Sam G. Polino & Co. v. State Road Commission
Opinion of the Court
On July 23, 1943, .the Monongah Construction Company entered into a contract with the state road commission to surface and stone base a certain project known as no. 3493-810; the road involved leading from Belington to Nestorville, in Barbour county, West Virginia; and covering a distance of approximately eleven miles. The contract, among other things, called for twenty-four thousand cubic yards of unclassified excavation; five hundred cubic yards of excavation for structures and approximately fourteen thousand four hundred cubic yards of knapped stone as the base course complete in place. The unclassified excavation was to be paid for at the rate of 40 cents per cubic yard. The excavation of the five hundred cubic yards for structures, including refilling, was to be paid at $1.50 per cubic yard. The fourteen thousand four hundred cubic yards of broken stone were to be supplied and put in place at the rate of $3.90 per cubic yard. Fourteen thousand four hundred cubic yards of knapped stone, complete in place, were to be supplied and placed at
The testimony shows that during the course of carrying on the project, which, as indicated, was rather extensive and entailed a large amount of excavating and material, there were many difficulties and disputes between the contracting firm and the road officials and supervisors, during which time some of the material was condemned and the contracting concern ordered to replace it; for certain reasons the excavating could not be carried out as originally planned and as shown on the plans and specifications, and the contracting firm alleges it was put to additional costs and expenses in carrying out the contract as changed and not provided for in the plans and specifications or the original contract itself.
Concerning these many disputes, the testimony is very conflicting. The claimant company maintains that it was obliged to do considerable extra work and furnish extra material not contemplated in any way by the contract. This contention, of course, is denied by the state department and we are there
By reason of the conflicting and uncertain testimony with reference to the many items for extra work, we have concluded to eliminate from our consideration all such items except two, which we feel are supported by a fair and impartial analysis of the testimony and should be paid.
The question of the widening of the berm beyond that contemplated in the contract and the plans and specifications, seems to be definitely settled; and the testimony, as shown by claimant’s witnesses and supported to a degree by the state’s witnesses, tends to show that there were 45,306 cubic yards of extra berm construction for which claimant was at no time paid and to which item he is entitled to remuneration at the rate of $.0424 per yard. There are admissions by the state’s witnesses that this extra berm construction was found necessary under the circumstances and conditions presented in carrying on the project, the only question being as to the amount of yardage involved and whether or not payment had been made. There is also testimony tending to show that by reason of the widening of the berm, the contracting firm was saved other expenses such as extra hauling, which would have been necessary had the berm not been widened to the width eventually established; however, when this matter is taken into consideration with the extra excavating that was found necessary, the claimant would be entitled in our opinion
Dissenting Opinion
dissenting.
In my judgment no additional compensation should be allowed for berm width over and above six feet on either side of the eighteen foot road, for the reason that all such additional width was contemplated and provided for by the specifications and settlement therefor was included in the final estimates. The six feet berm widths specified on the typical cross sections were merely minimum widths.
“The bidder is required to examine carefully the site of, and the proposal, plans, specifications and contract forms for the work contemplated; it will be assumed that the bidder has investigated and is satisfied as to the conditions to be encountered for performing the work as scheduled or as at any time altered without resulting in increases or decreases of more than the restricting percentage hereinafter stipulated, and as to the character, quality and quantities of work to be performed and materials to be furnished including increases and decreases, and as to the requirements of these specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered prima facie evidence that the bidder is satisfied as to all the conditions and contingencies.”
Paragraph 4 of the contract under which the work was done reads:
“(4) The contractor further agrees that he is fully informed as to all conditions affecting the work to be done, as well as to the labor and materials to be furnished for the completion of this contract, and that such information was secured by personal investigation and research and not wholly from the estimates of the Engineer; and that he will make no claim against the said State by reason of estimates, tests or representations heretofore made by any officer or agent of the State.”
It was the duty of Monongah Construction Company before submitting its proposal to the state road commission to go upon the ground of the proposed project and familiarize itself with all of the conditions found to exist there, and with the knowledge thus acquired to submit its bid for the work to be done. This is not only required by the specifications, which form a part of the contract, but is embodied in the contract itself. It must be assumed, therefore, that Monongah Con
I may add that I find no warrant in the record to sustain the award made for the 150 feet of pipe. There is qúite a difference between making a claim and proving if. Apparently little attention was paid by Monongah Construction Company or Sam G. Polino & Company, its assignee, to the specifications. It is as important to protect the interests of the state as the interests of the claimant.
I would disallow both of the items for which the awards are made.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.