McAnallen Bros. v. Board of Regents
Opinion of the Court
McAnallen Brothers, Inc., had a contract with the respondent, Board of Regents, for construction of a natatorium at West Virginia University. A part of that contract provided for the construction of a sanitary sewer. This claim is for the cost incurred by the contractor for extra work performed in
The record in this claim establishes that the contractor began construction on the sanitary line and within a week’s time encountered sub-surface hard rock similar to granite. The contractor attempted to use mechanical means to break the rock but soon resorted to the use of dynamite with the permission of the respondent’s field inspector. This method proved to be too time consuming to the contractor so the architect was requested to assist the contractor by redesigning the sanitary line. The architect complied with the contractor’s request by redesigning the line so as to raise the elevation, and alter the direction and ultimate length of the line. The contractor then constructed the sanitary line according to the redesign.
The architect for the respondent, William Hartlep, testified that the rock encountered by this contractor “is blue limestone which is nearly as hard as granite and very, very rare.” He further testified that the borings did not disclose this subsurface condition “because it’s a very isolated small area and I can’t explain it because it’s a freak occurrence of stone in that area. It’s one in a hundred shot that it would be there.”
The record in this claim establishes that an unanticipated sub-surface condition existed on the project and this condition caused the contractor to incur extra expense in the amount of $20,228.00 for which the contractor is entitled to be compensated. C. J. Langenfelder & Sons, Inc. v. State Road Commission, 8 Ct.Cl. 193 (1971). The Court, therefore, makes an award to the claimant in the amount of $20,228.00.
Award of $20,228.00.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.