T&L-Wheeling Plumbing & Industrial Supply Co. v. Department of Public Institutions
Opinion of the Court
Claimant furnished building materials and supplies to the Department of Public Institutions of the State of West Virginia for use in the construction of a new wall at the State Penitentiary for the period beginning July 27, 1964, and ending October 19, 1966. For unknown reasons, the vouchers, copies of
It appearing that there remains due and unpaid on said account the sum of $2275.22, and that the Respondent has no objection to the payment of said claim, the Court is of the opinion that the Claimant is entitled to be compensated, and an award is accordingly made to it in the amount of $2275.22.
Claim allowed in the amount of $2275.22.