A. J. Baltes, Inc. v. Department of Highways
Opinion of the Court
The claimant filed its claim for an equitable adjustment against the respondent in the amount of $1,393,814.53 for costs incurred in the execution of its contract with the respondent, which costs were due to excessive and unforeseen subsurface material that was unsatisfactory for use as embankment foundation.
The claimant was the successful bidder on respondent’s project 483(15). This project was for the construction of a portion of what is now Route 48, and covered approximately 2 1/2 miles of road in the mountains of Preston County, West Virginia, in the vicinity of Cooper’s Rock State Forest near Morgantown.
It was contended by the claimant that the site conditions indicated in the contract differed materially from the conditions actually encountered in three areas designated “claimed areas”. These areas were identified at the hearing as:
(1) from station 149a50 to 154a50, for a distance of 1500 ft.
(2) from, station 228a50 to 240a00, for a distance of 1150 ft.
(3a) from station 251a50 to 262a00, for a distance of 1050 ft.
(3b) from station 262a50 to 268a50, for a distance of 600 ft.
The claimant encountered unforeseeable subsurface conditions and material. The material was not suitable for embankment foundation. In order to reach rock or shale base, it was necessary to excavate to a greater depth and over a greater length than that indicated in the contract. The excavation to a greater depth resulted in costs not anticipated in the bid price. An increased amount of subsurface water was encountered, which required continuous pumping of the water from the claimed areas. High production equipment could not be used to its best advantage in the congested area. Additional equipment was required, and it became necessary for bulldozers to push hauling units out of the claimed areas when such units were unable to move under their own power. These factors interrupted the claimant’s planned schedule.
The claimant contends that the difficulties encountered entitled it to an upward equitable adjustment in the contract price under the terms of the “changed condition clause” or the “differing site condition clause” in Section 104.2 of the Standard Specifications of 1968. This section provides in part:
“Should the Contractor encounter or the Commission discover during the progress of the work subsurface or latent physical conditions at the site differing materially from those indicated in the contract, or unknown physical conditions at the site of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract, the Engineer shall be notified in writing of such conditions; and if the Engineer finds the conditions do materially differ and cause an increase or decrease in the cost of, or the time required for performance of the contract, an equitable adjustment will be made and the contract modified in writing accordingly.”
The respondent relies on another portion of Section 104.2 of the Standard Specifications of 1968, which provides:
*3 “The Commission reserves the right to make alterations in the Plans or in the quantities of work as may be necessary or desireable at any time either before or during the work under the Contract. Such alterations shall not be considered as a waiver of any conditions of the Contract nor invalidate any of the provisions thereof, provided such alterations do not decrease or increase the total cost of the project more than twenty-five percent, based on the original Contract quantites and the unit bid prices, and provided further that such alterations do not result in an increase or decrease of more than twenty-five percent in quantity of any one major Contract item
The difference between the original bid quantity of unclassified excavation and the quantity excavated was 4.4 percent. The respondent contends that since the above-quoted section requires a material difference of more than twenty-five percent in the quantity of a major item before there can be an adjustment in the contract price, the claimant is not entitled to an equitable adjustment.
Regardless of the fact that the quantity excavated was only 4.4 percent in excess of the original bid quantity to be excavated, the Court finds that a changed or different site condition existed. The crux of this claim is not the quantity of that excavated, but rather, the additional expenses required by the changed conditions not anticipated in the contract. The claimant had the right to rely upon the plans furnished by the respondent, and the plans should have been corrected to compensate for the extra expense incurred.
According to the Standard Specifications, and under the terms of the contract, the claimant was required to give the Engineer written notice that it intended to make claim for additional compensation in the form of an equitable adjustment due to differing site conditions. The contract further provides that such notice shall be given before work is commenced in the claimed area so that the Engineer is afforded the opportunity for keeping strict account of the actual cost. Failure to comply with this provision under the contract is to be considered a waiver by the claimant or contractor of any claim for additional compensation.
In this case, the claimant gave written notice by letter dated June 15,1971, and received by the respondent on June 17,1971. This was approximately two months after the claimant contends it encountered differing site conditions. John W. Baltes, of the
By reason of the changed site condition, the claimant incurred extra expense not contemplated under the contract. The claimant, in support of its claim, contends that it incurred additional expense and time in the following areas:
1. Additional cost of excavation and embankment construction.
2. Additional cost of excavation and equipment standby.
3. Additional cost of concrete paving equipment standby.
4. Additional cost of support equipment.
5. Additional cost of construction, maintenance, and removal of ramps and hard roads.
6. Additional cost of pumping and dewatering.
7. Additional cost of select rock fill.
8. Additional cost of drainage work.
9. Additional cost of work performed in 1973 due to price increases.
10.Additional cost of financing the added costs incurred in connection with performance of the contract.
Before discussing the claimed items of damages, it is necessary that the Court consider the motion made by the claimant at the close of the testimony that, in the event the Court found a changed condition did occur, the parties be permitted to negotiate the matter of the quantum of recovery, which motion the Court sustains, subject to the guidelines herein set forth. It is the opinion of the Court that all matters claimed by A. J. Baltes, Inc. are not recoverable, and consideration must be given to applicable laws governing recovery under a changed conditions clause.
Based upon the record, the Court is of the opinion that the respondent was not negligent in the preparation of boring data or other design specifications provided to all bidders on the project, nor that the respondent intentionally misrepresented anticipated subsurface conditions. In support of the claim for delay-caused damages, the claimant relies heavily upon the cases of Nolan Brothers, Inc. v. United States, 437 F.2d 1371 (1974), L. L. Hall Construction Co. v. United States, 379 F.2d 599 (1966), and Laburnum Construction Corp. v. United States, 325 F.2d 451 (1963). In each of the above cases, damages resulting from delays were recoverable when it was shown that the government was responsible for the delay. Recovery for damages due to idle equipment was allowed in Nolan, supra, when the government terminated the contract for its own convenience. In Hall, supra, the
In the case of Jefferson, supra, the government prepared design specifications based upon fifteen borings conducted at the project site. These proved to be erroneous, and resulted in substantial undercutting and delays. After being awarded an equitable adjustment based upon the “Rice doctrine”, the plaintiff sought recovery for delay-caused damages. In denying recovery, the court held that:
“In the absence of proof of some act or omission from which we can deduce that defendant is at fault we cannot conclude that there has been a breach within the Laburnum exception and, therefore, recovery is limited to the remedies provided for under the contract.” Jefferson, supra, at 1015.
In the instant case, we are presented with a claim for an equitable adjustment as provided for by the contract rather than a breach of contract action wherein the government is shown to be at fault or for recovery for a governmentally induced unreasonable delay. Respondent is liable for such damages only when it is shown to be responsible for the complained of delays. Accordingly, the claimant cannot recover damages from delays not caused by the respondent.
In determing the amount of recovery under a “changed conditions clause”, there are two standard techniques for demonstrating cost incurred as a result of the unanticipated condition. The first method, or “actual cost” theory, is based on a daily cost analysis of the additional expenses required by the changed condition.
The second method of computation is the difference between what it cost to do the work and what it would have cost if the
The recoverable items of cost must be realistically confined to the additional cost incurred by the claimant, and which were directly and proximately caused by the changed conditions. Expenses which the contractor would have been required to expend in any event had no changed condition occurred are not compensable as part of an equitable adjustment. Dale Ingram, Inc. v. United States, 475 F.2d 1177 (Ct. Cl. 1973).
Undoubtedly, the unanticipated condition caused expense to the claimant not contemplated in the original contract bid price. The claimant was required to excavate at substantially greater depths than indicated in the contract and at a substantial increase in both labor and equipment costs. This excavation was performed in narrow valleys caused the claimant to change radically the normal method of operation and to adopt more expensive and specialized methods of work. Continued excavation necessitated a constant flux of establishment and relocation of haul roads and ramps. Water conditions at the base of the excavations required unanticipated and costly pumping and drainage operations. In view of the conditions encountered, the claimant was forced to utilize a select rock fill at increased labor and equipment costs. All of the above are recoverable costs directly attributable to the changed condition and should be included in an equitable adjustment. Care must be taken to avoid duplications and overlaps, and recovery limited to those damages which claimant can prove to have been directly and proximately caused by the changed condition. In particular, the evidence concerning additional equipment appeared suspect. As the court in Lowder v. North Carolina State Highway Comm’n., 217 S.E.2d 682, 700 (1975) noted:
*8 “To report that 36 machines are on a job site on a given day is unsatisfactory. It would be better practice to report not only the number of machines on the job, but also the number of machines operating, the task each performs, and the length of time each operates. The product of that kind of record keeping is more likely to bear the earmarks of reliability.”
Judgment decisions by the contractor to stockpile equipment on the job site do not necessarily constitute costs recoverable under an equitable adjustment.
In each of the claimed items of damages, the claimant has include a 9% allowance for overhead, a 10% allowance for profit, and a 2% allowance for anticipated Business and Occupation taxes. This Court has recognized the validity of awards for overhead and Business and Occupation taxes. Baker & Hickey Co. v. State Road Comm’n., 7 Ct. Cl. 195 (1969). However, the courts are divided over whether profits are properly considered in determining the amount of the equitable adjustment. The Court is of the opinion that an equitable adjustment entitles the contractor to compensation for those expenses directly resulting from the changed condition, but not to a profit on the additional work. The primary purpose of the equitable adjustment is to protect the contractor from the risk of loss, and therefore, may be properly viewed as a recovery in quantum meruit.
The claimant claims damages occasioned by additional financing costs due to the changed conditions encountered. Admittedly, claimant is aware of that portion of West Virginia Code 14-2-12 which states that:
. .In determining the amount of the claim, interest shall not be allowed unless the claim is based upon a contract which specifically provides for the payment of interest.”
The claimant, however, urges this Court to consider a virtually identical Federal statute and a few cases decided by the United States Court of Claims allowing recovery of interest on finance charges on contractor loans. In his pre-trial brief, the claimant cites the cases of Bell v. United States, 404 F.2d 975 (1968) and Phillips Construction Co. Inc. v. United States, 374 F.2d 538 (1967) in support of his claim. The court in Bell upheld the practice of the Armed Services Board of Contract Appeals of allowing such recovery. This practice was initiated by a Department of Defense policy change in 1954 which departed from the long standing
In the instant case, the contract does not provide for the recovery of interest, and this Court by statute lacks jurisdiction to award interest, and therefore denies recovery of interest and finance charges.
As discussed above, two of the elements of an equitable adjustment under a “changed conditions” clause are the non-assessment of liquidated damages for delays directly resulting from the unanticipated condition and a reasonable extension of time in which to complete the required project when the claimant encountered the unforeseen subsurface condition, substantial excavation in excess of contract indications was necessitated. The additional time required to excavate to a suitable base caused interruptions to the claimant’s projected work schedule and resulted in a delay in the overall completion of the contract. Without prejudice to its contention that a “changed condition” under Standard Specification 104.2 had not yet been encountered, the respondent granted the claimant additional work days based upon the number of days the claimant actually spent on the fill bench areas in excess of the scheduled date of completion. While claimant contends this method of computation is inaccurate, the Court finds that this extension was reasonable.
Obviously, there was a direct causal relationship between the additional work required by the changed conditions and the overall delay in the completion of the project. However, it appears
The Court directs that the parties consider the findings herein, and at the approximate time not to exceed 120 days from the date of this opinion, file their recommendations for the amount of recovery for the approval of this Court.
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
A. J. BALTES, INC., a Corporation,
Claimant,
vs.
THE WEST VIRGINIA DEPARTMENT OF HIGHWAYS, et al.,
Respondents.
Claim No. D-1002
ORDER AND RECOMMENDATION
This day came A. J. Baltes, Inc., a corporation, Claimant, by James R. Watson, its Attorney, and came the West Virginia
It is hereby jointly recommended by A. J. Baltes, Inc., Claimant, and The West Virginia Department of Highways, et al., Respondents, that the Claimant is entitled to recover from the Respondents, the following sums of money on the following items:
I.EXCAVATION AND EMBANKMENT COST
A.Excavating and Select Rock Fill Placement Cost in “Claimed Areas”.$585,369.83
B. Labor and Equipment Cost for Blasting for Select Rock Fill in “Claimed Areas”.$81,633.02
C. Explosives Cost for Blasting Select Rock Fill for “Claimed Areas” .$32,106.32
Total Actual Cost for Excavation and Select Rock Fill Embankment in “Claimed Areas” .$699,109.17
II. IDLE EQUIPMENT STANDBY
From Date Equipment First Used Until 6/1/71.$42,374.03
III. OTHER ACTUAL COSTS
Including Haul Roads, Pumping, Dewatering and Drainage on Pipe Washout.$36,879.32
TOTAL ACTUAL COST FOR WORK IN “CLAIMED AREAS” .$778,362.52
IV. ADJUSTMENTS
A. Adjustment to total actual cost for payments made at unit bid price based on planned quantities of fill bench excavation between 3/1/71 and 10/31/71 .$154,032.34
TOTAL ADJUSTED ADDITIONAL COST DUE TO DIFFERING SITE CONDITIONS .$522, 356.49
V. PAYMENT FOR PRIOR DISALLOWED QUANTITIES
A. Waste
14,206 cubic yards were wasted from below template excavation near Sta. 237 after April 5, 1971.$12,501.28
B. FAT FILLS
Initially the Respondents disallowed 58,663 cubic yards but based upon the Court’s Opinion in the case styled Vecellio & Grogan, Inc. vs. Department of Highways, the Respondents have agreed to compensate the Claimant for 36,471 cubic yards .$46,813.96
VI. LIQUIDATED DAMAGES IMPROPERLY ASSESSED.$6,600.00
TOTAL RECOMMENDED AWARD .$588,271.73
It is further agreed by and between the Claimant and the Respondents hereto that all other items of claim and parts of items of claim not agreed to be paid in this recommendation, as set out and alleged in Claimant’s Notice of Claim filed in this action, are to be disallowed and not considered by the Court for any award and are to be dismissed.
Upon consideration of the Claimant’s and the Respondents’ representations, the Opinion of the Court heretofore filed in deciding the subject claim and the recommendation set out aforesaid, the Court is of the opinion to and does sustain the same and the same are hereby received, filed, and accepted; and it is hereby further ordered that the Claimant be and it is hereby granted an award against the Respondents in the total amount of Five Hundred Eighty-eight Thousand Two Hundred Seventy-one Dollars and Seventy-three Cents ($588,271.73).
Entered this 24th day of January, 1980.
John B. Garden
Judge
APPROVED BY:
A. J. BALTES, INC., a Corporation,
By James R. Watson Its Counsel
WEST VIRGINIA DEPARTMENT OF HIGHWAYS, et al.
By Stuart Reed Waters, Jr.
Their Counsel
Case-law data current through December 31, 2025. Source: CourtListener bulk data.