Haynes Construction Co. v. State Road Commission
Opinion of the Court
A contract was awarded to the claimant by the State Road Commission on April 28, 1960, for paving a segment of Interstate 77 in Jackson County, construction to begin within ten calendar days after the award and to be completed within 145 working days. The claimant immediately moved equipment and personnel onto the job, but was unable to start its paving operations. According to the claimant, the delay was entirely
At the completion of the claimant’s evidence, the parties requested a recess for the purpose of attempting to resolve the conflicts as to the time, quantities and costs involved in the claim. Thereafter, counsel for the parties announced that they had arrived at a settlement of their differences, and it was stipulated that the sum of $144,349.53 was justly due and owing to the claimant, being the sum of $134,081.70 for delay occasioned by the respondent and not the fault of the claimant, $9,717.83 for the increased expenditure for cement resulting from the delay, and $550.00 additional stockpile rental. All other claims were withdrawn or abandoned. The Attorney General of West Virginia concurred in the stipulation.
Upon consideration of the petition, the evidence adduced, the stipulation and statements of counsel, the Court is of the opinion that the claimant has presented a valid claim against the State of West Virginia within the jurisdiction of this Court, which in equity and good conscience should be paid, and, accordingly, it is the judgment of the Court that the claimant, Haynes Construction Company, should recover, and it is hereby awarded the sum of $144,349.53.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.