Edward L. Nezelek, Inc. v. Department of Finance & Administration
Opinion of the Court
Pursuant to the provisions of West Virginia Code, Chapter 14, Article 2, Sections 13 (3) and 18, Miles E. Dean, Commissioner of the Department of Finance and Administration, has filed a petition seeking an advisory determination respecting the claim of Edward L. Nezelek, Inc., a corporation, based upbn the following facts.
By a duly executed purchase order dated August 20, 1976, the Department of Mental Health (now the Department of Health) entered into a contract with Nezelek by which Nezelek became obligated to complete the first phase of construction of a Central Mental Health Complex near Pocatalico in Kanawha County for the sum of $5,851,000.00. The total cost of the project was estimated to be $25,000,000 to $30,000,000 excluding the cost of necessary roads and bridges. It is undisputed that the parties entered into the contract in good faith. The contract provided that it was to be performed within 470 working days after August 20, 1976. Several months later, an administrative determination to the effect that the contract should be cancelled was made, and that determination was communicated to Nezelek by letter dated March 4, 1977, from Mr. Dean. The reasons assigned for such determination were: that the isolated location of the complex was not suitable for its intended purpose and was in conflict with the concept of community health centers that were being constructed in other parts of the state: that the location was not served by water, sewer, or other utilities; that the location was not served by a public means of transporta
“A contractor under a building contract who, after having performed a portion of the contemplated work, is prevented from completing the same by the owner, or is justified in his abandonment thereof by the owner, may recover not only the value of the labor and materials bestowed upon the property and expenses necessarily incident to the work done and provided for in the contract, but also such profits as he could have made if he had been permitted to complete the work.”
The Court does not have before it all of the facts necessary to apply that measure to this case, but it certainly appears prob
Case-law data current through December 31, 2025. Source: CourtListener bulk data.