Paramount Pacific, Inc. ex rel. Pauley Paving Co. v. Department of Highways
Opinion of the Court
Paramount Pacific, Inc., was the general contractor for the construction of a bridge on Interstate Route 77 in Mercer County. Pauley Paving Co., Inc., as a subcontractor, paved the bridge deck in June, 1972. The respondent, acting under Section 1.5.9 of the Specifications, subsequently required the removal and replacement of a section of the deck because the concrete used in it did not meet specifications. The claimant asserts that the concrete did meet specifications, that the respondent’s action was arbitrary and unlawful or that, at most, must less expensive corrective action should have been required. The amount of the claim is $81,460.03 that being Pauley’s computation of the cost of removal and replacement.
During the trial, it was conceded by Pauley that the amount of its claim should be reduced by the cost of replacing a 12’ x 12’ area occupied by the cold joint (estimated at approximately $2,000.00) and by the cost of scoring or grooving the surface area which had been watered (710 square yards at $4.00 per yard). It also was agreed that the sum of $81,460.03 inadvertently had included $2,385.49 for extra work for which Pauley had been paid. In addition, that sum included a charge for idle equipment (a crane, a back hoe and a pick-up truck) and, for overhead, taxes, etc., an addition of 30% on labor, 20% on materials and 10% on equipment was included.
Although Mr. Welsh initially undertook to place the blame for the concrete problems upon the refusal of respondent’s engineer, Michael Ward, to permit the addition of water to the concrete up to
“There was so much conversation going on that day, and when the concrete came so dry there was a lot of excitement. In fact, everybody was pretty well in turmoil.”
Under Section 1.5.7 of the Specifications, no action by a state inspector (be he engineer or otherwise) can relieve a contractor of his duty to perform his work in accordance with plans and specifications. And, under Section 1.5.9, removal and replacement of defective work or material properly can be required. In view of all of the evidence, in this case, the Court cannot find that the respondent acted either arbitrarily or unlawfully. Accordingly, this claim must be denied.
Claim disallowed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.