Cavanaugh Landscaping Co. v. Department of Natural Resources
Opinion of the Court
On October 26, 1965, the claimant, Cavanaugh Landscaping Company of Akron, Ohio, entered into a written contract with the respondent, Department of Natural Resources, to construct four golf courses at West Virginia State Parks, two at Pipestem State Park, in Summers County, one at Twin Falls State Park, in Wyoming County, and one at Canaan Valley State Park, in Tucker County, for the contract sum of $710,000.00 One paragraph of the contract provides the following: “The Contractor hereby agrees to commence work under this contract on or before a date to be specified in a written ‘Notice to Proceed’ of the owner and to fully complete the project by October 14, 1966, as stipulated in the specifications. The Contractor further agrees to pay, as liquidated damages, the sum of $100.00 for each successive calendar day thereafter as provided in Paragraph 19 of the General Conditions.” The contract further provides that no changes in the work shall be made without the written approval of the Owner, charges or credits to be determined by specified methods, and the claimant was emphatically warned that no additional costs could be paid for without a Change Order. The State of West Virginia issued a Purchase Order dated October 30, 1965, acknowledging acceptance of the claimant’s proposal dated September 27, 1965 showing the deletion of several Alternates and a base contract price of $710,000.00. The Notice to Proceed was given on January 28, 1966. Sundry change orders increased the total contract price to $762,399.80, and extended the contract time from October 15, 1966, to June 1, 1968.
The Department of Natural Resources denies that it owes the claimant anything and contends that any losses which the claimant may have sustained were due to the claimant’s own fault.
The State had no right to delay the Notice to Proceed indefinitely, for example, to the day before the completion date of the contract as suggested by counsel for the claimant, and if the delay was unreasonable, claimant would have been entitled to an extension of time. The claimant made much of its concern about the $100.00 per day penalty after the completion date, but the record does not disclose that it ever requested an extension, and, in fact, it appears that the eventual change order extending the time was initiated by the respondent. The clai
The Citizens Committee appointed by the Governor began its investigation in the latter part of December, 1965. They made several recommendations for changes in design at Pipestem. Work was suspended at Pipestem by an order of the Department from March 25, 1966 through May 23, 1966. According to the claimant’s testimony, extra costs in the amount of $20,750.00, resulting from design changes in pursuance of recommendations of the Citizens’ Committee, occurred in the months of July, August, September and October, 1966. The incongruity of the dates is not explained. By the letter of May 10, 1966, heretofore referred to, the claimant complained that it had not been paid $20,000.00 for work performed at Pipestem during the work stoppage period, and warned that if estimates were not paid, all work at Pipestem would have to stop and damages would be requested. In less than two weeks from the date of that letter, the order 'was given to resume work. Some of the recommended changes in design were made, but there is no clear showing that the claimant was damaged thereby. There is testimony to the effect that additional work was done, including additional grading, but no diary was kept, no payrolls specifically attributed to extra work, no measurements of dirt moved, and change orders were not requested. This was the only suspension of work ever ordered by the Department and it applied only to Pipestem, not to the other two State Parks. At least to some extent it appears that the Citizens Committee was more help than hindrance to the claimant, and the effort toward changing some of the design appears to have been a cooperative one. The Court is of opinion that the evidence adduced on behalf of the claimant is not sufficient to sustain the allegations of Item 2 (c).
Items 2 (b) and 2 (c) discussed above are typical of the remaining items of this claim. Items 2 (d), 2 (i), 2 (j), 2 (k), 2 (m) and' 2 (n) all involve alleged delay as the proximate cause of increased costs. The evidence, and frequently the lack of it, indicates that inclement weather and the claimant’s own failures substantially contributed to the claimant’s discomfort, inconvenience and financial loss.
Items 2 (e), 2 (f) ,2 (g), 2 (h) and 2 (1) involve claims of additional work and expense which, under the contract, could not be paid for without the prior approval of the Department and a written change order. This work was done without change orders, and without proof of extra work or demand for extra compensation.
Item 2 (g) complains of the failure of the Department to furnish adequate drainage. The contract did not require the State to provide drainage, but when during the course of the work it became apparent that certain drainage was necessary, a change order was requested and provision for drainage costing $27,399.80 was granted.
The fact that the claimant was unable to obtain copper wire at the time it was needed for the installation of the automatic draining system at Twin Falls and the resultant damage in the claimed amount of $42,000.00 cannot be attributed to any fault of the Department of Natural Resources. This alternate was clearly a part of the base contract and the responsibility for having to dig the ditch twice was a combination of a scarcity of copper wire, weather and bad judgment. The claimant did no more than it was required to do under the contract.
Damages to the claimant’s business and the loss of future profits claimed in Item 2 (n) are too remote and speculative to deserve serious consideration by the Court.
Obviously, this was not a happy or profitable experience for the claimant. The Court recognizes that the claimant sustained losses, some due to its own fault such as having to dig a ditch twice at an additional cost of $42,000.00, some as the result of
The Court is of opinion that the claimant has not proved its case by a preponderance of the evidence, and, accordingly, this claim is disallowed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.