C & D Equipment Co. ex rel. First National Bank of South Charleston v. State Building Commission
Opinion of the Court
The claimant, C & D Equipment Company, a corporation, filed its Notice of Contract claim against the respondent, the State Building Commission of West Virginia, a public corporation created under the laws of the State of West Virginia, with powers and duties conferred upon it by Chapter 5, Article 6 of the official Code of West Virginia, seeking to recover the sum of $48,340.36. The case was submitted on a Stipulation of Facts and only legal questions relating to the interpretation of the Contract are presented to this Court for determination.
The following is the factual situation as revealed by the Record. The State Building Commission was created for the construction of public buildings for specified purposes with powers to contract and acquire by purchase or otherwise real property necessary for its corporate purposes and to exercise the power of eminent domain to accomplish such purposes. The Commission is also authorized to construct buildings on real property which it may acquire in the City of Charleston, and issue State Building Revenue Bonds to finance the costs of its projects. Prior to the 29th day of December, 1967, the State Building Commission decided upon and did commence the acquisition of property for the erection and construction of
The delay of the State Building Commission to make 'available the structures is charged as a breach of its contract. The claimant was required to raze a structure in one area and move to an entirely different location to demolish another structure, completely disrupting its plans to execute the Contract according to a schedule of operations as contemplated by the parties, thereby causing the plaintiff to spend an additional sum of money for the rental of equipment, labor and for the idleness of its own equipment and other costs and expenses over and above the Contract price, making a total claim of $48,340.36.
The claim for damages and extra compensation, with supporting data and affidavits, was thoroughly investigated by the State
In order to finance the work, the claimant assigned the money it was to receive under the Contract to The First National Bank of South Charleston, which Assignment was accepted by the State Building Commission.
The claimant’s contention is that it is entitled to recover damages for the delayed release of structures for demolition in violation of a contemplated sequence of operations which would have enabled the contractor to do its work efficiently and economically. The State’s contention admits the authorized payment to the claimant of $29,907.68 as additional compensation for damages and extra work, but denies any legal obligation to the claimant.
An examination by this Court of all the contract documents, including the specifications, bid proposal and all the circumstances surrounding the project, reveals that the contractor relied upon an orderly, efficient and business-like release of the structures for demolition. In our opinion, it cannot be seriously contended by the respondent that when a completion date is specified for designated structures not
In view of the foregoing, we are of the opinion that this is a legal claim which the State in good conscience should pay for failure to perform its part of the Contract in a reasonable and proper manner. If the State, for reasons beyond its control, was unable to make structures available for timely demolition, it should have exercised its right set forth in the Contract documents, to eliminate from the project such structures as were not available for demolition.
For the reasons stated herein, the Court is of opinion to award claimant the sum of $29,907.68.
Claim allowed in the amount of $29,907.68.