Fisher v. State Board of Control
Opinion of the Court
In this proceeding claimant B. E. Fisher seeks to obtain an award against the board of control of West Virginia for the balance of money which he maintains is due to him under the terms and provisions of a certain written contract made and entered into by and between himself and said board, bearing date on the 30th day of October, in the year 1947, whereby he agreed to move six buildings then located at the TNT plant at Point Pleasant, West Virginia, to Lakin, West Virginia, and for the further sum of money claimed to be due and unpaid to him for furnishing additional material and doing extra work, not included in said written contract.
The facts developed upon the investigation and hearing of the claimant’s case may be briefly stated as follows:
The Lakin state hospital, an institution for the care and treatment of mentally ill persons of the negro race, is located at Lakin, West Virginia. The hospital was in need of further
This contract contams this provision: “The State Board of Control agrees to furnish as many as twelve prison laborers to dig ditches, footers, etc., if needed.” It further provided: “If this job be awarded me, work will start on or by November 5, 1947, and be completed on or by November 30, 1947. Unless the required materials can not be purchased immediately.” Work was begun within a reasonable time and the buildings transported from the TNT plant to Lakin hospital promptly and there placed upon locations designated by persons representing the board of control.
Due to conditions incident to world war II Fisher experienced much difficulty in obtaining necessary materials for use in the work and on this account progress was often slow. However, at all times when weather conditions were favorable and materials available laborers provided by Fisher were at work on the job. Fisher, himself, by reason of the state of his health, found it necessary to sojourn in Florida for a time. During his absence his representatives were proceeding with the work at the hospital premises. It is, we think, very satisfactorily shown that the board of control did not at any time furnish twelve prison laborers to do the work specified to be done by them in the contract. At no time were more than eight of these prisoners engaged in the work which they were sup
Under date of April 11, 1949, Joseph Z. Terrell, president of the board of control, addressed a communication to Fisher advising him that the written contract was being cancelled for reasons in said letter contained. No other or further payment was made by the board to Fisher under the terms of said written contract. The work provided by said written contract to be done by Fisher was performed by him, notwithstanding such delays as occurred from time to time in its necessary performance. In addition to such work as was done by Fisher under the contract in writing he did, at the special instance and request of officers and agents of the board of control, furnish the following material and did the following work:
15 Window Frames at $7.50 each .$112.50
15 Windows.-.— 119.38
Extra wiring on cafeteria . '... 93.30
Filling 500 cubic yards of dirt inside of building 500.00
Digging ditches, footers, etc. (which was intended to be done by prison labor) _ 250.00
It is apparent to the members of the court that the state has received the benefit of all of this additional work not required to be done under the written contract. The officers of the
In claim No. 534, LeRoy Roberts v. State Board of Control, 4 Ct. Claims (W. Va.) 235, we approved a claim for work done at Concord College for which payment had been denied by the board of control because of what was contended to be the absence of a contract duly authorizing such work. This claim was ratified by the Legislature and promptly and unhesitatingly paid by the auditor. In that case we held as follows:
“Pursuant to the purpose and spirit of the act of the Legislature creating the state court of claims, an award may be made for the payment of a claim against the state when the peculiar facts supporting such claim show it to be just and meritorious and for which the state has received distinct value and benefit.”
The confusion and misunderstanding which has caused so much trouble in this case is largely due to the fact that there have been too many bosses, and in the last analysis the fact remains that the state of West Virginia has received the benefit of the claimant’s work and should in equity and good conscience pay for it.
The president of the board of control could not arbitrarily terminate the board’s contract with Fisher, and the letter which he addressed to Fisher attempting to do so was wholly abortive.
Concurring in Part
concurring in part dissenting in part.
An award in the amount of $3,509.43 has been made by a majority of this court, said amount being for $2,434.25, the unpaid remainder of the amount fixed in claimant’s contract, plus $1,075.18, for additional material furnished and extra work done by the claimant. I can concur only in awarding the unpaid remainder of the contract price, plus $93.30 for extra wiring, $112,50 for window frames, and $119.38 for windows, or $325.18 of claimant’s bill for for additional material and extra work.
There are two items in claimant’s bill for additional material and extra work — $250.00 for digging ditches, footers, etc., and $500.00 for filling 500 cubic yards of dirt inside of buildings— which I hold are unjust claims for which the Legislature should not appropriate.
The testimony in the case shows that the claimant and one of his witnesses held that the prison labor promised in the contract did not dig all the ditches, while two witnesses for the respondent held that all the digging had been done by the prison labor. The determining factor against the ditch digging claim is the statement by the claimant’s plumber (r. p. 71) that what ditches had been dug by the prison labor, and the way they were dug, were not very good; that water had run
The majority members of this court have opined that the agreement of respondent to furnish prison labor “to dig ditches, footers, etc., if needed” obligated the respondent to furnish such labor in connection with filling 500 cubic yards of dirt needed as a base for concrete floor in one of the buildings. There is nothing in the record to show that claimant ever requested such labor in connection with the filling, and the record (p. 85) further shows that Thad Boggess, the claimant’s foreman, understood that the prison labor was supposed “to do such as digging sewer ditches, water, and footings around the buildings.” If there was any parol agreement under which the claimant was not expected to dig and haul the 500 cubic yards aforementioned, the evidence in the case fails to establish it.
For the reasons set forth, I dissent from that portion of the majority opinion allowing $750.00 for the two items — digging ditches and filling dirt — in claimant’s bill for additional material and extra work.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.