contract was completed and at a time when certain billings which had been rendered by the plaintiff to the defendant had not been paid by the defendant. The trial court was correct in concluding that it was an issue for the jury to decide on the evidence presented which of the parties breached the contract.
In American Jurisprudence it is stated that:
“Whether the wrongful withholding by the owner of amounts due under the terms of a building or construction contract is an excuse for nonperformance on the part of the contractor depends upon whether the contract so provides or whether, in the absence of such a provision, such conduct prevents performance.”2
And in Gorbin on Contracts it is said:
“Although a builder may be privileged to suspend work, or even to renounce the contract, by reason of the nonpayment of an instalment, he is not required by the law to do either one. If he wishes to do so, he may proceed with the work, treating the nonpayment as a mere*716 partial breach. He may get judgment for the amount that is due; or he may wait until completion and sue for the full price with damages for the delay in payment.”3
There is no doubt that a breach of a contract may be waived. The contract in this case called for payment ten days after each billing. However, the plaintiff accepted the first two payments which were made more than ten days after billing and the plaintiff continued to work steadily on the contract until the end of January even though defendant was seriously late in paying several billings. If failure to comply with the provision as to time of payment would have justified the plaintiff in rescinding the contract, this conduct could be considered a waiver of the right to rely on the delay in payments as a ground for rescission.
In Stolper Steel Products Corp. v. Behrens Mfg. Co.
“ ‘Even where time is made the essence of a contract, this provision may be waived by the party for whose benefit or protection it is inserted, either expressly or by extending the time for payment or performance or by granting indulgence to the other party in this regard; and when such a waiver has been made, he cannot arbitrarily and summarily declare a forfeiture of the contract for delay, but must first demand payment or performance and give the other party a reasonable time and opportunity, after such demand, to comply.’ ”
The defendant points out in his brief that the plaintiff never made written demand for payment, fixing a date after which he would consider the contract terminated. However, the Stolper Case does not state that such notice or demand must be in writing and the defendant’s brief
“. . . So too, the refusal of one party to perform an executory contract unless the other party consents to a modification, as distinguished from a mere request for a modification, amounts to a total breach of the agreement.”5
The plaintiff did not cite a demand for modification of the contract as a breach of the contract but rather alleged the failure to make payments as required by the contract as the breach on which the plaintiff based his refusal to continue.
We conclude that the evidence, viewed most favorably to the plaintiff, is not insufficient to support a verdict that the defendant had breached the contract between the parties by refusing to pay the periodic billings authorized by the contract.
Both parties in stating the question involved in their briefs refer to “substantial performance.” The doctrine of substantial performance
By the Court. — Judgment affirmed.
Quality Lumber & Coal Co. v. Kemp (1970), 46 Wis. 2d 621, 624, 176 N. W. 2d 401; Wallow v. Zupan (1967), 35 Wis. 2d 195, 198, 150 N. W. 2d 329.
13 Am. Jar. 2d, Building and Construction Contracts, p. 66, sec. 62.
3A Corbin, Contracts, p. 273, sec. 692.
(1960), 10 Wis. 2d 478, 487, 103 N. W. 2d 683, quoting from 1 Black, Rescission and Cancellation (2d ed.), p. 623, sec. 219.
17 Am. Jur. 2d, Contracts, p. 901, sec. 443. See also: Stolper Steel Products Corp. v. Behrens Mfg. Co., supra, footnote 4, at page 488; Richards v. Manitowoc & Northern Traction Co. (1909), 140 Wis. 85, 121 N. W. 937.
Kreyer v. Driscoll (1968), 39 Wis. 2d 540, 159 N. W. 2d 680, states that a dispensation in favor of the contractor on the theory of substantial performance should be granted in eases of incompleteness only when such details are inconsiderable and not the fault of the contractor.
See 3A Corbin, Contracts, p. 274, sec. 693, for remedies of the contractor when the owner breaches a construction contract.