Charleston Construction, Inc. v. State Road Commission
Opinion of the Court
Charleston Construction, Inc., the claimant, filed a claim in the amount of $2,412.19, with interest thereon from July 1, 1965, arising from work done on Project 1-64-160 (10) in Cabell County. The respondents have filed no Answer, and the case is submitted on a stipulation admitting the facts and the amount of damages as alleged in the Notice of Claim. The Construction Agreement has not been made a part of the Record and the facts are sketchily presented.
It appears from the stipulation that the claimant at approximately 1:45 P.M. on June 30, 1965, received a shutdown letter from the Project Supervisor of the State Road Commission suspending its work as Contractor on the Project on the ground that the sand used on the Project did not meet specifications.
The Contractor contends that it should be compensated for equipment rental sustained during the period of shutdown, the show-up time paid for the men during the delay, and for the time and equipment used in re-handling the sand, as well as for the material lost in re-handling.
The Specifications of the State Road Commission provide that materials failing to meet the requirements of these Specifications shall not be used, and that the Contractor shall furnish samples when required. All materials are to be approved before being incorporated in the work. The duration of the suspension of the work because of the defective laboratory tests was from 1:45 P.M. on one day until 11:00 A.M. of the next day. The prosecution of the work was delayed for a very short period of time, and even if we assume that the respondents were guilty of
It is the opinion of this Court that the claimant is entitled to reasonable compensation for any damages resulting from the improper isssuance of the shutdown order, but only for such damages as are the direct and proximate consequence of the shutdown order.
The unnecessary and additional stock piling of the sand in the hope that specification sand could be found appears to have been done in good faith and should be a proper item for compensation. Therefore, the claim for moving stock piles is allowed in the amount of $625.68. The equipment rental loss representing rental of various items of equipment on the job for an eight-hour period, in the opinion of this Court, is not com-pensable, as the equipment was already installed on the Project and could not have been removed and put to profitable use elsewhere and returned to the Project within the short duration of the temporary suspension. The equipment rental is an item of overhead that the Contractor would be required to pay whether or not the work had been suspended. This item in the aggregate amount of $1,166.24 is disallowed because of the minimum duration of delay. The State Road Commission has the discretion to suspend work if it deems it to be for the best interests of the State.
The show-up item claimed for the men who were ordered to return to work on July 1st, and sent home after another sample was taken, which failed to meet specifications, is allowed in the amount of $137.62, as a proximate item of damage. The cost of the sand wasted because of the re-handling of the material in a quantity of 197 tons, the stipulated amount, is allowed in the amount of $482.65, as a proper item of damage.
The Court is of the opinion, therefore, to award the claimant the sum of $1,245.95, said sum representing the aggregate of the above mentioned items allowed as damages for the erroneous temporary suspension of the work. It is the further
Claim allowed in the amount of $1,245.95.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.