U.S.A.A. Insurance v. Department of Highways
Opinion of the Court
The claimant, Harold F. May, filed this claim in the amount of $184.89 against the respondent for damages to his 1977 Monte
Doyle Thomas, the respondent’s foreman for the area in question, testified that surface material could not be applied to a highway during a rain or when the road was wet. He identified his daily time sheets for August 22, 23, 24, 25, and 26, 1977. These sheets, which were introduced as Respondent’s Exhibit No. 1, reflect the type of work performed, equipment used, and the location of the work for each day. The sheets revealed that no work was performed by the respondent on W.Va. Route 6/6 on any of the days covered by the sheets introduced.
From the record, the Court is of the opinion that the claimant has not shown by a preponderance of the evidence that the damages sustained were the result of actionable negligence on the part of the respondent. Accordingly, the claim is disallowed.
Claim disallowed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.